Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
MANAGEMENT RESPONSIBILITIES
-
Has an emergency drill been held on site within the last 3 months? (Reg 314 and 43)
-
Is emergency contact information clearly displayed? (Reg 314 and 43)
-
Is there safe access and egress to and from all areas of site? (Reg 40 and 314)
-
Is the site office clearly marked with suitable signage to allow safe access for visitors? (Reg 314 and 43)
-
Is there suitable public protection where works are adjacent to boundaries, public access ways, roads, adjoining buildings etc? (Reg 315)
-
Is there records of weekly safety committee meetings and are site management involved?
-
Is there an elected Safety Representative on site?
-
Representatives Name & Company:
-
Are daily Pre-start meetings being carried out and do they communicate all issues to the workers?
-
Are all Safe Work Method Statements adequately reviewed onsite and are the workers in each activity trained and signed into the SWMS? (Reg 299, 312)
-
Are induction records complete and filed according to procedure? (Reg 315, 317)
-
Are all workers on site inducted and have signed into the Pre-start? (Reg 315, 317)
-
Have the required inspections and observations been completed and filed since last site audit?
-
Is all safety signage posted at the site entrance, in the site offices, lunch areas and throughout the site as required? (Regs 298, 308)
-
Have all visitors signed in and the register is up to date?
-
Does the site have all the required permits on site? (BA, Op Works, Footpath/ crossover/ road closure etc.)
-
Is a hazard register maintained on site and available for workers to view?
-
Have all hazards been closed out in a timely manner?
-
Are hazards reported in the toolbox and WPHS committee meetings?
-
Is the Safety Plan in place and available on site? (Reg 309-310)
-
Is a Emergency Plan in place and does it adequately describe evacuation procedures and testing of emergency equipment? (Reg 314 and 43)
ACCESS
-
Access ways (excessive water, trip hazards etc.)
-
Site shed, lunch shed and common areas clean and free of trip hazards, sharps and other items.
-
Lighting in walkways, storage areas and common areas.
-
Site vehicle and personnel entrances.
-
All openings and holes in the ground, slabs, formwork, scaffold etc. covered, secured and clearly marked.
-
Bin areas clean, chutes cleaned out and walkways clear of rubbish.
AMENITIES
-
Is the lunch room adequately sized for the maximum number of workers to use at any one time?
-
Is there washing facilities, lined rubbish bins, boiling water, chilled water and fridge space to store food?
-
Are toilet facilities clean and hygienic with adequate stocks of toilet paper and soap?
-
Is there a plumbed-in toilet connected on site if the sewer connection is available?
-
Is there enough toilets on site to accommodate 1 per 15 workers?
-
Is there are toilet located on ground level, fourth level and every subsequent third level? (where applicable)
-
Is clean and chilled drinking water available within 30m of every work face? On ground level and every second level after that? (Regs 41, 315a schedule 5a part 3 item 7)
-
Is there a clearly marked first aid location?
-
Is the first aid box adequately stocked and replenished when required?
-
Are all First Aid records filed on site?
-
Is there staff on site which are trained in First Aid?
-
Is there an emergency siren/ horn on site? (Regs 314, 41, 42)
-
Over-head services clearly marked, exclusion zone observed per Energex regulations.
-
Traffic Management plan in place and required road/ lane closures?
-
Are fire extinguishers adequately located and are they charged, tested and tagged?
-
Is there suitable shelter and seating in the lunch rooms for the number of workers on site? (Regs 41, Schedule 5a part 3 item 5 (1) and (2))
-
Is the lunch room clean, hygienic and separate from work activities?
ELECTRICAL
-
Are leads run on elevated hooks or away from access and egress paths, safe from mechanical damage and out of water?
-
No leads longer than 30m and not piggy-backed or in double plugs?
-
Are all leads correctly connected to temporary boards, and are the boards correctly mounted, weatherproof, with RCD protection and with lockable latches?
-
Is there an electrical testing register maintained on site?
-
Are any damaged, expired or non-tagged items removed from site?
-
All lead and electrical equipment in good condition, tested and tagged.
SCAFFOLD
-
Is there adequate bracing in all directions? (COP 6.2)
-
Are wall ties correctly positioned, every 3 bays, every 2 lifts? (COP 5.6)
-
Are there handrails, kickboards, working platforms and the like installed where falls of 2m or more are present? (Reg 306P)
-
Is there adequate protection from falling objects? (COP 4.5)
-
Is there adequate access to the working platforms and are they the correct distance from the work face? (COP 5.8-5.10)
-
Are only platform ladders being used?
-
Only double width trestles being used?
-
Are handover certificates signed at handover of each section of scaffold? (COP 8.3)
-
Are incomplete areas of scaffold excluded and correctly signed? (COP 4.5)
-
Are scaffolds regularly inspected and records kept on site?
-
Are scaffold standards founded in solid foundations with adequate sole boards, not undermined? (COP 5.4.1)
WORK AT HEIGHTS
-
Is engineered edge protection installed correctly where fall hazards exist, or are exclusion zones in place within 2.4m of an exposed edge?
-
Are Safe Work Method Statements (SWMS) in place for work at heights over 2m?
-
If harnesses are being used, are the personnel trained on the use of? Are the harnesses inspected and in good condition? Are the anchor points installed and signed off by a competent person? Are procedures in place for emergency retrieval of fallen persons?
HAZARDOUS SUBSTANCES
-
Is a Hazardous Substances register maintained on site?
-
Are all containers adequately labelled?
-
Are storage areas provided to safely store substances as required?
-
Are procedures in place and equipment available to clean up spills or leakage of hazardous substances?
-
Are PPE, storage, handling and methodology guidelines from MSDS's incorporated into the SWMS for tasks using hazardous substances?
CRANES & RIGGING
-
Crane operators, riggers and dogmen used for all range operations?
-
Is there a safe working zone for all crane operations?
-
Condition of plan, and competency assessments completed for all cranes and rigging used on site, including records of all certificates, logbooks and licences.
-
Crane log book completed daily?
-
Crane set up on firm level ground, engineers specification and sign off where applicable.
PLANT AND EQUIPMENT
-
Are hoists correctly setup with adequate foundation and connections to the building, with overhead protection for operator.
-
Has the hoist operators qualifications and competency been assessed?
-
Are forklift operators licensed and trained for the specific type of forklift?
-
Are manufacturers instructions for load capacities in all directions marked on excavator?
-
Are roll protection mechanisms in place for all excavation equipment?
-
Are reverse and visual alarms audible and operating?
-
Are Elevated Work Platforms (EWP) logbooks and daily inspections completed and records kept on the machine?
-
Have all competency assessments been completed for all workers operating EWP's?
-
Are EWP's only used on level surfaces?
EXCAVATION & CONFINED SPACES
-
Is the site plan available and marked up to date with existing and new underground services?
-
Is there any confined space works being done? Has a confined space entry permit been completed and licensed workers used?
-
Are emergency procedures developed for confined space works?
-
Is emergency rescue equipment, gas monitoring equipment, radios etc. and trained personnel in place?
-
Are excavations isolated/ excluded with barriers and signage?
-
Are excavations greater than 1.5m deep battered, benched or shored to prevent collapse? Or has geotechnical advice as to stability been sought?
-
Has spoil, material and equipment been stored away from excavation edge?
-
Are dust control measures in place?
-
Are excavation permits completed for excavation works undertaken?
-
Current Dial Before You Dig (DBYD) plans in place and updated monthly?
HOT WORKS
-
Is fire fighting equipment located with bottles or at the work area?
-
Are flash back arresters fitted to the hand piece and bottles?
-
Are hoses in good condition?
-
Are welding screens used and adequate ventilation being used?
-
Are hot works permits in place and filed on site?
-
Are Oxy acetylene bottles stored upright and in a lockable trolley?
ENVIRONMENTAL
-
Fire ant materials removed to site within fire ant zone, in accordance with RMP?
-
Is CEMP in place and available on site?
-
Are dust suppression/ collection measures in places for cutting and grinding of silica based products or other harmful dusts?
-
Is a rubble strip in place, cleaned and maintained?
-
Is the roadway and pedestrian footpath clean of all mud, debris, trip hazards, potholes etc?
-
Are noise controls in place for loud works?
-
Are adequate silt control measures installed and maintained as per the Sediment Erosion Control Plan?
-
Fire ant inspections up to date and RMP in place?