Installers to call the store prior to site arrival to ensure that the store has not closed early due to staff sickness.
-
Mitie work wear and Identification badges are to be worn and displayed at all times whilst on site.
-
Installers to sign in to site log books and undertake all required permit related activities.
-
Installers must log in to the PCS portal and download the store asbestos register and report prior to commencing any work related activities. The client will be monitoring this remotely.
-
Generic & site specific risks/RAM's must be reviewed, prepared and signed off prior to commencement of work.
-
Obtain key's & codes from Ladbrokes staff and/or confirm site lock up process prior to store closure.
-
Site audit to be completed prior to commencement of works. The audit must include 4 photos from each corner of the store along with 4 lux level readings. Lux level readings must be taken from the cash desk area, one area where writing takes place, the open area 2m from the front door in a central location, 2m from the cash desk in a central location drawing. Please upload lux level readings and photos to this form.
-
All operatives attending site must wear mandatory PPE as set out in the site specific RAM's.
-
Isolate and lock off circuits to be worked on.
-
Face masks to be worn when removing ceiling tiles or accessing ceiling void.
-
Use Gloves when handling tiles and fittings.
-
Undertake the lighting installation as per the agreed specification and drawings. Please note that some fittings may have to be moved due to A/C units, glare on gaming machines/ TV’s or poor light levels. Please update the drawings to reflect the lighting installation.
-
Install Emergency lighting as per design.
-
Prioritise the main shop floor lighting installation prior to completing all other remaining works.
-
Lighting circuits to be tested and re-energised upon completion of works. A minor works certificate must be filled out upon completion of works. Please upload photo evidence.
-
Window lighting time clocks to be reset upon completion of works. Time set points are on at 08:00 hrs and off at 23.59 hrs.
-
Site audits must be undertaken upon completion of works. Evidence must include 1x as fitted sketch drawing, 4x lux readings & 4 photos taken from the same location as the pre-install audit. Please upload lux level readings, drawing and photos to this form.
-
Installers to vacuum floors and clean down desks/worktops, seating, etc. and leave the store as it was found.
-
All waste must be removed from site and disposed of as per the guidance issued by the Project Manager.
-
Installers must sign out of store log books and complete all permit related activities prior to leaving site.
-
Installers to request store staff member (preferably store manager where possible) signature confirming that they are satisfied with the installation where appropriate.
-
Installers to upload a copy of the Entain (store staff to complete) pre-start & post completion check list. Failure to do so could lead to a return journey and/or charges for claimed store damages.
-
Installers to secure the store and return the keys to the appropriate Ladbrokes employee as per the guidance issued by the Project Manager.
-
The installers store pack must be issued to Mitie within 24 hours. The store pack must include as fitted drawings, work record sheet/engineer's timesheets, survey/Install records, minor works certificates, EML test certificates, before and After Photos & lux level readings documented via IAuditor.
-
Installers sign off upon completion of works.