Title Page

  • Document No.

  • Audit Title

  • Client / Site

  • Auditor

  • BY SIGNING THIS FORM, THE SITE SUPERVISOR AGREES THAT THESE OBSERVATIONS AND RECOMMENDATIONS ARE A TRUE REFLECTION OF THE FINDINGS OF THIS AUDIT.

  • Supervisor

  • Conducted on

  • Departure time

  • Personnel

  • Location
  • * THE FOLLOWING SECTION (1.0) MUST BE COMPLETED AND CONSIDERED SATISFACTORY BEFORE CONTINUING FURTHER WITH THIS AUDIT.

1.0 Preliminary Requirements

  • 1.1 Is there a valid ( I.e in date) ASB 5 Notification Form on site for the works to be audited

  • 1.2 Is there (or will there be) asbestos removal work or cleaning in progress within the enclosure during the audit.

  • 1.3 Is there provision to observe work practices within the enclosure by means of CCTV and / or viewing panel(s)

  • 1.4 Is there a site specific Plan of Work available on site for the works

  • 1.5 Is there a copy of the Company Standard Procedures version 4 / Generic Procedures available on site

  • 1.6 Is the Decontamination Unit fully functional in terms of power, ventilation and the provision of hot and cold running water for showering

  • 1.7 Identify all isolations that have been confirmed

  • Comments / Clarifications

  • * DO NOT PROCEED WITH THE AUDIT UNLESS EACH RESPONSE ABOVE IS AFFIRMATIVE. SHOULD ANYTHING ABOVE BE AMISS THAT CAN BE RECTIFIED IMMEDIATELY, THEN CONTINUE WITH THE AUDIT ONCE RECTIFIED.

    * SHOULD ANYTHING ABOVE BE AMISS THAT CANNOT BE RECTIFIED IMMEDIATELY THEN INFORM THE SUPERVISOR THAT THE AUDIT CANNOT CONTINUE.

    * INFORM THE COMPLIANCE MANAGER WITHOUT DELAY 029 2047 1040 THAT THE AUDIT COUL NOT BE CONTINUED AND STATE THE REASON(s)

2.0 ASB 5 Notification Form

  • 2.1 What form of asbestos containing material does the ASB 5 state is being worked upon

  • 2.2 What is the approximate extent of the works stated in the ASB 5

  • square m

  • Linear m

  • No of bags

  • 2.3 What is the maximum number of employees per shift stated on the ASB 5

  • How many operatives (including the supervisor) are on the site

3.0 Site Documentation

  • 3.1 Is the Contract Supervisor the same person as specified in the plan of work

  • 3.2 Does the plan of work detail whom the contractor is contracted

  • 3.3 Does the plan of work detail when the work is to be carried out? (Including start / finish times and weekend variations)

  • 3.4 Does the plan of work detail the analytical company providing the 4 stage clearance

  • 3.5 Does the plan of work detail who the analytical company is contracted to

  • 3.6 Does the plan of work detail the type of asbestos involved

  • 3.7 Does the plan of work detail the condition of the asbestos containing material to be removed

  • 3.8 Does the plan of work (or standard procedures) detail who is authorised to amend the plan of work

  • 3.9 Are welfare facilities detailed in the plan of work and are they available for use as described

  • 3.10 Does the plan of work (or standard procedures) detail decontamination entry and exit procedures

  • 3.11 Does the plan of work (or standard procedures) detail the type of respirators to be used

  • 3.12 Does the plan of work (or standard procedures) detail the construction method for enclosures and air locks

  • 3.13 Does the plan of work (or standard procedures) detail the arrangements for smoke testing and witnessing

  • 3.14 Please record name / title of proposed witness

  • 3.15 Does the plan of work detail the asbestos removal technique to be used

  • 3.16 Does the plan of work detail the air monitoring arrangements for the duration of the works

  • 3.17 Is the scope of works adequately described in the plan of work, and does it match the details recorded on the ASB 5

  • 3.18 Is there a site specific risk assessment available for inspection for hazards other than asbestos? (Hot work, work at heights, use of hand tools, confined spaces, electricity, manual handling etc)

  • 3.19 Is there a set of COSHH assessments on site? (Smoke Fluid, Foam Spray Adhesive etc) NB Material Safety Data sheets on their own are insufficient

  • 3.20 Is there a copy of the current valid licence available for inspection

  • 3.21 Is there documented evidence on site confirming current insurance cover for both employers liability and public liability? E.g insurance schedule

  • 3.22 Are daily site and plant inspection records (including DCU, enclosure, air locks, NPU's & vacuum cleaners) available for inspection and up to date

  • 3.23 Does the NPU inspection record include manometer / pressure gauge readings for each NPU in use (including DCU)

  • 3.24 Has the smoke test record for the enclosure been completed and do the witness details match those stated in the plan of work ? (I.e as 3.14)

  • Comments / Clarifications

4.0 Site Supervisor and / or Operative(s)

  • 4.1 Supervisor's Name

  • In enclosure

  • Current Medical Certificate

  • Evidence of competence<br>Either RSPH Competence Certificate no more than 12 months old or current Training Certificate or evidence through Training Needs Analysis

  • Face fit test certificate for RPE in use

  • Examination record for RPE in use<br>Daily if in enclosure, current monthly if not

  • Adequate response when questioned regarding emergency procedure? (If not in enclosure)

  • Supervisor / Operative(s) Clean shaven. (If out of enclosure, or if seen before entry)

  • Operatives

  • Operative 4.2
  • 4.2 Name

  • In enclosure

  • Current Medical Certificate

  • Evidence of competence<br>Either RSPH Competence Certificate no more than 12 months old or current Training Certificate or evidence through Training Needs Analysis

  • Face fit test certificate for RPE in use

  • Examination record for RPE in use<br>Daily if in enclosure, current monthly if not

  • Adequate response when questioned regarding emergency procedure? (If not in enclosure)

  • Supervisor / Operative(s) Clean shaven. (If out of enclosure, or if seen before entry)

  • Comments / Clarifications

  • 4.3 For certificates where the name of HAS has not been recorded on the certificate.<br> Has each copy been individually authenticated by or under the direction of senior management, with a statement confirming their validity.

5.0 Site Organisation

  • 5.1 Does the sketch plan included in the plan of work match the site set up, including the positions of the NPU, air lock, bag lock (if applicable), viewing panels / CCTV and DCU as a minimum

  • 5.2 Do viewing panels and / or CCTV show all areas so far as is reasonably practicable

  • 5.3 Is each viewing panel (where applicable) at least 600 x 300 mm

  • 5.4 Are there adequate warning signs which comply with the Safety Signs and Signals Regulations? (Including the black hand prohibition symbol)

  • 5.5 Is there a suitably stocked First Aid Kit available on site

6.0 Plant on Site / Certification

  • 6.2 Are current DOP test certificates (or copies) available and relevant to each vacuum on site

  • 6.1 Are there at least 2 H-type vacuum cleaners on site

  • 6.3 Does the number and capacity of the NPU's in use correspond with that stated in the plan of work

  • 6.4 Are current DOP test certificates (or copies) available and relevant to each NPU on site

  • 6.5 Is there a current DOP test certificates ( or copy) available on site for the NPU within the dirty end of the DCU

  • Comments / Clarifications

7.0 Enclosure / Airlock

  • 7.1 Is the enclosure in sound condition and constructed so as to prevent the spread of asbestos

  • 7.2 Is the airlock free from visible asbestos debris

  • 7.3 Is a bucket and sponge (or similar) available for decontamination of respirator

  • 7.4 Are the airlock openings either oval or rectangular in shape

  • 7.5 Do the flaps cover the airlock openings adequately

  • 7.6 Are all the airlock flaps weighted

  • 7.7 Is each stage of the airlock at least 1m x 1m x 2m (height)

  • 7.8 If 7.7 is No was this variation justified in the Plan of Work

  • 7.9 Does the inner stage of the airlock have a viewing panel at least 600 x 300 mm

  • 7.10 If 7.9 is No, please indicate why not

  • Comments / Clarifications

8.0 Air Extraction Equipment

  • 8. 1 Is the extract sited in relation to ideal air management

  • 8.2 is the extract capable of providing either a minimum of 8 air changes per hour (enclosures > 120 cubic m) or airflow at least 1000 cubic m per hour for smaller enclosures

  • 8. 3 Is the extract vented to outside atmosphere where practical

  • 8. 4 Does each NPU have a non return flap on the exhaust side of the HEPA filter

  • Comments / Clarifications

9.0 Observed Work Practices

  • 9.1 Is the pre filter (or roving head) the only part of the NPU exposed to the working area ( I.e NPU sheeted out if inside enclosure)

  • 9.2 Does the RPE (including filter) being used, match that stated in plan of work

  • 9.3 Are all components of full face RPE uniquely identifiable ? E.g mask, blower and battery identified / marked / tagged with name or item / serial number.

  • 9.4 Are colours of coveralls as stated in the plan of work or standard procedures

  • 9.5 Are disposable working coveralls and transit coveralls 'category 3 type 5/6'

  • 9.6 Are all items of necessary PPE being properly worn? (E.g overalls not tucked into boots, overall hood headstraps etc)

  • 9.7 Does the dust suppression method being used match that stated in the plan of work

  • 9.8 Is the dust suppression method suitable for type of work or material? ( if needle injection machine used, please state manufacturer)

  • 9.9 Does the asbestos removal technique being used match that stated in the plan of work

  • 9.10 Has the waste been appropriately bagged? ( e.g immediately and single bagged if still in enclosure )

  • Comments / Clarifications

10.0 Hygiene Facility

  • 10.1 Is the unit positioned in relation to the work area as stated in the plan of work

  • Direct connection ?

  • Transit arrangement ?

  • 10.2 If the unit is not directly connected to the enclosure, would it have been reasonably practicable to do so

  • 10.3 Is the transit route as short as possible and away from occupied areas

  • 10.4 In addition to item 1.6 above, is the unit fully functional / in working order ? (Heating, lighting, water filter, drains etc)

  • 10.5 Are the internal doors and external door to the dirty end all fully self closing

  • 10.6 Is there an adequate number of shower heads for operatives ? (I.e at least one for every 4 operatives)

  • 10.7 Is there a nailbrush provided in the shower area

  • 10.8 Is the unit in good condition and clean so far as is reasonably practicable

  • 10.9 Are towels provided

  • 10.10 Are the clean end and dirty end doors marked (including prohibited entry and mandatory PPE signage, where required)

  • 10.11 Is there a clearance test certificate from the previous job, for the dirty and shower compartments of the hygiene unit

  • Date of DCU clearance test

  • Comments / Clearance

11.0 Waste

  • 11.1 Are the waste disposal arrangements as described in the plan of work

  • 11.2 Is the waste transit route free from residual or spilt waste

  • 11.3 Where applicable, is there sufficient means to segregate waste from equipment / supplies within the company vehicle

  • 11.4 Has a separate bag lock been provided

  • 11.5 If 11.4 is No, was this justified in the plan of work? ( NB "small amount of waste" is not a valid justification

  • 11.6 Is each stage of the bag lock at least 1m x 1m x 2m (height)

  • 11.7 If 11.6 is No was this variation justified in the Plan of a Work

  • 11.8 Is the bag lock free from visible asbestos debris

  • 11.9 Does the inner stage of the bag lock have a viewing panel at least 600 x 300mm

  • 11.10 If 11.9 is No please indicate why not

  • Comments / Clarifications

12.0 Company Vehicle(s)

  • Enter Reg, Make and Model

  • Vehicle 12.
  • 12.1 Reg, Make and model

  • Is the van reasonably tidy and with minimal risk of the spread of asbestos

  • Is the waste section free of all asbestos material

13.0 Scaffolding

  • 13.1 Is the asbestos removal contractor using any scaffolding on site

  • 13.2 Was a subcontractor used to erect the scaffolding

  • Severn Scaffold Division utilised

  • 13.3 Was the scaffolding liable to disturb asbestos while being erected

  • Name the subcontractor and write down their licence number

14.0 Further Comments / Clarifications

  • Did you note any new hazards not previously identified

  • Please list the hazards

  • Have these hazards been controlled, Status is ?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.