A - Actions from previous Inspections
The following questions apply to DNV GL inspections
-
A1- Have all actions from over 2 months ago been actioned?
-
A2- Have all actions from 2 months ago been actioned?
-
A3 - Have all actions from 1 month ago been actioned?
1 - Safe Steps
-
1a - Are access ways free from slip, trip, fall hazards?
-
1b - Are access ways clearly marked?
-
1c - Are floor openings suitably covered, secured and with clear signage or fenced off?
-
1d - Are sufficient rubbish bins provided and being used?
-
1e - Is site tidiness condition acceptable?
-
1f - Is material stacking and storage acceptable?
2 - Fire Prevention
-
2a - Are sufficient fire extinguishers / hoses provided and in working order?
-
2b - Are muster points clearly marked and sufficient in size?
-
2c - Are evacuation routes clearly marked?
-
2d - Are the means of raising fire alarm clearly posted and working effectively?
-
2e - Is emergency lighting sufficient and working effectively?
3 - Confined Space
-
3a - Is a permit to enter in place?
-
3b - Have possible sources of hazardous material or gas been isolated to prevent their entry into the confined space?
-
3c - Has a suitable atmospheric check been conducted?
-
3d - Is ventilation adequate?
-
3e - Is there an adequate communication procedure between those inside and outside the confined space?
-
3f - Is an adequate evacuation procedure in place?
-
3g - Is rescue equipment available and ready to use?
4 - Work at Height
-
4a - Are openings through which a person could fall adequately guarded?
-
4b - Is the open side of stair case provided with substantial hand rail?
-
4c - Are fall prevention measures as detailed in safety plan/method statement and (if applicable) permit to work at height?
-
4d - Is a fall arrest system used to prevent falls fit for purpose?
-
4e - Are anchor points for clipping lanyard clearly marked and tested?
-
4f - Is it clear that ladders may only be used for access and not for working on?
-
4g - Are ladders of suitable material, adequate strength and secured to prevent undue movement?
-
4h - Is scaffold constructed in accordance to the design?
-
4i - Is scaffold form 5 indicating condition in order and signed by CP & in date?
-
4j - Are arrangements in place to prevent material falling from height?
-
4k - Does the Scaffold conform to CSSR – schedule III?
5 - Lifting Operations
-
5a - Is there a lifting plan?
-
5b - Is lifting gear suitably colour coded?
-
5c - Are staff involved in lifting operations competent and authorised?
-
5d - Can it be demonstrated that the rigger checks for visible defects (such as deformation, cracks and broken strands) in lifting gear before each use?
-
5e - Are tag lines used?
-
5f - Are persons not involved in the lift kept at a safe distance?
-
5g - Has the path and final resting place of load been checked to ensure safety?
6 - Electricity
-
6a - Are electrical boxes locked to prevent access?
-
6b - Are electrical cables secured in such a way as to prevent damage?
-
6c - Is the general condition of electrical equipment good?
-
6d - Is the electrical distribution system safe and conforming to MTR standards?
-
6e - Is the person responsible for electrical distribution clearly identified and contact number?
-
6f - Are there sufficient 110V socket outlets available?
7 - Plant & Machinery
-
7a - Is plant adequately fenced off to prevent unauthorized access?
-
7b - Are emergency stop switches provided to electrical motors?
-
7c - Do signs adequately warn pedestrians not to enter plant operating areas?
-
7d - Is the plant operator competent?
-
7e - Is plant registered with a distinct number?
8 - Excavation
-
8a - Is a “permit to dig” system in place?
-
8b - Are under-ground utilities adequately identified?
-
8c - Do drawings indicate the location of underground utility services?
-
8d - Is the CP in attendance at ALL times during hand excavation – until discovery?
-
8e - Is adequate support provided to excavations deeper than 1.2m?
-
8f - Is adequate access / egress provided to excavations?
-
8g - Are barriers in place to prevent falls of people and plant?
-
8h - Are suitable and sufficient warning signs displayed?
-
8i - Has a form 4 been signed by a CP and is it in date?
9 - Falsework
-
9a - Is an approved method statement available at site?
-
9b - Is falsework compliant with method statement requirements?
-
9c - Has timber used in falsework been stress graded?
-
9d - Do adjustable struts or props comply with BS4074?
-
9e - Is the foundation protected against flooding or wash out by heavy rain?
-
9f - Is an effective permit-to-load & permit-to-unload system operating?
10 - Behaviour / Supervision
-
10a - Is adequate supervision available at site?
-
10b - Have workers been provided with a relevant pre-start safety briefing?
-
10c - Are workers wearing the PPE provided for their work and working environment?
-
10d - Are supervisors aware of the requirements of the relevant method statement?
11 - Lock Out / Tag Out Systems - LOTO
-
11a - If a LOTO system is required, are affected workers aware of the LOTO system?
-
11b - Can workers identify all hazardous energy sources on the equipment concerned?
-
11c - Is the lock suitable and sufficient and is the controller’s name identified?
12 - Working with Electrical Tools
-
12a - Are electrical hand tools limited to 110V?
-
12b - Are portable lights limited to 110V?
-
12c - Are electrical tools identifiable by a number?
-
12d - Are electrical tools registered?
-
12e - Do records show issue & inspection dates?
-
12f - Are guards on fans in good condition and adequate to prevent finger injury?
13 - Work over Water
-
13a - Is a boat and boatman nearby if there is a risk of falling into the sea?
-
13b - Are sufficient life buoys and recovery lines in place?
-
13c - Has a rescue plan been developed and tested?
-
13d - Do workers at risk of falling into water wear life vests?
-
13e - Are other water hazards covered by netting to protect against drowning?
14 - Tunnels
-
14a - Are fire extinguishers, hose reals and first aid boxes spaced at every 100m?
-
14b - Are emergency phones spaced at every 60m?
-
14c - Is there suitable segregation of pedestrians from vehicles and plant?
-
14d - Is sufficient drinking water provided with cups?
-
14e - Are sufficient rescue respirators provided and readily accessible?
-
14f - Are walkways provided for pedestrians to within 100m of work face?
-
14g - Is there strict control of smoking and fire hazards to prevent fire in tunnel?
-
14h - Are vehicles and plant in the tunnel maintained to MTR standard?
15 - Operational Railways
-
15a - Have MTR requirements for working near railways been implemented?
-
15b - Is the person in charge suitably trained and qualified to MTR requirements?
-
15c - Are barriers and signs in place to warn of the danger of works near railways?
-
15d - Is the “Contractor’s CP (Track)”on site at all times?
-
15e - Is the “Contractor’s CP (non-track)” on site at all times?
16 - Public areas - Foot Paths
-
16a - Are members of the public suitably warned of dangers at site entrances?
-
16b - Are members of the public protected from falling material? Netting – fans etc.
-
16c - Are members of the public protected from vehicles entering and leaving site?
-
16d - Are members of the public adequately protected by hoarding, lights, paths etc.?
17 - Highways
-
17a - Are workers adequately protected from being struck by vehicles?
-
17b - Are sufficient banksmen used to ensure safe crossing of roads?
-
17c - Is entry / exit of vehicles adequately controlled?
18 - Work in Compressed Air
-
18a - Are CPs for Supervision and PIC of air supply on site during Compressed Air work?
-
Note : Refer to Cap 59M Regulation 5 and 6 (3) (b)
-
18b - Are there sufficient “Man lock attendants” on site?
-
Note : according to Regulation 10, minimum 3 lock attendants are required
-
18c - Do workers receive medical examinations as required?
-
18d - Do workers who have been working in compressed air wear their “Labels”?
19 - High Risk Operations – with Fire Risk
-
19a - Are hot-work permit conditions complied with?
-
19b - If required, is a “stand-by” person in attendance as specified?
-
19c - Are adequate precautions in place, such as welding screens, fire extinguishers?
-
19d - Are barriers and/or warning signs erected to prevent persons coming in contact with hot surfaces?
20 - High Risk Operations – Plant Erection / Dismantling, Mobilisation and Removal
-
20a - Are arrangements (e.g. warning signs, barriers, look-out man) in place to ensure high risk erection / dismantling is controlled?
-
20b - Are erection / dismantling procedures displayed at point of use?
-
20c - Is it clear that erection / dismantling must be under control of authorised person?
-
20d - Is transportation, loading and unloading suitably controlled and supervised?
-
20e - Is there a suitable method statement and risk assessment for this work and is it complied with?
21 - High Risk Operations – Demolition, Asbestos Removal, Diving etc.
-
21a - Are hazards, risks and precautions identified and documentation available at site?
-
21b - Have those persons at risk been adequately briefed as to risks and precautions?
-
21c - Is specialist PPE and equipment available and used as required?
-
21d - Are other required precautions in place and complied with?
22 - Special Hazards
-
22a - Guarding of machinery – Are hazards identified and is guarding checked?
-
22b - Permit-to-move / Permit-to-operate – are hazards known and controlled?
-
22c - Speed limits – established and enforced?
-
22d - Does the ASLI work correctly? Is it checked weekly?
-
22e - Are lifting hooks fitted with a safety latch?
-
22f - