Title Page

  • Conducted on

  • Prepared by

  • ITP Ref No:

  • Level:

  • Area:

  • Zone / Room:

  • Drawing No:

  • Revision No:

  • Calibration Report No:

  • Date Calibrated:

  • Calibration Expiry

  • Service Type:

  • Direction of Flow Correct

  • Material Type:

  • Identification Labels Correct

  • (For HDPE / Poly refer to AS2566 Appendix M for test procedure)

  • Pipework visually inspected for damage and there are no open ends

  • Pressure limiting valves, hot water heaters, TMV's and equipment disconnected or isolated prior to test

  • Pipeline filled with water and water flushed

  • Pipeline filled with water and air blend from system

  • Testing in accordance with AS3500.1 Clause 18:37

  • Test Commenced at:

  • Pressure reading at commencement:

  • Test Completed at:

  • Pressure reading at completion:

  • Test

  • Minimum test time is 30 minutes @ 1500 KPA or 1.5 times working pressure

  • Test witnessed on behalf of Client Representative:

  • Name:

  • Signature

  • Date & Time:

  • Test carried out by:

  • Signature

  • Walls can be closed:

  • Ceilings can be closed:

  • Trenches can be backfilled:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.