Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Project
-
Select date
Drainage
-
All expansion joints properly aligned, anchored & tabs off?
-
All drainage trap arms are properly secured and graded?
-
All drainage clean outs are tightened with pipe dope(cast pipe only)
-
Location of clean outs?
-
All drainage tested?
-
Laundry boxes secured as per spec?
-
Kitchen sink rough-ins in proper location. ( Drainage 8" off centre-double sink. Drainage on centre - single sink.
-
Floor flanges pinned down/bolt hole orientation correct
-
W/C is 12" from finished wall?
-
W/C is minimum 15" from sidewall/ tubs/cabinets?
-
All equipment has been checked for proper performance?
-
When testing in winter anti-freeze added to p-traps
-
All backing for fixtures are in place.
-
All upgrades installed.
Gas risers
-
All gas risers marked & tagged
-
All gas stub outs are secure, tested, painted and proper distance from wall depending on exterior finish.
-
Suite gas valves on inside wall/handles off valve and hung on valve body?
Heating & domestic water
-
Heating pipe is not in contact with structure/behind studs on concrete. At least 1/2" gap.
-
Heating loops are pulled and fire stopped/tapped off ends and blocked
-
All 2x4's are cutout for heating runs at least 1/2" above and below
-
All heating stub outs installed?
-
All heating stubbed out 1-1/2" out from face of drywall and 3" from floor to centre of pipe.
-
All backing for H2O risers are in place
-
Water lines and water valves are in proper locations and flagged for drywallers
-
Location of water headers and recirculating valves marked for as-builts
-
Water valves fit inside walls
-
Water properly secured
-
Water mains tested
-
Water suite distribution is tested for leaks and crossed lines
Protection
-
Protection plates installed ( heating, gas, H2O, trap arms)
-
Riser clamps are installed and in wall and retightened.
-
Pipe insulation has been completed & trimmed to allow for expansion and contraction to lesson noise.
-
All h2o and heating piping wrapped with dishwasher hose to protect against Steele stud.
-
Pressure left in lines after testing.
-
All valves on slab on grade (handles removed and hung by valve)
Fixtures
-
Tubs properly levelled and shimmed
-
Tub and shower valves rough in heights/centred properly on tubs and showers(spout 6" above tub, valve and shower head- site specific) and diverted is at proper depth in wall.
-
Shower valves have 1/2" nipple in shower head.
-
Waste overflow has been tightened
-
Waste overflow trim kits on.
-
I hereby certify that I have inspected the above and found all items to be equal to or above required standars. Position: