Information

  • Audit Title

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Previous Audit Report

  • Has the previous audit report been closed out?

  • Have all previous issues been cleared?

Health & Safety Management Plan

  • Ensure the project QSE plan is up to date and signed by all relevant parties.

  • Is an emergency plan defined and in place complete with emergency contact numbers?

  • Has the plan been communicated to all parties, including sub-contractors.

  • Are responsibilities defined?

  • Are all FME Document present and meet Group requirements.

Risk Assessments and Method Statements

  • Ensure all Method Statements have been prepared by a competent person and have been checked, reviewed and signed.

  • Are method statements adequate and suitable for the task?

  • Does the method statement offer the necessary controls and required level of protection?

  • Ensure all contractors are working in accordance with the method statement.

  • Risk Assessments and Method Statements compliant?

Site Set up

  • Are the following items displayed?

  • Fire Plan?

  • Emergency plan and contacts?

  • First aid location signs?

  • Assembly point signs?

  • Accident reporting process?

  • No Smoking signs?

Induction

  • Ensure all staff receive a site specific safety induction before starting work.

  • Are all site induction records in safety file and up to date.

  • Ensure all staff who have been inducted display an induction sticker on their safety helmet or wear a photo identification badge.

  • Are all visitors including the client representatives being inducted?

  • Are site safety inductions being adequately carried out both for staff and visitors?

Consultation

  • Has a system been established for employees to comment and be consulted on health, safety and welfare issues.

  • Is there a site suggestion box?

  • Are any actions being implemented ?

  • Ensure appropriate Tool Box Talks are given to all employees and that the Tool Box Talks are appropriate and relevant to the work being undertaken.

  • Ensure that an attendance register has been maintained and signed by all persons present at each Tool Box Talk.

Management Controls

  • Have appropriate signs/notices been erected around the site i.e. mandatory use of PPE, Incomplete Scaffolds, No Smoking, Traffic Management, Fire assembly, Fist Aid Points etc.

  • Are all FME policies, memos and alerts on display in site office?

  • Are all incidents and accidents logged and reported in site safety file?

  • Ensure adequate supervision is provided for all activities on the site paying particular attention to work activities in high risk areas

  • Ensure that all persons are familiar with the requirements of the site safety rules and that they are complied with on site.

  • Ensure site safety rules are displayed in a prominent position e.g. reception, canteen, site office etc.

  • Ensure all subcontractors have been assessed and are adequately resourced and competent for the work they are undertaking.

First Aid

  • An appropriate number of trained and qualified first aiders should be available on the site.

  • Check the number of first aiders required, this is dependent on the type of work or operations, the number of workers on site and any special or unusual hazards.

  • Are the names of all first aiders detailed on the site notice board?

  • All first aiders should be clearly identified on site through the use of an appropriate helmet sticker.

  • Ensure the first aid kit contains only first aid materials.

  • The location of the first aid box should be indicated on the site notice board and the door of the room in which it is contained. Are they clearly indicated?

  • The First Aid box should be;

  • Marked with a white cross on a green background.

  • Be placed where it can be seen and used.

  • Be checked and replenished on a regular basis.

  • Are new staff made aware of its location as part of their induction?

Welfare Facilities

  • Mess facilities shall be of sufficient size for the number of employees on site.

  • Ensure access to the welfare facilities are accessible to all persons on the site.

  • Ensure a supply of wholesome drinking water and cups are provided.

  • Ensure that all drinking water supplies are appropriately signed.

  • Are pre-hydration sachets available on site.

  • Ensure sufficient toilets are readily available, maintained, kept clean & are properly lit.

  • Ensure there are washbasins, hot and cold running water, soap and towels.<br>

  • Are welfare facilities compliant?

Environmental Management

  • Have all practical measures been implemented to increase the energy efficiency of the site.

  • Carbon footprint measurement process in place?

  • Is an Environmental Emergency Plan in place?

  • Is it communicated via induction?

  • General Environmental Management

  • Are environmental guidance notes available on site?

  • Are any noise/dust issues present and are they being suitably controlled?

  • Is plant and equipment fitted with suitable and effective silencers?

