Information
BAFFIN WIND PROJECT - 13140009
-
Conducted on
-
Prepared by
-
WTG Number
Third Party Review
-
Project Name: Baffin Wind Project
-
Project Number: 13140009
-
WTG #:
-
Date & Time
-
Bottom of excavation is consistent with design requirements (Barr Drawing S02-R1), Geotechnical Report (Barr Engineering, Baffin Wind Project Geotechnical Report, OCT 2013)
-
If over-excavation is needed, are engineer requirements met per Drawing?
-
Third party has inspected excavation and has approved excavation for use
-
Third Party: Element Materials Technology
-
Third Party Representative Signature
Mortenson Review
-
Mud Mat boundary is marked and visible (or specified bank to bank, or other)
-
Bottom of excavation has no standing water other than small intermittent puddles less than 1" in depth
-
Screed stakes are level and located correctly (center of hole, encompass AB cage area)
-
Excavation has no voids
Mud Mat Grade Stake Design Elevation:
-
(2')
Actual Elevation:
-
Does the actual elevation meet design requirements?
-
Excavation sump and pump in place prior to concrete placement, if needed?
-
Excavation has been cleared of all loose or unstable materials (rocks, soils, chunks, etc?)
-
Drain tiles (if present) are plugged, rerouted, marked, and sump pumps can keep up
-
Confirmed no NCNs are present
-
If yes, are they closed?
-
Excavation approved for Mud Mat placement by Mortenson & Third Party?
-
Mortenson QAQC Signature
-