  • Chorus SO#

  • ENS Job#

  • Conducted on

  • Prepared by

  • Location
  • Are workers on site or is this a completed installation?

  • Personnel

NGA.01 Inventory Data Correct

  • 110.050 | Inventory database updated

NGA.02 Closure Labelling Correct - inc Data Card

  • 110.051 | Network labelling correct at AOFDF and log completed

  • 110.052 | FFP Cabinet data card completed in pencil. ABF- microduct #, splitter and splitter leg, FF - splitter and splitter leg

  • 110.053 | ONT - All ONTs labelled with 'SLID' number - schools, commercial, locations with multiple services

  • 110.054 | Fibre closure customer trays labelled

NGA.03 Correct SOW Code Claimed

  • 110.055 | Correct Statement of Work codes used

NGA.04 Solution Tested and Working

  • 110.056 | Techmate tests completed at install.

NGA.05 Correct CSE Followed

  • 110.057 | Contractor appearance/manner/service completion card left (customer view)

  • 110.058 | Customer ring before arrive/Technician called ahead

NGA.06 Site Tidy, No Task waste

  • 110.059 | Site tidy, no task waste - Customer/Business Premises

  • 110.060 | Site tidy, no task waste - exchange

  • 110.061 | Site tidy, no task waste - outside plant

NGA.07 No Fibre Task Waste/Fibre Shards

  • NGA.07 No Fibre Task Waste/Fibre Shards

NGA.08 Permanent Reinstatement Completed to Standard

  • 110.063 | Ground reinstatement completed

NGA.09 External Pathway to FTP Installed Correctly

  • 110.064 Codes | Decision tree applied for correct lead in method

  • 110.065 Aerial Service Lead | Unused copper aerial lead removed

  • 110.066 Aerial Terminal | Aerial Lead-in managed and entry correct

  • 110.067 Aerial Terminal | 20mm or 32mm conduit secured to pole (wooden – galvanised saddles for white PVC pipe, plastic saddles for grey/beige 32mm HDPE pipe, secured with clouts or bandit straps.  600mm spacing)

  • 110.068 Pedestal | Pedestal microduct connectors installed in vertical positions only

  • 110.069 Aerial Service Lead | Correct aerial Service Lead used

  • 110.070 Aerial Service Lead | Correct aerial fittings used and installed correctly (screw eyes, clamps, pole and buildings)

  • 110.071 Aerial Service Lead | Pipe on poles, secured correctly

  • 110.072 Aerial Service Lead | Roadway crossing at correct height

  • 110.073 Aerial Service Lead | Correct procedure followed to extend 4/7 way up pole

  • 110.074 Buried Service Lead | Service Lead terminated correctly

  • 110.075 Buried Service Lead | Correct type of pipe above ground level

  • 110.076 Buried Service Lead | Depth correct

  • 110.077 Buried Service Lead | Correct surface mount fastenings used/spacing to suit surface,. Spacing max 600mm supported, 300mm unsupported

  • 110.078 Buried Service Lead | Copper locate installed with fixed fibre lead in if not installed with existing copper

  • 110.079 FAT | Slack Managed in fibre management coil (1.5 - 2m) FAT

  • 110.080 Boundary Connection | 1-Way connected correctly at boundary

  • 110.081 Boundary Connection | Cover board installed at boundary prior to reinstatement

  • 110.082 Hand Hole | Customers' S/way duct managed round edge of handhole

  • 110.083 Hand Hole | Handhole joint installed correctly between lateral and service lead

NGA.10 FTP Installed Correctly

  • 110.084 ETP | Correct ETP installed, tidily and secure

  • 110.085 ETP | Heat shrink splice protectors secured from movement

  • 110.086 ETP | Gas block connector installed correctly on the microduct

  • 110.087 ETP | Sufficient metallic location element left for locate purposes

  • 110.088 ETP | Micro duct held in position with zip tie or integrated saddle within ETP

  • 110.089 ETP | Lid secured and laser label positioned externally on the lid

  • 110.090 ETP | Unused copper pairs are capped with clearing connectors

  • 110.091 ETP | Fibre managed correctly

  • 110.092 ETP | Min 5mm hybrid cable sheath inside ETP

NGA.11 Internal Pathway Installed Correctly

  • 110.093 ETP | Pipe or flexi duct fitted to building is secured and managed correctly

  • 110.094 Customer Premises | Correct cable used, secured correctly and tidy

  • 110.095 Customer Premises | Correct clearances observed

NGA.12 Building Penetrations Watertight and Fireproofed

  • 110.096 ETP | Cable entry to building sealed

  • 110.097 BUDI | Fire and smoke barriers installed/reinstated

NGA.13 ONT and ITP Installed Correctly/Wiring Integrated

  • 110.098 Customer Premises | ONT installed and secured correctly, at least 300mm above the floor. Pigtail secure

  • 110.099 Customer Premises | Min 10mm hybrid cable sheath inside ONT

  • 110.100 Customer Premises | ITP installed on hybrid copper cable at ONT and labelled correctly

NGA.14 Fibre Management Within Closure Correct

  • 110.101 FFP Cabinet | FFP Cabinet - ABFU managed correctly and secured in tube with strain bung

  • 110.102 FAT | FAT - Fibre correctly managed within FAT and trays

  • 110.103 FAT | FAT - Heat shrink splice protectors secured from movement

  • 110.104 GLC | GLC - All microducts secured into management brackets

  • 110.105 GLC | GLC - Fibre routed and laid up correctly in tray

  • 110.106 Flash 9 | Flash 9 - Fibre routed and laid up correctly in trays

  • 110.107 BUDI | BUDI - Fibre routed and laid up correctly in tray. All unused connectors capped

NGA.15 Correct Sealing Practices Completed at Closure/FFP

  • 110.108 FFP Cabinet | FFP Cabinet - ABFU managed correctly and secured in tube with strain bung

  • 110.109 FAT | FAT - Silica Gel Pack installed/replaced

  • 110.110 FAT | FAT - All Latches are closed - ports blocked/sealed

  • 110.111 Flash 9 | Flash 9 - All populated Microducts fitted divisible seal. Unused fitted with strain relief plugs or end stops

  • 110.112 Flash 9 | Flash 9 - Closure base 'O' ring clean, dry undamaged & correctly seated. Spare 'O' ring in closure

NGA.16 Network Elements Secured

  • 110.113 Work Areas & Safety | Network elements secured

  • 110.114 Aerial Terminal | Aerial Terminal lid secure

  • 110.115 Pedestal | Pedestal straight and secure

  • 110.116 FAT | FAT Swing Arm and bracket in working order / or mounted on manufactured bracket

  • 110.117 FAT | FAT chamber Lid Locked and lock bung installed

  • 110.118 Hand Hole | Hand hole locked, with lock facing the Customer Boundary and openable

  • 110.119 GLC | GLC Lid secure

NGA.17 Optical Patch Cords Correctly Managed

  • 110.120 AOFDF | AOFDF - Optical cables & cords adequately managed within racks and shelves

  • 110.121 AOFDF | AOFDF - Protective caps on all unterminated connectors

  • 110.122 FFP Cabinet | FFP Cabinet - All unused connectors capped

  • 110.123 FFP Cabinet | FFP Cabinet - Allocated splitter leg routed over mandrel into correct tray position

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.