Machine Guarding
-
1. All rotating components, gears, shafts, and belts guarded?
-
2. Are all pinch points eliminated or guarded?
-
3. Type of guarding used? 3e. Scanner guard?
-
4. Are interlocks installed and operational w/ LOTO ability?
-
5. Do interlocks shut down cell?
-
6. Check palm button to restart
-
7. Are there lighting changes within the cell to inform TM's of
-
LOTO?
Controls
-
2. Anti-tie down / Anti-repeat?
-
3. Do the palm buttons have guards?
-
5. Are E-Stops in place, visible, and marked with red buttons?
-
6. Are there E-Stop Cables and is the cable red and accessible?
-
7. Are either style of E-Stop within reach of the operator?
-
8. Are Stack lights or operational lights used for the work cell?
-
9. Are the stack lights visible by the operator at the work cell?
-
Robotics
-
1. Does each Robot have an independent controller with an
-
E-Stop?
-
2. Is there an E-Stop on the teach pendent for each unit?
-
4. Do the robot(s) have amber lights installed?
-
5. Guarding types: 5e. Light Curtain?
-
6. Light curtain distance calculations available? (attach copy)
Control of Hazardous Energy
-
1. Is the machine or equipment capable of being Locked Out?
-
2. Is there an schematic drawing posted that indicates Lock
Out points?
-
7. Does the fence have gates with interlocks?
-
8. Has the control of hazardous light been accomplished? effective? (Can he or she see weld flash?)
-
9. Has the machine been reviewed for sound emission? 10 Are decibel readings acceptable?
-
12. Do the stored energy points have ID's and labels?
-
15. Are Lock Out hasps attached to gate?
-
16. Is there a picture of a proper lock out on each entry point?
Ergonomics
-
1. Was a design Ergonomic risk assessment completed?
-
2. Was there a build Ergonomic assessment completed?
-
3. Are working heights acceptable? 3b. What is the furthest reach?
-
4. Is operator position to tooling acceptable?
-
5. Is operator position to materials acceptable?
-
6. Is the operator lifting above 50 lbs?
-
7. Is there a lift assist in place?
-
10. Has a ERA or NIOSH calculations been completed?
-
11. Are carts used to deliver materials to cell?
-
12. Are Ergo mats in place?
-
13. Are tool rest required for tool storage between cycles?
-
14. Are tool balancers needed for tools?
-
15. Is lighting of work station adequate?
-
16. Has Ergonomic Ace been used to evaluate waste?
Physical Hazards
-
1. Have risk assessments been completed?
-
4. The Exits are identified?
-
7. All sharp corners have been identified and eliminated?
Electrical
-
2. Does each Electrical panel list - supply from and supply to?
-
4. Exposed wires, broken conduit,?
-
5. Are there any covers missing?
-
6. Are there any use of extension cords or surge protectors?
-
7. Are all switches on exterior of panels clearly marked?
-
8. Are there any 110 v plugs at the cell? 9 Are high voltage signs used?
-
10. is there a set of schematics available?
Color Codes
-
1. Is all piping labeled according to ANSI and Magna standard?
-
2. Are all Guards in caution yellow?
-
3. Are all moving parts in warning orange?
-
5. Are start buttons green?
-
6. Are containers, tankage properly labeled with content with
-
GHS labels and volume?
Exposure Issues
-
1. Are any vapors give off product or produced?
-
2. Are any gases given off or produced?
-
3. Is any dust produced?
-
4. IS there any mist given off or produced?
-
7. Will an IH air study be required?
Exposure Control Methods
-
1. Are local exhaust hoods used in the process?
-
2. Are Engineering dwgs available?
Fire Prevention and Protection
-
2. Are all fire protection equipment ID' s in RED?
-
3. Are all fire protection equipment accessible? 4h. Other substances not listed
Cranes & Hoists & Lift Assists
-
1. Load rated system, system capacity, posted ratings?
-
2. Pendants labeled, tagged?
-
3. E-stop buttons labeled and visible? movement?
Acoustics
-
Sign Off' s
-
Notes and Comments
-