Title Page
-
Site conducted
-
First Line of Address
-
Conducted on
-
Prepared by
- Ben
- Steve
- Tom
- David Unsworth
- Luke
- Jared
Pre-Works Risk Assessment
-
Measure Carried Out
- Solar PV
- Solar Battery
-
Does the customer understand the works being carried out?
-
Stop work and advise customer reason of visit
-
Are all household items removed creating a safe working area?
-
Are all tools suitable for use ?
-
Any other Restictions or Concerns?
-
Local hospital been identified prior to work commencing?
-
Please State local Hospital...
Asbestos
-
Is there an asbestos report present for the job?
-
Has the asbestos report been read
-
Installer Signature - Please sign when all relevant questions have been filled and you are happy with the precautions in place to complete potential works on Asbestos Containing Materials if present
Pre Work - Before Installation
-
Where is the majority of works taking place?
-
DNO and Meter
-
Proposed location of consumer unit , AC isolator & generation meter
-
Proposed location of Inverter, DC isolator & AC isolator
Mid Install - During Installation
-
Conduit / Trunking run for AC Cables
-
Cable Run for DC Cables
-
Wide shot of mounted consumer unit, generation meter & AC Isolator with covers off
-
Photo of fire grommets
-
Wide shot of mounted inverter, AC Isolator & DC Isolator with covers off
Post Work - After Installation
-
Incoming Mains Supply, Fuse Rating Photo, Electric Meter, Wide Shot
-
Incoming Mains Supply Location
-
Tails Size
-
Water Bond , Gas Bond & Oil Bond
-
Inverter Location
-
Number of smoke detectors installed
-
Consumer Unit Labelled & RCBO’s
-
Has Surge Protection Been Installed ?
-
Wide Shot of AC Install
-
Generation Meter
-
Handover pack (located near consumer unit)
-
Wide Shot of DC Isntall (DC Isolator, Inverter & AC Isolator)
-
WiFi Dongle Plugged In
-
DC Cables - Clipped & Warning Stickers
-
Schematics Completed and in place
-
Inverter Powered Up - Solar Generated (W)
-
Inverter Serial Number & Spec
-
Innovation Sticker on Inverter (close up showing details)
-
Number of panels on roof
Electricians Completion
Electrician Completion
-
Installers
- Ben
- Steve
- Tom
- David Unsworth
- Luke
- Jared
-
Has the installation been carried out in accordance with BS 7671?
-
Were all materials used in compliance with BS 7671 standards?
-
Has the client been provided with all necessary documentation, including user manuals, safety information, and maintenance schedules?
-
Is The Customer Aware of Shut Down & Start Up Procedure ?
-
Are all photos geotagged
Customer Satisfaction
-
Has google review card been left with resident or posted
-
Confirmation of Completion by the occupier - this confirms that the customer is happy with the install