  • Do you have a sealed drawing for this pour?

  • Is shoring installed the same as the sealed drawing?

  • Is shoring visually plumb?

  • Is the column hung jack base in the location according to drawing?

  • Does screwjack extension meet the sealed drawing requirements?

  • Are spans by the sealed drawing?

  • Is the stringer still used the same as shown on drawing?

  • Is joist spacing by the drawing?

  • Are the joists used the same on the drawing?

  • Are two (2) 1-1/4" dia threaded rod w hex nuts and washers connecting the jack base to column?

  • Are all threaded rods w nuts and washers tightened to snug fit?

  • Are all pins of the Transverse Truss in place?

  • Are all clamps connection joist to truss properly installed and in place?

  • Are all pins of the Castellite Beam in place?

  • Are all lifting brackets of the Castellite Beam in place?

  • Is the connection between Transverse Beam and Castellite Beam as shown on drawing?

  • Columns reached 100% of specified 28 day strength?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.