Title Page
-
Conducted on
-
Prepared by
QUIZ
-
Question 1: What should we do before authorizing a contractor’s intervention on a dock leveler platform?
- a. Check that the contractors has risk assessment for the works to perform and has fulfilled all the access control requirements.
- b. Coordinate previously to the works with Operations to ensure lack of impact from both parts and organize Permit to Work.
- c. A & B are correct.
-
Question 2: Why are permit to work (PtW) so important?
- a. Permits to work are a formal management system used to control high-risk activities as part of the control safety measures. These enable an assessment of risks to be made and to specify control measures, which will be put in place in order to minimize the risk.
- b. Permit to work is the minimum requirement that proofs an individual is trained to carry out specific jobs.
- c. Permit to work is not important.
-
Question 3: Who is authorized to perform LOTO?
- a. Operation Supervisor
- b. Shift Manag
- c. Anyone who performed LOTO KNET-training
- d. Only the RME or technician maintenance people who received appropriate training
-
Question 4: What should I do if an emergency stop does not work on a conveyor?
- a. We can work if the others emergency stop are functioning.
- b. We have to stop the conveyor with a functioning e-stop, and ask for RME.
- c. Technician maintenance people to apply LOTO procedure.
-
Question 5: Can I apply LOTO without removing “air pressure”?
-
Question 6: The Permit to Work for routine activities can be signed only by external contractors without the formal approval of OPS or RME or WHS.
-
Question 7: Is it required to implement access control requirements for contractors before grant their access to our sites?
- a. Yes, hiring justification, workers, ID and RightCrowd and provide the basic information about the workplace.
- b. Yes, ensure previously that the RAMS and all legally required Health & Safety documentation from workers and the company itself is in place..
- c. A & B are correct.
-
Question 8: When working on live equipment, which steps do, you have to take?
- a. Works on live equipment are forbidden and can be authorized only by RME manager or delegate AND WHS.
- b. Must be isolated as per the LOTO process. Disconnect the power source before servicing or repairing electrical equipment.
- c. a and c are correct