Information
-
Job Complete?
-
Total time taken
-
Document No.
-
Reference:
-
Client / Site:
-
Location:
-
Date:
-
Prepared by:
General Details
-
SYSTEM HAS BEEN:
-
Type of system:
1. DESCRIPTION
-
Short description of carried works
2. INSTALLATION DETAILS
-
RECORDING EQUIPMENT INSTALLED?
-
Connection details IP addresses, ports etc...
-
CAMERAS INSTALLED?
-
Fully functional speed dome (PTZ)
-
Static camera
-
DETECTION EQUIPMENT (PIRs, PHOTO BEAMS...) INSTALLED?
-
Motion detector PIR
-
Photo beam
-
PA SYSTEM INSTALLED?
-
Amplifier
-
Horn Speaker
-
Paging microphone
-
COMMUNICATIONS EQUIPMENT INSTALLED?
-
3/4G Router
-
Connection details IP addresses, ports etc...
-
Ethernet router
-
Connection details IP addresses, ports etc...
-
WiFi point to point Link antenna
-
Connection details IP addresses, ports etc...
-
POWER SUPPLY UNIT (PSU) INSTALLED?
-
12VDC
-
24VAC
-
CCTV WARNING SIGN INSTALLED?
-
SITE CONNECTED TO MONITORING STATION?
-
Connection details IP addresses, ports, emails
-
OTHER EQUIPMENT INSTALLED?
1. DESCRIPTION
-
Short description of carried works
2. INSTALLATION DETAILS
-
MAIN SYSTEM PANEL INSTALLED?
-
WIRELESS CAMERA/PIR INSTALLED?
-
PA SYSTEM INSTALLED?
-
BATTERY FOR PA SYSTEM INSTALLED?
-
KEYPAD INSTALLED & HANDLED TO CLIENT?
-
KEY-FOB INSTALLED & HANDLED TO CLIENT?
-
SITE CONNECTED TO MONITORING STATION?
-
Connection details IP addresses, ports, emails, chip number etc...
-
OTHER EQUIPMENT INSTALLED?
-
CCTV WARNING SIGN INSTALLED?
1. DESCRIPTION
-
Short description of carried works
2. INSTALLATION DETAILS
-
MAIN SYSTEM PANEL INSTALLED?
-
CAMERA TOWER INSTALLED?
-
PA SYSTEM INSTALLED?
-
SITE CONNECTED TO MONITORING STATION?
-
Connection details IP addresses, ports, emails, chip number etc...
-
OTHER EQUIPMENT INSTALLED?
-
CCTV WARNING SIGN INSTALLED?
-
Type of system:
1. DESCRIPTION
-
CCTV System has been decommissioned. Decommissioning engineer/s removed equipment from site, counted and checked with client that equipment hasn't been damaged.
2. DECOMMISSIONING DETAILS
-
Recording equipment taken?
-
Power supplies taken?
-
Cameras taken?
-
PIR detectors taken?
-
PA equipment taken?
-
Communications equipment taken?
-
Any other equipment removed from site?
-
Site removed from monitoring?
-
Found damaged equipment?
-
Details
-
Pictures
1. DESCRIPTION
-
CCTV System has been decommissioned. Decommissioning engineer/s removed equipment from site, counted and checked with client that equipment hasn't been damaged.
DECOMMISSIONING DETAILS
-
Control panel taken?
-
Keypad taken?
-
Wireless Cameras/Detectors taken?
-
Key-fob taken?
-
PA equipment taken?
-
Any other equipment removed from site?
-
Site removed from monitoring?
-
Found damaged equipment?
-
Details
-
Pictures
1. DESCRIPTION
-
CCTV System has been decommissioned. Decommissioning engineer/s removed equipment from site, counted and checked with client that equipment hasn't been damaged.
2. DECOMMISSIONING DETAILS
-
Mobile tower taken?
-
Power supplies taken?
-
Cameras taken?
-
Any other equipment removed from site?
-
Site removed from monitoring?
-
Found damaged equipment?
-
Details
-
Pictures
1. FAULT DESCRIPTION
-
Short description of the fault
2. SERVICE DETAILS
-
Description of carried works
-
Parts installed?
-
Parts removed?
System Technical Specification
-
For permanent systems only.
3. SYSTEM TECHNICAL SPECIFICATION
Sign off
4. SIGN OFF
4.1 Engineer
-
Engineers notes:
-
I confirm that works has been done to client requirements and systems operates accordingly (Signed by Engineer):
4.2 Client
-
Client notes:
-
I confirm that the works stated above was done to my satisfaction. Sufficient instruction and training has been provided to ensure proper operation of the systems (Signed by client):