Information
-
Site conducted
-
DOCUMENT NUMBER:
-
DATE OF AUDIT:
-
SITE PHOTOGRAPH:
-
ENVIROCALL PROJECT NUMBER:
-
CLIENT:
-
SITE ADDRESS:
-
ENVIROCALL SUPERVISOR or SITE MANAGER:
-
ENVIROCALL CONTRACT MANAGER:
-
OPERATIVES:
-
LICENSING STATUS:
-
REMOVAL DETAILS (Building description, ACM details, ongoing work at point of audit etc.):
1 PLANNING
-
1.01 RAMS - All sections completed accurately?
-
1.02 RAMS - Specific location of works is correct?
-
1.03 RAMS - Scope of air monitoring is accurate and sufficient?
-
1.04 RAMS - Emergency details are complete and correct?
-
1.05 RAMS - Planned welfare is appropriate and sufficient?
-
1.06 RAMS - Preliminary protection is adequate?
-
1.07 RAMS - Type of RPE is appropriate for the works?
-
1.08 RAMS - Other PPE is appropriate for the works?
-
1.09 RAMS - CMH calculation is stated correctly (including air locks, reductions etc)?
-
1.10 RAMS - Detailed work sequence is clear and thorough?
-
1.11 RAMS - Waste arrangements appropriately planned?
-
1.12 RAMS - RA covers all significant risks and control measures are all applicable?
-
1.13 ASB5 is present?
-
1.14 ASB5 - All relevant sections have been completed accurately?
-
1.15 ASB5 - All dates are correct?
-
1.16 ASB5 - Total personnel on site is within the number(s) notified?
-
1.17 DRAWING - Building drawn accurately?
-
1.18 DRAWING - ACM is depicted clearly?
-
1.19 DRAWING - Plant (NPU, lighting, H- vacs etc.) is correctly placed on drawing?
-
1.20 DRAWING - Transit and waste routes are clearly described?
-
1.21 WASTE - Waste note available and completed to correct stage in works.
2. COMPANY ADMINISTRATION
-
2.01 CURRENT FORMS ON SITE: Company Standard Procedures?
-
2.02 CURRENT FORMS ON SITE: Asbestos License?
-
2.03 CURRENT FORMS ON SITE: Waste Carriers License?
-
2.04 CURRENT FORMS ON SITE: ARCA//ACAD Certs?
-
2.05 CURRENT FORMS ON SITE: Liability Insurance Certificate?
3 SITE ADMINISTRATION
-
3.02 FORMS COMPLETED CORRECTLY: Site Induction?
-
3.03 FORMS COMPLETED CORRECTLY: Daily Site Log?
-
3.04 FORMS COMPLETED CORRECTLY: Daily Site Inspection?
-
3.05 FORMS COMPLETED CORRECTLY: DCU Checklist?
-
3.06 FORMS COMPLETED CORRECTLY: Scaffolding Tower Checklist?
-
3.07 FORMS COMPLETED CORRECTLY: Proof of Isolation?
-
3.08 FORMS COMPLETED CORRECTLY: Smoke Test Enclosure?
-
3.09 FORMS COMPLETED CORRECTLY: Confined Space?
-
3.10 PERSONNEL PAPERWORK: All Medicals current and available on site?
-
3.11 PERSONNEL PAPERWORK: All Asbestos Training Certificates current and available on site?
-
3.12 PERSONNEL PAPERWORK: All Face Fits current and available on site?
-
3.13 PERSONNEL PAPERWORK - All operatives have current 6 Monthly RPE cert on site?
-
3.13a PERSONNEL PAPERWORK: All Operatives have a current Monthly RPE test in the iFile?
-
3.14 PERSONNEL PAPERWORK: All other relevant training for current tasks current and available on site (eg EAS induction, confined space, PASMA)?
-
3.15 CURRENT PLANT CERTS ON SITE: DCU gas cert?
-
3.16 CURRENT PLANT CERTS ON SITE: DCU Electrical?
-
3.17 CURRENT PLANT CERTS ON SITE: DCU DOP Test Cert?
-
3.18 CURRENT PLANT CERTS ON SITE: DCU Previous Clearance Certificate?
-
3.19 CURRENT PLANT CERTS ON SITE: NPU DOP Certificate(s)?
-
3.20 CURRENT PLANT CERTS ON SITE: H-Vac DOP Certificate(s)?
-
3.21 CURRENT PLANT CERTS ON SITE: All plant is PAT Tested?
4 SITE OPERATIONS
-
4.01 PERSONNEL: All operatives are wearing Envirocall uniform or correctly coloured overalls?
-
4.02 PERSONNEL: All PPE appropriate to current task is in use?
-
4.03 PERSONNEL: RPE is clean and boxed (or in use)?
-
4.03b Are exposure records and daily mask checks up to date and available and filled in correctly?
