BAFFIN WIND PROJECT - 13140009

  • Conducted on

  • Prepared by

  • WTG Number

Third Party Review

  • Project Name: Baffin Wind Project

  • Project Number: 13140009

  • WTG #:

  • Date & Time

  • Bottom of excavation is consistent with design requirements (Barr Drawing S02-R1), Geotechnical Report (Barr Engineering, Baffin Wind Project Geotechnical Report, OCT 2013)

  • If over-excavation is needed, are engineer requirements met per Drawing?

  • Third party has inspected excavation and has approved excavation for use

  • Third Party: Element Materials Technology

  • Third Party Representative Signature

Mortenson Review

  • Mud Mat boundary is marked and visible (or specified bank to bank, or other)

  • Bottom of excavation has no standing water other than small intermittent puddles less than 1" in depth

  • Screed stakes are level and located correctly (center of hole, encompass AB cage area)

  • Excavation has no voids

Mud Mat Grade Stake Design Elevation:

  • (2')

Actual Elevation:

  • Does the actual elevation meet design requirements?

  • Excavation sump and pump in place prior to concrete placement, if needed?

  • Excavation has been cleared of all loose or unstable materials (rocks, soils, chunks, etc?)

  • Drain tiles (if present) are plugged, rerouted, marked, and sump pumps can keep up

  • Confirmed no NCNs are present

  • If yes, are they closed?

  • Excavation approved for Mud Mat placement by Mortenson & Third Party?

  • Mortenson QAQC Signature

  • Photos:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.