  • Is an Aspects & Impacts register in place - risk prevention measures identified etc.?

  • Are spill kits available?

  • Located in the correct areas?

  • Staff and operatives aware of their location?

  • Have emergency drills taken place?

Fire Risks and Management

  • Is there a fire risk assessment in place?

  • Ensure there are emergency procedures for evacuating the site in case of a fire, flood, explosion etc.

  • Ensure all staff know what these procedures are and that they form part of the site induction.

  • Check that there is an adequate means of raising the alarm, and that it is regularly tested.

  • Ensure that there are adequate escape routes and that these are kept clear of obstructions.

  • Ensure that the quantity of flammable materials, liquids and gases are kept to a minimum and are adequately stored.

  • Ensure that smoking and other ignition sources are banned in areas where gases or flammable liquids are stored or used.

  • Check that flammable and combustible waste is removed regularly and stored in suitable bins and skips.

  • Check that suitable fire extinguishers are provided and that they are maintained and in a good condition.

  • Check that all fire extinguishers have had an annual inspection.

Traffic Management

  • Has a traffic management plan been prepared?

  • Are traffic management arrangement suitable and sufficient ?

  • Are pedestrians segregated from moving vehicles and plant?

  • Are storage areas identified?

  • Are loading areas identified?

  • Are procedures in place for the unloading of vehicles to prevent fall from vehicles?

  • Have one way or turning points been identified?

  • Are seat belts being used?

  • Are traffic management arrangement sutable?

Personal Protective Equipment (PPE)

  • PPE General Requirements - Ensure PPE compatibility issues have been considered and that one piece of PPE not restrict the effectiveness of another piece of PPE.

  • Ensure that PPE is issued on an individual basis.

  • Ensure that it is suitable for the type of work being undertaken.

  • Check that the PPE is marked with the genuine 'CE' mark to help identify type of protection.

  • Check that it is kept in good condition.

  • Ensure that it is appropriately replaced.

  • Ensure all staff and visitors are wearing the Freyssinet Group minimum PPE Requirement (safety shoes, helmet, hi-viz vest, glasses, gloves).

  • Eye Protection

  • Ensure that it is of a suitable grade for the type of work being undertaken. I.e. light protection or full goggle etc.

  • Check that it is kept in good condition.

  • Foot Protection

  • Ensure that footwear is fitted with steel toecaps and steel sole plates.

  • Ensure that footwear is manufactured to CE standards.

  • Hand Protection - Ensure that where damaged to the hands may occur through activities such as handling, or when using hazardous substances/chemicals that all persons affected wear the appropriate class of safety glove.

  • Are all gloves free from damage?

  • Ensure gloves are the correct size.

  • Ensure gloves are correct for their application and the activity being undertaken.

  • Check that hands are washed frequently after spells of work.

  • Check the availability of barrier creams and skin cleansers.

  • Hearing Protection

  • Ensure the correct type of protection is in use for the task.

  • Ensure that hearing protection is used as instructed.

  • Where ear plugs are in use ensure the correct size ear plugs are being worn.

  • Ensure that hearing protection is kept clean and checked regularly for damage.

  • Ensure Areas which are mandatory hearing protection zones are signed as such using the appropriate signs.

  • Respiratory Protection (RPE) - Avoid the use of nuisance dust masks.

  • Ensure that the correct type of respiratory equipment is used for the works being undertaken.

  • Ensure that persons are trained for the use of the RPE and where applicable have a face fit test to ensure the effectiveness of the RPE.

  • Ensure that all equipment is cleaned and checked after use.

  • Safety Helmets

  • Ensure all staff and visitors are wearing safety helmets.

  • Were all helmets found free from damage?

  • Ensure helmets are worn correctly.

  • Were helmets within their expiry date - helmets should be changed every 2-3 years.

  • When working at height are three point chin strap helmets being used?<br><br>

  • When required sun block should be supplied to employees in contact with direct sunlight

Housekeeping

  • Ensure all debris and waste is removed from the work area upon completion of the work or at the end of each shift.

  • Ensure Debris is not be allowed to collect around the FME work area.