-
4.04 PERSONNEL: All operatives are clean shaven?
-
4.05 VEHICLE: Externally clean and in good condition?
-
4.06 VEHICLE: Considerately parked (as per RAMS)?
-
4.07 VEHICLE: Waste compartment is free from storage?
-
4.08 VEHICLE: Storage compartment is free from waste?
-
4.09 VEHICLE: All equipment stowed safely and tidily?
-
4.10 VEHICLE: The rear of the van generally clean? No obvious debris or contaminated waste?
-
4.11 DCU: On site, set up and operational?
-
4.12 DCU: Attached to enclosure or as near as possible (as per MS)?
-
4.14 DCU: Correct Vehicle number plate?
-
4.15 DCU: Level - support legs down?
-
4.16 DCU: Externally clean and in good condition?
-
4.17 DCU: Secure (clamped and locked)?
-
4.18 DCU: All internal surfaces are clean?
-
4.19 DCU: All internal surfaces are in good condition?
-
4.20 DCU: Clean end contains sufficient supplies of Tyveks, towels etc?
-
4.21 DCU: Warm running water?
-
4.22 DCU: Doors fully self-closing?
-
4.23 DCU: Correct signage to doors?
-
4.24 DCU: Free from inappropriate items stored inside?
-
4.25 DCU: Sufficient shower gel and nail brushes?
-
4.26 DCU: Drainage filter is clean?
-
4.27 DCU: Water is being drained correctly (as per MS)?
-
4.28 DCU: Spare NPU filters present?
-
4.29 DCU: More than one shower per 4 operatives?
-
4.30 DCU: Waste bags filled to safe and manageable level?
-
4.31 DCU: Clean filter in NPU?
-
4.32 DCU: Internal fixtures are as per guidance?
-
4.33 DCU: DCU is earthed (at generator and with earth rod)?
-
4.34 DCU: RPE charger/tester present and operational?
-
4.35 NPU: Externally clean?
-
4.36 NPU: Placed as per MS?
-
4.37 NPU: Gauge working and readable?
-
4.38 NPU: Gauge reading is ok (<12 o'clock, in the green)?
-
4.39 NPU: Correctly attached to the outside of the enclosure (or sheeted if not practicable)?
-
4.41 NPU: Spare filters on site?
-
4.40 NPU: Units are identifiable either via stickers or Envirocall numbering and these match the certificate?
-
4.42 NPU: Vented externally if practicable?
-
4.43 H-VACS: Sufficient number on site (min 2no unless only 1no operative, 1no near inner airlock stage for decontamination)?
-
4.45 H-VACS: Bagged correctly when outside the enclosure?
-
4.46 H-VACS: Stickers legible and match certificates?
-
4.47 OTHER PLANT/EQUIPMENT: Smoke machine is on site with accessories?
-
4.48 OTHER PLANT/EQUIPMENT: All tools specified in MS are on site and in good condition?
-
4.49 OTHER PLANT/EQUIPMENT: Sharps are managed appropriately?
-
4.50 WELFARE: Welfare on site matches MS?
-
4.51 AREA CONTROL: Signage clearly identifies 'Asbestos Work Areas'?
-
4.52 AREA CONTROL: Heras fencing/safety barriers/barrier tape in use to control access (SFARP)?
-
4.53 AREA CONTROL: Transit Route and Waste Route clearly signed, clean and clear?
-
4.54 AREA CONTROL: All equipment is stored securely, tidily and safely?
5 ENCLOSURE
-
5.01 ENCLOSURE: Well constructed and braced and supported appropriately?
-
5.02 ENCLOSURE: Adequately signed (full signage obviously visible from every standpoint)?
-
5.03 ENCLOSURE: VP/CCTV provides adequate view of current work areas?
-
5.04 ENCLOSURE: All gaps (eg. vents/risers/pipes) have been suitably sealed?
-
5.04 AIRLOCK: Well constructed?
-
5.05 AIRLOCK: 3 stages minimum 2mx1mx1m (or equivalent - please justify)?
-
5.06 AIRLOCK: All necessary decontamination equipment in inner stage (footbath and brush, water bucket and sponge or wipes for RPE)?
