Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Site Visit Questions (Answer all Questions)
-
Job No:
-
Project Title:
-
ESB Supervisor
-
ESB Design Drawing
-
ESB PO Work Instruction (If Available)
-
Who is noted as PSCS for these works?
-
Type of ESB Works Involved
- T&D
- ERW FAULT WORKS
- High Voltage
- Reinstating
- Joint bay works
- Site investigation and trial holes
- Cable Pulling
- Mini Pillar Works
- Sub Unit Repair/ Replace/ Remedial
- Other
-
Visit Date:
-
Site Location:
-
Site Size (Approx.):
-
Programme for works - Steps for works and how long works are estimated
-
Do you have service drawings available?
-
Is there any High Volatge ESB
-
Is there any High Pressure Gas
-
Do we need to notify relevant bodies for Supervison prior to works commencing?
-
Traffic Management required?
- Yes
- No
-
Is there an ESB Design/PO/Work Instruction on site
- Yes
- No
-
Upload supporting documents of Design/PO
-
Do we need to liase with Public and business in area and is there a letter drop required?
- Yes
- No
-
Type of Traffic Management required?
- Road Narrows
- Stop and Go
- Contra Flow
- TLSO
- Other
-
Traffic lights in or near the work Zone?
-
Do we need to request a TLSO?
- Yes
- No
-
Is there an area for work vehicle parking
- Yes
- No
-
Do we need to notify Councils for paking spaces?
-
If spaces taking up how many spaces needed?
-
Pre work Site visit checklist Photos
-
Do you notice any particular defects in work area? Take pictures of these
-
3 - Step process To be completed
-
List other tasks:
Risks Indentified on site
-
Additional Comments?
-
Identify Possible Emergency Procedure Requirements: (Near River/O/H Lines/Heavy Traffic)
-
Is there any Enviromental apspects that may be impacted when working in this location? eg Close to Waterways?
-
Do You Notice Any Particular Risks/Hazards:(Main risks in the area)?
-
Are there any Hospitals, Schools, Colleges, Churches in Direct proximity to Work Zone etc?
- Yes
- No
-
Photos of Risks identified
-
Overheads in area if so what type?
- ESB
- TELECOMS
- Stay wires
- Trees/Branches
- Other
- N/A
-
Type of spoil to be Removed
- Concrete
- Soil
- Spoil
- Tar
- Other
-
Will any Spoil removed contain contaminate?
-
Confined Space Required?
- Yes
- No
-
Will works take place directly under Overheads?
- Yes
- No
-
Suggested overhead contols.
- Goalposts
- Signage
- Shroud
- Switch Out
- Machine Liniter
- Other
- N/A
-
Picture of Overheads
-
Height at which the overheads are measured?
-
Identify Services/Stakeholders on Site:(Scars of roadway/Stopcocks in footpath/Gas Meters on houses?)
- ESB
- GNI
- IW
- EIR
- Virgin
- BT
- Other
-
Do you expect the excavation to exceed expected depths during Works?
- Yes
- No
- TBC
-
Welfare Unit Required?
- Yes
- No
-
Do any other external agencies require notification? (e.g Dublin Bus, Traffic News, AA . Luas, Irish Rail, etc)
-
Identify Plant & Machinery Suitable for this Site/Access/Type of works (Ensure Certified Plant)
- 5T excavator
- 3T Excavator
- Cat
- Genny
- Van
- Hotbox
- Pick up
- Grab
- Cable Carrier
- Winch
- Compressor
- Whacker Plate
- Jumping Jack
- Consaw
- Roadsaw
- Drill
- Power Pack
- Skill saw
- Generator
- Pump
- Dumper
- Ladder
- Other
-
Identify Any Skills or Training Relevant to the Site or Project:
- First Aid
- Manual Handling
- CSCS 360 Excavator
- CSCS Dumper
- Abrasive Wheels
- Lugs
- SLG
- First Aid
- ESB Induction
- Covid 19 Induction
- Covid 19 Compliance Officer
- GPR
- Other
-
Completed By:
-
Name (Printed):
-