Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Roof sheets extend into gutter 50mm
-
Screw lines straight and fixed at every 3rd rib and every 2nd rib at perimeter
-
No blown washers to screw
-
No dented/ creased/ scratched sheets
-
Ridge cappings straight with no buckles/ creases/ damage
-
Silicone applied neatly to joints
-
Secret gutters/ valleys/ flashings finished parallel
-
Flumes installed plumb and sealed properly
-
Screws not missing metal battens
-
Sheets not pressing down on fascia (5-10mm gap)
-
All barge cappings fixed with no damage to ends and joints trimmed neatly
-
No sunscreen residue left on roof sheets
-
No damage to gutters
-
No paint used on roof (no touching up of scratches, etc)
-
Sarking/ anticon to be lapped and taped 150mm min past ridge and at joins sarking / anicon finished into gutter
-
Gutters free from off cuts and screws
-
Screws used ITW class 4 zips
-
Fire batts/ flashing installed as per detail
SAFETY / HOUSEKEEPING
-
No sheet off cuts left in roof space
-
All left over material placed neatly on rubbish pile