Title Page
-
Conducted on
-
Prepared by
-
Location
Asset Details For Reference
-
Asset Type e.g. manhole number, chainage etc.
Contractor(s) Onsite
-
Name of Contractors Visible Onsite
-
List the number of workers onsite and their trade i.e. Foreman, construction worker, traffic controller etc.
Plant Onsite
-
List the type and number of visible plant onsite.
Weather Condition
-
Weather
- Sunny
- Hot
- Cold
- Humid
- Overcast
- Rain (light)
- Rain (heavy)
- Windy
Works Being Performed
-
Type(s) Of Work
- Pipe Lining
- Steaming
- Junction Sealing
- Junction Cutting
- Pipe Cleaning
- End Sealing
- Civil Works
- CCTV
- Drilling
- Tunneling
- Pot Hole Excavation
- Other
Observations / Comments / Compliance
-
Has the Contractor performed and documented a pre-start?
-
Add media
-
Check that the Safe Work Method Statement (SWMS) / Work Method Statement (WMS) are onsite, relate to the work and have been implemented.
-
Add media
-
Have the required Traffic Management Plans (TMP’s) been approved by the relevant authority (Council, DTMR etc.)?
-
Add media
-
Are control measures in place (signs, barricading) for both public vehicle traffic and pedestrians, and are they in accordance with the approved TMP
-
Add media
-
Emergency procedures and plans are available
-
Add media
-
Check that the confined space entry permits and risk assessment have been filled out and implemented.
-
Add media
-
Local Govt. worker documentation completed (if works located in private property)
-
Add media
-
PPE in good condition and being worn?
-
Add media
-
Housekeeping adequate (including storage areas)?
-
Add media
-
Any safety or environmental concerns?
-
Add media
-
Photos taken of what, where, when and why.
-
Add media
-
Variations – Anything that needs to be recorded for information or proof of variations?
-
Add media
-
Any community or customer concerns?
-
Add media
-
Were there any discussions had or comments made that need to be documented?
-
Add media
Photos
-
Add media
Inspection Complete
-
Verified By (Signed)