Information

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

ExacTrac X-Ray Generator

  • Space for Dual Generator available? (include photo)

  • Is there a floor pull box underneath x-ray generators (include photo)?

  • Is the pull box less than 16"x16"?

  • Is the location of the pull box such that cables can be pulled and x-ray generator won't tip in?

  • Are the x-ray generators separated?

  • Is the conduit length from X-Ray Generator #1 to X-Ray Generator #2 less than 15m?

  • 20m X-Ray Generator cable ordered?

  • Power Supplied: 480V 70A or 208V 100A?

  • 5 conductors: 3 phase, 1 neutral and 1 ground?

  • Correct circuit breaker / disconnect installed within 6' (include photo)?<br><br>

Conduits

  • 1x5" from floor box 1 to x-ray generator 1

  • 1x5" from floor box 2 to X-Ray Generator 2

  • 1x3" from x-ray generator 1 to computer cabinet

  • 1x3" from x-ray generator 1 to x-ray generator 2

  • Grounding bar and needed conduit in place?

  • Do all conduits meet the cable length limitations?

ExacTrac Computer Cabinet

  • Space for computer cabinet available (include photo)

  • Is computer cabinet located outside the treatment vault? (Only required if treatment energy of 10MV or higher will be used, N/A otherwise.)

  • If No, has this been approved by Happy and additional shielding been ordered?

  • Is there a floor pull box underneath Computer Cabinet (include photo)?

  • Is the pull box less than 16"x16"?

  • Location of the pull box is such a way that cables can be pulled and cabinet won't tip in?

  • Power supplied: 120V 30A single phase

  • Network drop / data connection for computer cabinet in place? (include photo). ***N/A if Elekta integration***

  • Confirmed with IT / customer that this will be live during installation? ***N/A if Elekta integration***

  • Correct circuit breaker / disconnect installed within 6' (include photo)

Conduits

  • 1x3" from computer cabinet to each flat panel detector

  • 1x2" from computer cabinet to IR Camera

  • 1x1" from computer cabinet to warning light 1 and 1x1" from warning light 1 to warning light 2

  • 1x2" for power from computer cabinet to each In Room Distribution Box and Control Room Distribution Box

  • 1x2" for data from computer cabinet to In Room Distribution Box

  • 1x3" for data from computer cabinet to Control Room Distribution Box

  • 1x2" from computer cabinet to baseframe pull box

  • 1x2" from computer cabinet to bluetooth module

  • Pathway is available for network cable to Elekta NSS firewall? ***Elekta integration only***

  • Grounding bar and needed conduit in place (include photo)?

  • Do all conduits meet the cable length limitations?

Ceiling Mounts

  • IR Camera mount installed, free of obstructions, leveled and rigid (include photo)?

  • Both Flat Panel Detector mounts install, free of obstructions, leveled and rigid (include photo)?

  • Is the mount in correct location?

  • Are the mounts in correct location?

  • Touch screen monitor mount installed, free of obstructions, leveled and rigid (include photo)?

  • Is the mount in correct location?

X-Ray Tube Floor Boxes

  • X-Ray Tube Floor boxes are installed and are within specified tolerance (include photo)?

  • For on-floor solution, is routing of on-floor cable raceways planned such that they can access generators and do not interfere with anything vital? (Note that with TrueBeam-Slim cables cannot run immediately to patient-left side of linac.)

Distribution Boxes

  • In Room Distribution Box installed (include photo)?

  • Is it installed in the correct location (withing 9' of touch screen monitor)?

  • 1x2" conduit from In Room Distribution Box to Touch Screen monitor in place?

  • 1x1" conduit from In Room Distribution Box to IR Camera and each Flat Panel Detector in place?

  • 1x2" conduit from In Room Distribution Box to Bluetooth module in place?

  • Control Room Distribution Box installed (include photo)?

  • Is it installed in the correct location?

Warning Lights and Interlock System

  • Are both the warning lights installed (include photo)?

  • Emergency stop interlock in place?

  • Door Interlock in place?

  • Beam on interlock in place?

Pre-install cables

  • Are the pre-install cables pulled? List cables that have not been pulled or issues related to the cables (include photo)?<br>

Storage Space & Trash Removal

  • Main Shipment storage space identified (include photo)?

  • Trash removal discussed with customer?

Pre-install coordination

  • Date by which all pending pre-install work needs to be complete

Linac specs and coordination

  • Is 4DTC version more than 10.2.3? If new linac order then get confirmation from Varian that it will be installed.

  • Is BCCV installed? If new linac order then get confirmation from Varian that it will be installed.

  • Is laser guard installed? If new linac order then get confirmation from Varian that it will be installed.

  • Is ADI/MMI installed? If new linac order then get confirmation from Varian that it will be installed.

  • Couch recalibration services ordered and scheduled?

  • Juniper firewall installed? Add photograph. If new linac order then get confirmation from vendor that it will be installed.

  • Is the R&V system installed?

  • What R&V system does the customer have? (Include version number)

  • Is CITB ET kit installed? If new linac order then get confirmation from Elekta that it will be installed.

  • Is the ET goal post kit installed? If new linac order then get confirmation from Elekta that it will be installed.

  • Is XVI 5.0 or higher installed? If new linac order then get confirmation from Elekta that it will be installed.

  • Is iGuide 2.1 or higher installed? If new linac order then get confirmation from Elekta that it will be installed.

  • Is NSS installed? If new linac order then get confirmation from Elekta that it will be installed.

  • For Elekta linac with ETX integration, is MOSAIQ 2.5 or higher installed? If new linac order then get confirmation from Elekta that it will be installed.

  • Is the Elekta frameless extension MI part # 10105-414 ordered/delivered?

  • iBeam evo couch adapter for brainlab couch mount ordered/delivered?

  • Integrity 1.2 for Beam Modulator, MLCi, MLCi2 or Integrity 3.2 for Agility installed? If new linac order then get confirmation from Elekta that it will be installed.

Installation Coordination

  • Installation Dates & Installation Team

  • Any security clearances, badges, safety courses, immunization etc required by hospital/contractor from installation team?

  • Contractor / Facilities will be assisting with moving the cabinet in place from storage?

  • Select date

  • Electrician will be present during installation to connect the back panel to the wall and connect power

  • Select date

  • Identify who is going to be signing the STATEMENT OF COMPLIANCE FROM HOSPITAL / CONTRACTOR during accetpances

Additional Photographs

  • Add media

Signatures

  • Brainlab PM Signature

  • Customer / Contractor representative signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.