Part I - Application<br>Phần I - Thông Tin

  • Hotwork Permit No.

  • Applicant: Tenant/Contractor Bên Đăng Ký: Tenant/Nhà Thầu

  • Contact Work Supervisor (Lessee/Contractor) Tên Giám Sát (Khách Thuê/Nhà Thầu) - Yêu cầu có số điện thoại liên hệ khi cần

  • Designated Work Area Vị trí khu vực thi công nóng
  • Permit Validation Duration - Start Date

  • Permit Validation Duration - End Date

  • Work Brief Description

  • Conducted on

  • Prepared by

Part II Work Preparation Checklist

  • 1. The operator is competent for the task (e.g. certificate, experience, ability etc.,)

  • 2. A fire watchman is assigned to supervise the whole work process, until 30 mins after the work is completed.

  • 3. The work safety (fire prevention) and emergency response training evidence are trackable.

  • 4. All equipment/tools involved in the task are free of obvious defects.

  • 5. The written fire risk analysis and mitigation measures are approved by the facility management team.

  • 6. The approved written work method statement/Job safety analysis has communicated with the worker

  • 7. Work area is clear and there is no flammable material within 10 meter of the hot work area. Otherwise, fire barriers or welding curtains or other acceptable measure must be in place to prevent the spark/slag contact with the flammable material.

  • Work area is clear and there is no flammable material within 10 meter of the hot work area. Otherwise, fire barriers or welding curtains or other acceptable measure must be in place to prevent the spark/slag contact with the flammable material.

  • 8. A fire extinguisher is kept at the work area for the whole work duration.

  • 9. Security center & security patrol team are informed.

  • 10. The equipment, electric cable and other devices nearby the hot work area are protected adequately (if any)

  • 11. Proper personal protection equipment is provided for the worker. E.g. insulating gloves, safety goggles etc.,

  • 12. All other safety measures described in Job safety analysis/work method statement are in place

  • 13 The following requirements must be 100% fulfilled If any compressed gas cylinder is involved:<br>- Cylinder are well secured; Regulators, hoses, flashback arrestors are functional well;<br>- Oxygen and acetylene cylinders are kept at least 6.0 meters apart, and 10 meters away from open flame;<br>

  • We have attended work safety training, understand fire and injury prevention and emergency treatment, confirmed that working conditions are as described in the work instruction, and promised to strictly follow the work instruction and PPE policy.

  • After on-site inspection, it has been confirmed that all fire and injury risk mitigation measures (include but not limited to Item 1 to 13) are sufficient and effective, the risk is acceptable, and we promise to ensure that the risk will be under control by monitoring the work process. Therefore, we are formally requesting that the landlord can approve this task.

Worker (Signature):

  • Name/signoff:

  • Date:

Fire Watchman (Signature):

  • Name/signoff:

  • Date:

Supervisor of Applicant (Signature):

  • Name/signoff:

  • Date:

Tenant’s Site Representative (Signature):

  • Name/signoff:

  • Date:

Part III Endorsement and Approval

  • 1. The fire and critical injury prevention measures are in place as described in the JSA/WI, and acceptable.

  • 2. Sprinkler system and other fire prevention function are well; or <br>The fire system impairment permit is approved

  • 3. Periodical security patrol is arranged (hourly/bi-hourly).

  • 4. Special measures are in place to prevent any false alarm/mis-action of the fire system. (fire system impairment permit shall be approved if needed)

  • 5. CNSH (Cainiao Smart Hub) Fire Safety and/or Hot Work safety requirements are fully followed

  • 6. CNSH HQ (Cainiao Smart Hub HQ) Safety Team has been consulted prior to work commencement on:<br>- Hot work happens on warehouse roof<br>- Hot work happens inside of water tank, septic pit.<br>- Hot work happens on diesel supply system<br>- Any PU or similar material involved within the hot work process

  • After onsite checking the work safety condition, we confirmed that all asset protection and major injury prevention measures are in place and acceptable, and we officially approve this task.

Facility Management Leader (signature):

  • Name/signoff: Sơn

  • Date:

Property Management Leader (CAINIAO):

  • Name/signoff: Duy

  • Date:

Part IV Extension or Close

Extension Gia Hạn Thêm

  • Extended new Date

Supervisor of Applicant (Signature):

  • Name/signoff:

  • Date:

Facility Management Leader (Signature):

  • Name/signoff: Sơn

  • Date:

Close

  • I confirmed that all hot work is completed, and the permit shall be closed.

Facility Management Leader (Signature):

  • Name/signoff: Sơn

  • Date:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.