Title Page
-
Application Number
-
Conducted on
-
Assessing Engineer
-
Real Property Description
-
Site Address
Project Details
-
Developer Name
-
Developer Phone
-
Developer Email
-
Contractor Name
-
Contractor Phone
-
Superintendent Name
-
Superintendent Phone
Checklist
-
Roadworks
Roadworks
-
Grades and profiles to roads and footpaths constructed to design
-
AC surfacing for texture and finish/free of blemishes
-
Bitumen surfaces to be swept of excess stone/bitumen
-
Street names, signs, line-marking, hazard boards, traffic signs, guide posts
-
Boundaries clearly denoted with markers
-
Check conduit against markers
-
Driveways, footpaths and other concrete works constructed as per design
-
Joints in the seal (especially where various development stages apply) are flush
-
Road surface damage, when cause by utility service providers, should be repaired during the maintenance period
-
Back of kerb turfed to a minimum width of 800mm
-
All service fixtures (such as valves) are flush with the surrounding verge
-
Concrete footpaths and pram ramps are constructed to the specified standards
-
Signs and pavement marking for roads and bikeways are installed as per the approved drawings
Additional comments
-
Additional comments relating to Roadworks
-
Concrete Kerb & Channel (CKC) and Medians
Concrete Kerb & Channel (CKC) and Medians
-
The correct type are used at all locations (including medians) in accordance with the specified standards
-
Transitions and connections to existing construction are smooth and to a satisfactory standard of workmanship
-
Service markers are placed in kerb face.<br>Conduits (including water) should be exposed for inspection purposes.
-
Lip and back of kerb are flush with the roadway and footpath respectively
-
All channelisation works and medians have been satisfactorily completed
-
Backing strips are provided to median kerbs where required
-
Subsoil drains are provided under medians
Additional comments
-
Additional comments relating to Kerb & Channel
-
Stormwater Drainage
Stormwater Drainage
-
Roads, pipes, structures, flow paths clear of silt and debris
-
No ponding on roads, in pipes, structures, kerbs on flow paths
-
Turfing and/or grass seeding applied to prescribed areas
-
No damage to pipes
-
No reinforcing steel exposed to cut off pipes
-
Quality of concrete work/pipe joints and mortaring acceptable
-
Pipe penetrations to manholes finished off
-
Check for unsound render work
-
Converter slabs mortar bedded
-
Manhole lids to specified class requirements
-
Correct drops through manhole
-
Open cut channel section
-
Inter-allotment drainage pipes and manholes to grade, per alignment and are clean and dry
-
Correct manhole sizes, lids, locations
-
Manhole lids finished to match finished surface levels and slopes per specification
-
Subsoil drains to have end caps and frog flaps
-
Stone pitching as to specified requirements and/or other scour protection treatment
-
Headwalls/outlets compliant
-
No obvious defects in headwalls and pipe crossings
-
Pipe layout is as per the plan or approved amendments with respect to pipe size, levels and location
-
Trenches: No visual subsidence as occurred and all density tests are available and satisfactory
-
Closed circuit television (CCTV) camera inspection to demonstrate that the pipes do not sustain any premature cracking
-
Appropriate overland flow paths are provided and clear of obstruction
-
Subsoil drainage discharges to gullies or other approved point of discharge
-
Pipes are laid straight to grade and line
Additional comments
-
Additional comments relating to Stormwater Drainage
-
Earthworks
Earthworks
-
Toe of fill batters and top of cut batters are set back a minimum of 0.3m from boundary of the public space
-
Retaining walls are contained wholly within the allotments
-
Retaining walls are constructed in accordance with the approved drawings
-
Batter slopes are constructed in accordance with the approved drawings
-
Batter slopes stabilised against erosion
-
Interim drainage is constructed in accordance with approved drawings
-
Smooth transitions have been provided between new work and natural channels
-
Cut-off walls have been constructed to all concrete channel edges and outlet or inlet structures
Additional comments
-
Additional comments relating to Earthworks
-
General (strike, site cleanliness, etc.)
General
-
All disturbed areas have been topsoiled and seeded with a minimum 40% strike and/or stabilised with an approved chemical binding agent
-
Site is clean; tidy and free of rubbish, rocks, sticks, unauthorised stockpiles, etc.
-
Allotment earthworks to be free draining and generally in accordance with the approved design
-
Stormwater quality control measures in place
-
Integrity of environmentally significant areas compliant
-
Work on adjacent or balance lots to be free draining and generally cleaned and tidied
-
All areas to be mowed
Additional comments
-
Additional comments relating to General items
-
Stencil pattern concrete
Stencil Pattern Concrete
-
Level of concrete pavement joins neatly onto the AC surface and the CKC
-
Good coverage of colour hardener have been applied as per the specification
-
Two coats of protective sealer have been applied
Additional comments
-
Additional comments relating to Stencil Pattern Concrete
-
Fencing and features
Fencing and features
-
Specifically approved entrance features are constructed in accordance with the drawings
-
Sound attenuation fences are contained wholly within the allotments and constructed in accordance with the drawings
Additional comments
-
Additional comments relating to Fencing and features
-
Landscaping
Landscaping
-
Landscaping is placed as per the approved landscaping plan
-
Date irrigation system is to be removed
-
Irrigation system has been removed
-
Establishment program is implemented
Additional comments
-
Additional comments relating to Fencing and features
-
Water Quality
Water Quality
-
Implement the approved erosion and sediment control plan during construction phase
-
Water quality designs constructed to design
-
Water quality checklist provided (water by design completed)
Additional comments
-
Additional comments relating to Water Quality
-
Parks
Parks
-
Council parks officer present on inspection or has been notified that the works require a parks inspection
Additional comments
-
Additional comments relating to Parks
-
Assessing Officer (Engineer)
-
Assessing Officer (Parks Officer)
-
Consulting Engineer