-
5.07 AIRLOCK: Appropriately signed?
-
5.08 AIRLOCK: Vision panel in dirty end (and is clean)?
-
5.09 AIRLOCK: Clean end is clean?
-
5.10 AIRLOCK: Flaps are adequately weighted and overlap opening?
-
5.11 AIRLOCK: Transiting clothing/footwear in place?
-
Tick if there is enough room on site to install a Baglock?
-
5.12 BAG LOCK: Well constructed?
-
5.13 BAG LOCK: Appropriately signed?
-
5.14 BAG LOCK: Vision panel in dirty end?
-
5.15 BAG LOCK: Flaps are adequately weighted?
-
5.16 BAG LOCK: Entrance is taped unless bag run in progress (unless specified on RAMS as air inlet)?
-
5.17 BAG LOCK: Sections are large enough to handle waste passing through (min 1x1x2m - more for pipes, boards etc)?
6 ACCESS
-
6.01 Height is accessed as per MS?
-
6.02 Access equipment is in good condition?
-
6.03 Access equipment is correctly and completely erected?
7 OTHER RISKS
-
7.01 Risks have been controlled on site as per RAMS?
-
7.02 Any new hazards found on site have been managed effectively (please detail below)?
-
7.03 Trip hazards are well managed (hoses/cables/equipment etc)?
-
7.04 First aid kit is on site (sufficient for number of operatives)?
-
7.05 Appropriate fire extinguishers (eg. Van, DCU etc) are on site?
-
7.06 Air horn is available (or suitable method of attracting attention reliably from outside the enclosure)?
-
7.07 Adequate lighting is in place throughout all work areas?
8 ASBESTOS REMOVAL
-
8.01 All Control Measures specified in the POW/RA are in place on site?
-
8.02 ACM is being sufficiently wetted - as per POW?
-
8.03 All wetting equipment specified in the POW for the current task is in use on site?
9 WASTE MANAGEMENT
-
9.0 Waste within the enclosure is being bagged immediately?
-
9.01 To the extent reasonably practicable, waste bags are being quickly removed from the enclosure?
-
9.02 All waste is double bagged?
-
9.03 From observation, waste bags are being sufficiently cleaned?
-
9.04 Waste bags show evidence of sufficient wetting?
-
9.06 Waste bags are being filled appropriately (not over filled)?
-
9.07 ACMs are not being broken to fit in the bags - larger items are wrapped?
-
Tick if RAMS specify use of skip?
-
9.08 Skip is present?
-
9.09 Skip is locked?
-
9.10 Skip is well signed?
-
9.11 Skip is of adequate size for the ACM?
10 OTHER CONTRACTORS WORKING ON BEHALF OF Envirocall (analysts/scaffolders/electricians etc)
-
Tick if other companies contracted by Envirocall are currently working on site
-
Please enter contractor details for each Company on site:
Contractor
-
Name of Company:
-
Name(s) of Operatives:
-
Reason for being on site:
-
Are the contractors POW & RA on site?
-
Do we have evidence of Contractors competence to perform task at hand?
-
Please specify this evidence:
-
Are the Contractors performing their task in accordance with their POW and RA?
11 INDIVIDUAL COMPETENCE REVIEW (please note this does not affect the audit score and is solely used for training needs analysis)
-
Tick to undertake individual competency assessment:
-
Repeat for each individual assessed:
New assessment
-
Person completing the following section:
-
Assessment catagory
- RPE
- DCU/decontamination
- H-Vac
- Van
- Negative pressure
- Removal/wetting techniques
- Area Control
- General H&S
-
1 Describe common faults you may be looking out for during RPE pre-use checks:
-
2 Explain the importance of RPE cleanliness:
-
3 Why should RPE always be kept boxed when not in use?
-
4 For what reasons would an operative need to rearrange a face fit test even when his certificate is in date?
-
5 What other factors may effect a suitable face fit?
undefined
-
1 Failure to decontaminate properly could lead to what?
-
2 Describe what is done inside the enclosure to help with thorough decontamination:
-
3 In a direct connection, explain the importance of, and the features of the intervening tunnel between airlock and DCU.
-
4 Please specify the equipment needed for each of the three airlock stages:
-
5 Explain under what rare circumstances the full-face RPE wouldn't be used during transiting, and explain the alternative arrangements that should be used:
-
6 Describe the decontamination equipment that should be set up on (non-licensed) projects where no DCU is required:
-
7 Specify what needs to be done inside the DCU prior to leaving site each day:
undefined
-
1 Explain why brushes or brooms should never be used for cleaning:
-
2 Explain suitable transportation of the H-Vac (ALG 01/09p20):
-
3 Why would the analyst need the H-vac to be left in place for the 4-stage clearance?
-
4 Why should overly wet materials never be cleaned with H-Vac?
-
5 What pre/post use checks do you perform on your H-Vacs?
undefined
-
1 Describe the importance of negative pressure:
-
2 What factors could affect uniformity of negative pressure within the enclosure?
-
3 Describe when additional air inlets should have been planned, and describe precautions you need to take when they are used:
-
4 Why should stripping operations stop during filter change?
-
5 How does smoke testing aid you in determining the sufficiency of planned airflow?
-
6 Describe how the NPU manometer (gauge) can help you manage adequate pressure?
undefined
-
1 Why should all areas of the van be as clean as reasonably practicable?
-
2 Describe the importance of stowing all equipment safely and tidily:
-
3 Under what circumstances is it permissible to carry waste in the storage section of the van?
undefined
-
1 What site factors would cause you to contact CM regarding planned stripping techniques?
-
2 What precautions need to be taken during wet stripping techniques?
-
3 How can the Supervisor ensure operatives are pre-wetting ACMs adequately?
-
4 Describe the adequate use of wetting agents (eg 'Astrip'):
-
5 What factors can lead to poor (under or over) wetting?
-
6 What problems can be caused by poor (under or over) wetting of ACMs?
-
7 Describe correct placing of needles for injection wetting:
-
8 What is the aim of effective spraying?
undefined
-
1 At what point does signage need to be in place warning 3rd parties that work is in progress.
-
2 Describe the difference between an 'asbestos work area' and a 'respirator zone':
-
3 Regarding welfare, what activities should never take place within an asbestos work area?
undefined
-
1 Describe factors (other than asbestos) that you need to manage on site?
-
2 When is work 'at height'?
-
3 What is a 'confined space'?
-
4 Why is electricity a particular risk on site?
-
5 What pre-use equipment checks do you employ to eliminate or reduce electrical risks?
-
6 What practices/equipment can be used to reduce the risk of slips or trips?
-
7 How could the work of other (non- Envirocall )contractors affect the Management of your site?
-
8 What H&S considerations apply to driving?
-
9 Apart from Envirocall operatives, who else do you need to consider when managing site risks?
-
10 Describe PPE (other than RPE, STC boots and overalls) necessary on some sites?
-
Competency assessment completed by:
12 SUB-CONTRACTED ASBESTOS OPERATIVES
-
Please note: The comments in this section reflect the individual opinion of the Site Manager. The information collected is used for training need analysis, and for sub-contract operative competency assessment. It will be treated in the strictest of confidence, and used only within Envirocall.
-
Are there any sub-contracted asbestos removals operatives on this site?
-
Repeat for each individual SC operative on site:
SC operative:
-
Name:
-
Labour provider (agency):
-
Please comment on specifics (especially if any section scores less than 6):
-
Would you recommend this operative be employed by Envirocall in future?
13 ANEMOMETER AIRFLOW MEASUREMENT
-
Tick to undertake NPU test
-
Anemometer (LV130) test:
Tick to test:
-
Envirocall NPU number:
-
Measured Volume from Cert (M3/hr):
-
Volume of air to be moved according to RAMS (after reduction):
-
Active area of filter (m2 - X):
-
Airflow Measurement 1 (Top left):
-
Airflow Measurement 2 (Top right):
-
Airflow Measurement 3 (Bottom left):
-
Airflow Measurement 4 (Bottom right):
-
Airflow Measurement 5 (middle - if > 1500NPU):
-
Average of above airflow measurements (Y):
-
Actual measured airflow (X x Y x 3600 = M3/hr):
-
Confirm that this is sufficient to produce at least 8 air changes per hour:
-
INSUFFICIENT NP - STOP JOB TO REASSESS!
14 SUMMARY
-
Tick if there are any non-conformances above
-
NON-CONFORMANCE SUMMARY:
Non-conformance
-
Non-conformance detail:
-
Describe action taken to complete non-conformance:
-
Person/People responsible for non-conformance completion:
- Auditor
- Operative
- Supervisor
- Contract Manager
- Head Office
-
Date of non-conformance completion:
-
Non-conformance completed by:
-
FURTHER DETAILS:
-
SITE MANAGER:
-
AUDITED BY:
-