  • Ensure staff adopt the philosophy of 'A tidy site is a safe site'.

  • Ensure materials are stored in an appropriate manner so as not to cause damage to or a weakening of the material.

  • Are All hazardous/flammable liquids contained within a bundled area/tank?

Waste Management

  • Is a waste management plan in place and sutable?

  • Ensure the plan is signed by all including the client/client representative?

  • Is the plan being maintained?

  • Is it being reviewed on a regular basis?

  • Are bins clearly labelled?

  • Are all waste carries and transfer stations records available?

  • Are waste transfare notes available and correctly filled in?

  • Is the process communicated via induction?

  • Waste management requirements compliant?

Access and Egress

  • Is there safe access and egress to all working areas of the site?

  • Have pedestrian walkways been provided to protect them from moving vehicles?

  • Are walkways free from obstructions and stored materials?

  • Are access routes adequatelly lit?

Access - External

  • Ensure site access points are clearly signposted on the approaches to the site.

  • Ensure adequate on-site signage is provided to warn and advise both vehicle drivers and pedestrians.

  • Ensure that there is always a clear access route to and from all parts of the site.

  • Have access routes been agreed with the main contractor prior to the commencement of work

  • If necessary has the use of traffic flag men to control traffic around site entrances been considered?

  • Ensure there are suitable barriers and warning notices to keep members of the public separated from the site works and site traffic.

  • Ensure safe pedestrian access is provided across all site entrances.

Control of Substances Hazardous to Health (COSHH)

  • Have COSSH Assessments been carried out for all potentially hazardous materials and substances being used on the site.

  • Are material safety data sheets available to assist with COSHH assessments.

  • Have the hazards associated with the use of such materials been properly communicated to those affected.

  • Are alternative safer substances available which can be used as substitutes.

  • Ensure all dangerous/hazardous materials/Substances are clearly marked/identified and stored in a secure location appropriate to the substance.

  • Have the appropriate control systems and PPE been provided and is the PPE being used.

Electrical Equipment

  • Check that low voltage tools and equipment are being used wherever possible.

  • Check that cables and leads are protected from damage.

  • Check all connections are properly made and suitable plugs are used.

  • Check that tools and equipment are visually checked and regularly inspected/tested by a competent person. (PAT)

  • Ensure that cables and trailing leads are not trip hazards.

  • Check that all temporary supplies are effectively bonded to Earth.

  • Ensure that suitable and sufficient task lighting is provided to enable operatives to safely carry out their work.

Lifting Operations/Equipment

  • Ensure a (competent) Appointed Person co-ordinates all lifting operations.

  • Have all lifting operation got a valid lifting plan?

  • Ensure that all lifting equipment has been tested and installed by a competent person and is regularly maintained and inspected.

  • Check that the operators are trained and competent.

  • Check that the rated capacity/safe working load is clearly marked.

  • Ensure that the lifting equipment is capable of lifting the heaviest component within the anticipated working radius - allow for sufficient spare capacity.

  • Ensure that cranes and other lifting equipment has sufficient space to operate safely.

  • All lifting equipment should have a thorough examination every 6 months.

  • Ensure lifting operations do not take place near overhead power lines and excavations.

Lone Working / Out of hours working

  • Is the work defined as low risk?

  • Is there a risk assessment for lone working?

  • Is access to first aid, welfare facilities and emergency services available to the worker/s?

  • Has the work been approved by the Construction Manager and reviewed by QSE Manager.

  • Lone Working compliant?

Manual Handling

  • Ensure that a manual handling risk assessment has been completed wherever regular lifting of heavy loads is required.

  • Check the suitability of using wheelbarrows, hoists, telehandlers and other plant or machinery so that manual handling of heavy objects is kept to a minimum.

  • Avoid the repetitive laying of heavy building blocks weighing more than 20KG.

  • Ensure all staff have received manual training.

  • Manual Handling compliant?

Occupational Health, HAV'S, Noise and Associated Health Risks

  • Check that workers have had information and training so that they know what the risks are from HAV.

  • Check that exposure to HAV has been reduced as much as possible by selecting suitable work methods and Plant.

  • Ensure reduced-vibration tools are used wherever possible.

  • Check vibration tools are properly maintained.

  • Noise - As a general rule, if you: - have to shout to be heard at a distance of 2m, the noise level is approx 85dB and you should consider wearing hearing protection.

  • - have to shout to be heard at a distance of 1m, the noise level is approx 90dB and you should definitely wear hearing protection.

  • Ensure that workers have had training so they are aware of the risks from noise on site and what they need to do to avoid these risks.

  • Check whether the noise can be reduced by using different working methods or selecting quieter plant e.g.: by fitting breakers and other plant or machinery with silencers.

  • Preventative maintenance can also help to reduce the noise caused by wear and tear on plant and machinery.

  • Ensure that people not involved in the work are kept away from the source of the noise.

Plant & Equipment

  • Ensure that tools and equipments are stored correctly to avoid damage to the equipment and persons.

  • Dry, covered and secure storage areas should be provided for all tools and equipment.

  • Hand tools

  • Ensure that the right tools and equipment are being used for the right job.

  • Were all hand tools found to be in good condition with no defects?

  • Power Tools

  • Ensure operatives have been trained to use the tools/equipment they are using.

  • Check that all dangerous parts are guarded e.g. gears, chain, drives, projecting engine shafts etc.

  • Check that guards are secure and in good repair.

  • Ensure that the tools are in a good state of repair.

  • Check the supply cable for cuts, splits or other damage. All all cables free from damage?

  • Ensure that all operators are trained and competent.

  • Ensure all Plant and Machinery is inspected on a weekly basis by a competent person and recorded in a Plant Inspection Register.

  • Are all plant operators trained and hold a valid plant operators card for the categories being operated?

  • Is Plant Used Correctly.

Scaffolding/Working platforms

  • Check that any scaffold erection, alteration or dismantling is carried out by a competent person.

  • Ensure that the scaffold is adequately tied to the building or structure to prevent collapse.

  • Check that double guard rails and toe boards or other suitable protection at every edge.

  • Check that working platforms are fully boarded and that the boards are arranged to avoid tipping or tripping - i.e.: no overlapping boards.

  • Are the working platforms supplied the correct width as per Freyssinet requirements (800-1000mm)

  • Ensure that there are effective warning notices in place to stop any person using an incomplete scaffold.

  • Check that the scaffold is strong enough to carry the weight of materials stored on it and that they are evenly distributed.

  • Ensure that the scaffold has been properly maintained.

  • Ensure that a competent person inspects the scaffold regularly, at least once a week; and always after it has been altered, damaged and following extreme weather.

  • Are scaffold tags being utilised?

  • Ensure that these inspections are adequately recorded.

  • Are all scaffolds and working platforms sutable?

  • Select date

Working at Height

  • Check whether the work can be undertaken without working at height.

  • Check that access equipment is erected by competent persons and checked before use.

  • Ensure safe access and egress have been provided to areas.

  • Ensure that edge protection is provided to stop people or materials falling.

  • Ensure that precautions have been taken to stop people falling through fragile materials when working on roofs, e.g.: by providing barriers, covers or working platforms.

  • Ensure roof ladders are used in accordance with best practice requirements.

  • Ensure that people are kept away from areas below the roof work.

  • Ensure that ladders are in good condition, are not split, warped or have damaged rungs etc.

  • Check whether ladders are suitable for the purpose - only for short term work or for gaining access to another area.

  • Check that ladders rest against a solid level surface and that this is not a fragile or insecure material.

  • Check that ladders are secured to prevent them slipping sideways or backwards.

  • Check that ladders rise a sufficient height above their landing place (approx. 1m or 5 rungs).

  • Safe landing platforms to be provided where a ladder rises to a height of 9m or more.

  • Are work at height operation in accordance with the W@H Regulations?

  • Add drawing

Other

Summary

Audit Risk Level

  • Risk rating for this Audit.

Corrective Actions

Sign off

  • I confirm I have had the contents of this audit report explained to me.

  • Site in charge

  • Person conducting this Audit.

  • Audit concluded at:

Closure

  • All actions on this report have been completed on:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.