Title Page
-
Document No.
-
Audit Title
-
Job Number
-
Conducted on
-
Prepared by
-
Personnel
-
Basic Work Description:
-
Any Subcontractors?:
-
Buildings Work is being Performed:
-
GP Representatives for Current Projects:
1. General Information
-
1.1 Did any company representatives accompany the inspector?
-
1.2 Are all Safety/HazCom/Emergency Programs on site?
-
1.3 Are OSHA posters/Emergency numbers posted?
-
1.35 Are Daily JHA forms filled out?<br>AWS: <br>Subcontractors:
-
1.4 Are Confined Space Hazards identified and addressed - Permits Issued?<br>AWS:<br>Subcontractors:
-
1.5 Are Hot work Permits being used accordingly?<br>AWS:<br>Subcontractors: <br>
-
1.6 Are Gas Cylinders stored and used properly?
-
1.7 Are first aid kits available and properly stocked?
-
1.8 Are fire extinguishers available/charged/inspected?
-
1.9 Is Material storage proper?
-
1.10 Is housekeeping and sanitation proper?
-
1.11 Are flammable materials in approved containers and properly labeled?
-
1.12 Are all hand tools properly labeled/used/stored?
-
1.13 Are barricades around work and traffic proper?
2. Personal Protective Equipment (PPE)
-
2.1 Is all PPE provided by employer and readily available on site?
-
2.2 Is respiratory protection proper/silica standard enforced?
-
2.3 Is respiratory protection proper?
-
2.4 Is proper foot protection worn?
-
2.5 Is proper head protection worn?
-
2.6 Is proper eye protection worn?
-
2.7 Is hand protection/gloves proper?
3. Fall Protection
-
3.1 Are fall protection plans required and in place - Permits filled out?
-
3.2 Is fall protection provided at heights over 4 feet or site specific height?
-
3.25 Are Retractable lanyards being used in scissor lifts?
-
3.3 Is fall protection equipment inspected and maintained?
-
3.4 Are stairways protected and properly used?
-
3.5 Are ladders properly used and maintained?
-
3.6 Are all floor holes properly covered or protected?
4. Electrical
-
4.1 Are GFCI's in use?
-
4.2 Is temporary lighting used and proper?
-
4.3 Are lockout/tagout procedures in place and being used properly?
-
4.4 Are extension cords maintained/taped/hung and being used properly?
5. Scaffolding
-
5.1 Is a scaffold competent person on site?
-
5.4 Is fall protection provided for anyone working on scaffolding if required?
-
5.6 Are all scaffold frames pinned together?
-
5.7 Is scaffolding tied to structure using wire?
-
5.9 Are all work planks properly installed and free of damage?
-
5.10 Are all guardrails properly installed?
6. Heavy Equipment
-
6.1 Are all parts/equipment free of damage?
-
6.2 Are all guards in place and working properly?
-
6.3 Is all equipment maintained and inspected/documented?
-
6.4 Does all equipment have working Blue lights/backup alarms/flashing beacons?
-
6.5 Are all equipment operators trained/licensed?
-
6.6 Are seatbelts operative and in use?
-
6.7 Are aerial/scissor lifts properly used/documented/inspected?
-
6.8 Are forks on the ground when forklift is parked?
-
6.9 Is all equipment kept more than 10 feet away from overhead power lines?
7.0 Excavation/Trenching
-
7.1 Is the trench competent person on site?
-
7.2 Is the trench/excavation inspected daily?
-
7.3 Has proper soil analysis been completed?
-
7.4 Is employee protection proper for the type of soil/depth? (Trench Shoes,Shoring,Benching)
-
7.5 Is safe access/egress provided?
-
7.6 Are water removal procedures proper?
-
7.7 Has the trench been evaluated as a confined space?
-
Overall AWS Employee Notes:
-
Overall Subcontract Employee Notes:
-
Final Audit Notes:
-
8. Overall Rating for the Audit?
- Outstanding-No deficiencies
- Satisfactory-Minor issues
- Unsatisfactory-Major issues
-
Signature