Title Page
-
Company Inspected
-
Other Company
-
Foreman/Lead
-
Additional Personnel
-
Location
-
Date and Time
-
Inspector Name
-
Summery of what was observed:
Element A0: General
-
PPE OK?
-
OQ verified and appropriate for Task(s)?
-
Do they have valid 811 Ticket?
-
Are utilities marked?
-
Current OMC Manual available?
Element A1: Worksite Setup/Appearance & Presentation
-
Picture ID card
-
First aid kit onsite?
-
Fire extinguisher available (as required)
-
Proper warning sign placement/work zone setup
-
Appropriate use of barricading, cones and excavation protection
-
Flaggers in use (as required)
-
Required flagging certificate available
-
Traffic Control Adequate
-
Required permits
-
Proper load securement
-
Material Handling Adequate
-
Non-qualified individuals properly directed
-
Property damaged observed
-
Appropriate removal of excess material/debris
-
Any additional follow-up required
Element A2: Instrument Check
-
Equipment used
-
All equipment calibration(s) verified up to date
-
Was proper equipment startup procedure followed
-
Any additional follow-up required
Element A3: Proper Locating Practices
-
Locate marks are clear and accurate
-
Appropriate method was used to complete locate (.eg., direct, indirect, or measurement)
-
All FPU underground facilities marked in proposed work zone as shown on as-built
-
Excessive marking (e.g., on retaining walls aggregate driveways and decorative shrubs)
-
Was locate completed within required timeframe
-
Were appropriate follow-up and communication made
-
Any additional follow-up required
Element A4: Monitoring 3rd Party Excavations
-
Proper stand-by procedures followed
-
Properly inspects exposed underground pipe
-
Appropriately repairs pipe coating
-
Any additional follow-up required
Element A5: Emergency Response
-
Parked vehicles in safe locations(s)
-
Conducted a thorough initial assessment
-
Started leakage instrument before entering scene
-
Eliminated ignition sources
-
Took readings at appropriate locations
-
Evacuated as appropriate
-
Communicated and coordinated fire department assistance
-
Set and maintained required perimeter based on readings
-
Continued to monitor gas readings
-
Communicated with customers/other parties
-
Provided event status updates to DISPATCH or SUPERVISOR as needed
-
Communicated with FPU resources as they arrived
-
Safe Zone Huddle conducted
-
Incident Commander identified
-
Emergency response documentation appropriately completed (duplicated with documentation)
-
Any additional follow-up required
Element A6: Leak Survey Practices
-
Takes reading at appropriate locations
-
All required facilities surveyed
-
Properly surveys and classifies atmospheric corrosion
-
Survey completed by completed by compliance due date
-
Properly classifies leaks
-
Proper survey procedures followed
-
Any additional follow-up required
Element A7: Documentation
-
Accurate completion of as-builts, services cards and valve cards
-
Additional forms/reports completed accurately, as required
-
Accurate pressure test information documented
-
Pipe condition noted
-
Corrosion reading (as required)
-
Meter information accurately recorded
-
Proper brochures, stickers, tags or signs left as required
-
Emergency response documentation appropriately completed
-
Any additional follow-up required
Element B1: Excavation and Backfill
-
Locates present or locate number (as required)
-
Locates maintained throughout job
-
Were proper methods used to expose utilities
-
Shoring in use (as required)
-
Appropriate backfill material used
-
Buffer zones maintained
-
Spotter in use (as needed)
-
Acceptable excavation restoration
-
Appropriate use of ladder(s)
-
Proper procedures followed
-
Any additional follow-up required
Element B2: Installation and Maintenance of Pipe
-
Visual pipe inspection for damage and corrosion
-
Holiday detector used on steel pipe
-
Approved mechanical pull head used on pullback
-
Proper sealing of casing
-
Test leads installed (as required)
-
Anode installed (as required)
-
Tracer wire appropriately installed
-
