SU Progress
Start Of SU Build & Completion
-
Is The Site Set up Correctly?
-
Are the G-Network Inserts And Permit Board's on Display on the barrier's.
-
Has The Contractor Got the Updated Su Design Map.
-
Are The Toby's Sprayed In The Correct postion As Per The Design.
-
Was A Walk Thorugh Of The SU Conduted With The Site Agent/Ganger.
- Yes
- No
- N/A
-
Are there any change's needed to the design. (Change Control)
-
Doe's the SU connect To Existing G.Network SU's If Not Instruct the contractor To Do So.
-
Are There Any other heath & Safety Issues You can see that need's addressing.
-
Are there any Other issues / complaint's From Resiedents/public.
- Yes
- No
- N/A
-
Are There Any Missing Asset's On This SU Build.
-
Are the parking bay suspension still in place after the street has finished if so how meny bays.
-
Mesurement After Build completed.
-
G.Network Designer Sign off
-