Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Current version of plan set

  • Version of plans onsite

Site Conditions

  • Overview photos of site

  • Is the site neat and organized?

  • Is the site safe?

Racking

  • Is the racking installation complete?

  • Is the racking arranged per the latest plan set?

  • Is the racking installed straight and square?

  • Are connections fully engaged and torqued to manufacturers specifications?

  • Does this system have driven piers?

  • Are the piers located per plans?

  • Is pier installation complete?

  • Are piers plumb and straight?

  • Have piers passed pullout test?

  • Is this system ballasted?

  • Is ballast arraigned per plans?

  • Is ballast installation complete?

  • Does ballast meet ASTM C1491?

  • Does system require poured concrete foundations?

  • Are foundations installed per plans?

  • Has concrete passed compression tests?

Modules

  • Is module installation complete?

  • Are modules installed straight and square?

  • Are modules frames free from damage?

  • Is module glass free from damage?

  • Are module backsheets free from damage?

DC Wiring

  • Is module and source circuit (home run) wiring installed?

  • Is module wiring properly supported?

  • Is source circuit wiring properly supported?

  • Are field made module connectors of the same type as installed on modules?

  • Are conductors properly color coded?

  • Are conductors properly labeled?

  • Is DC raceway installed?

  • Does raceway specification match plans?

  • Is raceway located per plans?

  • Is raceway installed per plans and manufacturers specifications?

  • Is raceway properly grounded?

  • Is raceway properly labeled?

Equipment

  • Is equipment installed?

  • Are DC combiners installed?

  • Enter combiner identification

  • Photo of combiner

  • Is combiner location per plans?

  • Is combiner supported per plans and manufacturers specifications?

  • Does the combiner meet plan specifications?

  • Is combiner wired per plans and manufacturers specifications?

  • Is combiner properly grounded?

  • Is combiner properly labeled and identified?

  • Is combiner fused?

  • Enter fuse voltage rating

  • Enter fuse current rating

  • Enter fuse AIC rating

  • Are DC disconnects installed?

  • DC disconnect data

  • DC Disconnect
  • Enter disconnect identification

  • Photo of disconnect

  • Is disconnect located per plans?

  • Is disconnect supported per plans and manufacturers specifications?

  • Does the disconnect meet plan specifications?

  • Is disconnect wired per plans and manufacturers specifications?

  • Is disconnect properly grounded?

  • Is disconnect properly labeled and identified?

  • Is disconnect fused?

  • Enter voltage rating

  • Enter current rating

  • Enter AIC rating

  • Are AC disconnects installed?

  • AC disconnect data

  • Disconnect
  • Enter disconnect identification

  • Photo of disconnect

  • Is disconnect location per plans?

  • Is disconnect supported per plans and manufacturers specifications?

  • Is disconnect wired per plans and manufacturers specifications?

  • Is disconnect properly grounded?

  • Does the disconnect meet plan specifications?

  • Is disconnect properly labeled and identified?

  • Is disconnect fused?

  • Enter voltage rating

  • Enter current rating

  • Enter AIC rating

  • Are junction boxes installed?

  • Are junction boxes located per plans?

  • Are any additional junction boxes installed that are not on plans?

  • Do boxes meet plan specifications?

  • Are boxes installed per plans and manufacturers specifications?

  • Is box wired per plans and manufacturers specifications?

  • Are boxes properly grounded?

  • Are boxes properly labeled and identified?

  • Are inverters installed?

  • Enter information for each inverter

  • Inverter data
  • Enter inverter identification

  • Photo of inverter

  • Does inverter meet plan specifications?

  • Is inverter located per plans?

  • Is inverter installed per plans and manufacturers specifications?

  • Is inverter labeled per plans?

  • Is inverter properly grounded?

  • Is inverter wired per plans and manufacturers specifications?

  • Are aggregation panels installed?

  • Enter panel identification

  • Photo of panel

  • Is panel located per plans?

  • Is panel labeled per plans?

  • Is panel installed per plans and manufacturers specifications?

  • Is panel properly grounded?

  • Is panel wired per plans and NEC requirements?

  • Are switchboards installed?

  • Enter switchboard identification

  • Photo of switchboard

  • Is switchboard located per plans?

  • Is switchboard labeled per plans?

  • Is switchboard installed per plans and manufacturers specifications?

  • Is switchboard properly grounded?

  • Is switchboard wired per plans and NEC requirements?

  • Are transformers installed?

  • Enter transformers identification

  • Photo of transformers

  • Is transformers located per plans?

  • Is transformers labeled per plans?

  • Is transformers installed per plans and manufacturers specifications?

  • Is transformers properly grounded?

  • Is transformers wired per plans and NEC requirements?

AC Wiring

  • Are AC raceways complete?

  • Are raceways located per plans?

  • Does raceway meet plan specifications?

  • Is raceway properly grounded?

  • Is raceway properly labeled?

  • Is AC wire installation complete?

  • Does wiring match plan specifications?

  • Is wiring free from damage?

  • Are conductors properly color coded?

  • Are wires properly labeled?

Interconnection

  • Has interconnection been performed?

  • Is POCC located per plans?

  • Is POCC connection method per plans?

  • Is POCC properly labeled and identified?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.