Appropriate wire connection methods used
-
Proper locate marks left on jobsite
-
Continuity of tracer wire verified with locator
-
Air test at appropriate pressure and duration
-
Proper support of pipe
-
EFV installed (as required)
-
Riser appropriately positioned
-
Appropriate materials used
-
Depth standards met
-
Separation standards met (e.g., other utilities)
-
Were appropriate steps taken to protect exposed pressurized pipe
-
Proper procedures followed
-
Operated valve verifying stops are in placd
-
Any additional follow-up required
Element B3: Stopping Flow/Bypassing/Purging
-
Written procedures available and followed on job site (as required)
-
Pre-job procedure review completed
-
Feed check performed (as required)
-
Appropriate by-pass procedures followed (as required)
-
Proper stopping gas flow procedures followed
-
Appropriate static control methods used
-
Proper purging procedure followed
-
Proper procedures followed
-
All changed documented (as required)
-
Any additional follow-up required
Element B4: Fused Connections
-
Fusion Type
-
Proper pipe preparation
-
Appropriate iron temperature
-
Acceptable configuration (line up)
-
Proper location of fittings in relation to other fittings
-
Appropriate cooling time observed
-
Acceptable visual appearance
-
Appropriate tapping procedures followed (as required)
-
Signature (fused connection)
-
Proper stencil and markings (e.g., stab depth, pipe preparation marks) present
-
Proper pipe restraint used
-
Soap test performed
-
No leakage found or appropriately addressed
-
Proper procedure followed
-
Any additional follow-up required
Element B5: Mechanical Connections
-
Describe Fitting Manufacturer and Model
-
Proper pipe preparation
-
Proper tooling used (e.g., chamfer, stab depth or torque wrench)
-
Correct torque setting used
-
Appropriate tapping procedures followed (as required)
-
Appropriate pipe coating used
-
Holiday detector used on repaired/new coating
-
Soap test performed
-
No leakage found or appropriately addressed
-
Proper procedures followed
-
Any additional follow-up required
Element B6: Welded Connections
-
Proper pipe/fitting preparation
-
Acceptable visual appearance of weld
-
Appropriate tapping procedures followed ( as required)
-
Soap test performed
-
Appropriate pipe coating
-
Holiday detector used on new or repaired coating
-
No leakage found or appropriately addressed
-
Proper procedures followed
-
Any additional follow-up required
Element C1: Meter Sets/Pressure
-
Proper handling/storage of meters observed
-
Design standards met
-
Meter properly supported
-
Acceptable meter location
-
Regulators set and functioning properly
-
Regulator properly vented
-
Appropriately painted (as required)
-
Access flow valve tag on meter set
-
FPU sticker on meter set
-
Leak test performed
-
No leakage found or appropriately addressed
-
Meter/meter components functioning properly
-
Relief set and functioning properly
-
Meter instrument functioning properly (e.g., corrector/ES3)
-
Meter removal procedure followed
-
Rotary meter installation procedures followed
-
Inlet valve operable
-
Filter/Strainer maintenance performed
-
By-pass locked as necessary
-
Sensing lines locked as necessary
-
Proper procedures followed
-
Any additional follow-up required
Element 2: District and Service Regulators Installation, Activation and Maintenance
-
District Regulator Station
-
Throttle inlet valve to clear debris from line and purge
-
Pilot regulators correctly installed
-
Proper bypass procedure followed
-
Relief set and functioning properly
-
Relief sensing lines locked in open position
-
Regulators set and functioning properly
-
Sense lines returned to normal position
-
Soap test performed (Leak test performed)
-
Appropriately painted or referral made (as required)
-
Appropriately valves operated or referral made (as required)
-
No leakage found or appropriately addressed
-
Appropriate protection installed or referral made (e.g., bollard, guardrail, fence)
-
Regulator properly vented
-
Proper procedures followed
-
Any additional follow-up required?