Information
-
Client / Site
-
Conducted on
-
Location
-
Personnel
-
Site/Project Managers details:
-
Pile Type
-
Rig Required
-
Anticipated start date w/c
-
Number of piles
-
Duration
-
Provision and protection of access to site and piling area?
-
Does the concrete get delivered through the same site access?
-
Any access issues?
-
Construction issue drawings received 2 weeks prior to start?
-
Has the client received working platform information?
-
Level that piling mat is installed to
-
Under/overground obstruction or services identified and protected?
-
Franki setting out?
-
Daily concrete cubes?
-
Integrity testing? 48 notice required
-
Is debonding foam required?
-
Static/dynamic load test required?
-
Material storage area? Hard standing for pump, agitator, tool shed, and water supply.
-
Adequate welfare, drying room, hot water?
-
Any specific health and safety requirements?
-
Environmental issues?
-
Any site/delivery time restrictions?
-
Comments?
-
Client:
-
Franki foundations uk: