Lock Out Application Process
-
1. Notify affected personnel. 2. Properly shut down machine. 3. Isolate all energy sources. 4. Apply lockout devices, locks, tags and tags. 5. Verify the de-energisation of all energy sources.
PERSONS AFFECTED
-
Affected Personnel
- Machine Operators,
- Maintenance Personnel,
- Visitors,
- Temporary workers,
- Contractors,
ENERGY SOURCES INVOLVED
-
Identify sources of energy
- Electric Main
- Electric Static
- Air (pneumatic)
- Hydraulic
- Gas
- Stored Energy
- Valves, Vents and Drains (oils, coolant, water, etc)
- Batteries or capacitors
1. MACHINE TO BE ISOLATED & DETAILS
-
Equipment ID# / Name
-
Add media
-
Description :
-
Electrical Voltage
-
Hydraulic Pressure while in operation:
-
Air Pressure while in operation:
-
Method of isolation for this machine
- Valve lockoff
- Electrical isolation
- De-energise
- Key isolated and removed
- Fuse removal
-
Devices required to fully isolate:
- Hasp and lock
- Valve Lock
- Breaker lock
- Plug lock
- Chain & Lock
- Sign and tag
- Lock out Box
- Controller cover
-
Identify Lockout Points:
Lockout removal process
-
1. Remove all tools 2. Replace all guards and covers. 3. Notify all affected personnel 4. Check for all clear. 5. Re-energize per manufacturer or company procedure.