Title Page
-
Conducted on
-
Prepared by
-
ITP Ref No:
-
Level:
-
Area:
-
Zone / Room:
-
Drawing No:
-
Revision No:
-
Calibration Report No:
-
Date Calibrated:
-
Calibration Expiry
-
Service Type:
- Cold Water
- Hot Water
- Non Potable
- Warm Water
-
Direction of Flow Correct
-
Material Type:
-
Identification Labels Correct
-
(For HDPE / Poly refer to AS2566 Appendix M for test procedure)
-
Pipework visually inspected for damage and there are no open ends
-
Pressure limiting valves, hot water heaters, TMV's and equipment disconnected or isolated prior to test
-
Pipeline filled with water and water flushed
-
Pipeline filled with water and air blend from system
-
Testing in accordance with AS3500.1 Clause 18:37
-
Test Commenced at:
-
Pressure reading at commencement:
-
Test Completed at:
-
Pressure reading at completion:
-
Test
-
Minimum test time is 30 minutes @ 1500 KPA or 1.5 times working pressure
-
Test witnessed on behalf of Client Representative:
-
Name:
-
Signature
-
Date & Time:
-
Test carried out by:
-
Signature
-
Walls can be closed:
-
Ceilings can be closed:
-
Trenches can be backfilled: