Information
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
ExacTrac X-Ray Generator
-
Space for Dual Generator available? (include photo)
-
Is there a floor pull box underneath x-ray generators (include photo)?
-
Is the pull box less than 16"x16"?
-
Is the location of the pull box such that cables can be pulled and x-ray generator won't tip in?
-
Are the x-ray generators separated?
-
Is the conduit length from X-Ray Generator #1 to X-Ray Generator #2 less than 15m?
-
20m X-Ray Generator cable ordered?
-
Power Supplied: 480V 70A or 208V 100A?
-
5 conductors: 3 phase, 1 neutral and 1 ground?
-
Correct circuit breaker / disconnect installed within 6' (include photo)?<br><br>
Conduits
-
1x5" from floor box 1 to x-ray generator 1
-
1x5" from floor box 2 to X-Ray Generator 2
-
1x3" from x-ray generator 1 to computer cabinet
-
1x3" from x-ray generator 1 to x-ray generator 2
-
Grounding bar and needed conduit in place?
-
Do all conduits meet the cable length limitations?
ExacTrac Computer Cabinet
-
Space for computer cabinet available (include photo)
-
Is computer cabinet located outside the treatment vault? (Only required if treatment energy of 10MV or higher will be used, N/A otherwise.)
-
If No, has this been approved by Happy and additional shielding been ordered?
-
Is there a floor pull box underneath Computer Cabinet (include photo)?
-
Is the pull box less than 16"x16"?
-
Location of the pull box is such a way that cables can be pulled and cabinet won't tip in?
-
Power supplied: 120V 30A single phase
-
Network drop / data connection for computer cabinet in place? (include photo). ***N/A if Elekta integration***
-
Confirmed with IT / customer that this will be live during installation? ***N/A if Elekta integration***
-
Correct circuit breaker / disconnect installed within 6' (include photo)
Conduits
-
1x3" from computer cabinet to each flat panel detector
-
1x2" from computer cabinet to IR Camera
-
1x1" from computer cabinet to warning light 1 and 1x1" from warning light 1 to warning light 2
-
1x2" for power from computer cabinet to each In Room Distribution Box and Control Room Distribution Box
-
1x2" for data from computer cabinet to In Room Distribution Box
-
1x3" for data from computer cabinet to Control Room Distribution Box
-
1x2" from computer cabinet to baseframe pull box
-
1x2" from computer cabinet to bluetooth module
-
Pathway is available for network cable to Elekta NSS firewall? ***Elekta integration only***
-
Grounding bar and needed conduit in place (include photo)?
-
Do all conduits meet the cable length limitations?
Ceiling Mounts
-
IR Camera mount installed, free of obstructions, leveled and rigid (include photo)?
-
Both Flat Panel Detector mounts install, free of obstructions, leveled and rigid (include photo)?
-
Is the mount in correct location?
-
Are the mounts in correct location?
-
Touch screen monitor mount installed, free of obstructions, leveled and rigid (include photo)?
-
Is the mount in correct location?
X-Ray Tube Floor Boxes
-
X-Ray Tube Floor boxes are installed and are within specified tolerance (include photo)?
-
For on-floor solution, is routing of on-floor cable raceways planned such that they can access generators and do not interfere with anything vital? (Note that with TrueBeam-Slim cables cannot run immediately to patient-left side of linac.)
Distribution Boxes
-
In Room Distribution Box installed (include photo)?
-
Is it installed in the correct location (withing 9' of touch screen monitor)?
-
1x2" conduit from In Room Distribution Box to Touch Screen monitor in place?
-
1x1" conduit from In Room Distribution Box to IR Camera and each Flat Panel Detector in place?
-
1x2" conduit from In Room Distribution Box to Bluetooth module in place?
-
Control Room Distribution Box installed (include photo)?
-
Is it installed in the correct location?
Warning Lights and Interlock System
-
Are both the warning lights installed (include photo)?
-
Emergency stop interlock in place?
-
Door Interlock in place?
-
Beam on interlock in place?
Pre-install cables
-
Are the pre-install cables pulled? List cables that have not been pulled or issues related to the cables (include photo)?<br>
Storage Space & Trash Removal
-
Main Shipment storage space identified (include photo)?
-
Trash removal discussed with customer?
Pre-install coordination
-
Date by which all pending pre-install work needs to be complete
Linac specs and coordination
-
Is 4DTC version more than 10.2.3? If new linac order then get confirmation from Varian that it will be installed.
-
Is BCCV installed? If new linac order then get confirmation from Varian that it will be installed.
-
Is laser guard installed? If new linac order then get confirmation from Varian that it will be installed.
-
Is ADI/MMI installed? If new linac order then get confirmation from Varian that it will be installed.
-
Couch recalibration services ordered and scheduled?
-
Juniper firewall installed? Add photograph. If new linac order then get confirmation from vendor that it will be installed.
-
Is the R&V system installed?
-
What R&V system does the customer have? (Include version number)
-
Is CITB ET kit installed? If new linac order then get confirmation from Elekta that it will be installed.
-
Is the ET goal post kit installed? If new linac order then get confirmation from Elekta that it will be installed.
-
Is XVI 5.0 or higher installed? If new linac order then get confirmation from Elekta that it will be installed.
-
Is iGuide 2.1 or higher installed? If new linac order then get confirmation from Elekta that it will be installed.
-
Is NSS installed? If new linac order then get confirmation from Elekta that it will be installed.
-
For Elekta linac with ETX integration, is MOSAIQ 2.5 or higher installed? If new linac order then get confirmation from Elekta that it will be installed.
-
Is the Elekta frameless extension MI part # 10105-414 ordered/delivered?
-
iBeam evo couch adapter for brainlab couch mount ordered/delivered?
-
Integrity 1.2 for Beam Modulator, MLCi, MLCi2 or Integrity 3.2 for Agility installed? If new linac order then get confirmation from Elekta that it will be installed.
Installation Coordination
-
Installation Dates & Installation Team
-
Any security clearances, badges, safety courses, immunization etc required by hospital/contractor from installation team?
-
Contractor / Facilities will be assisting with moving the cabinet in place from storage?
-
Select date
-
Electrician will be present during installation to connect the back panel to the wall and connect power
-
Select date
-
Identify who is going to be signing the STATEMENT OF COMPLIANCE FROM HOSPITAL / CONTRACTOR during accetpances
Additional Photographs
-
Add media
Signatures
-
Brainlab PM Signature
-
Customer / Contractor representative signature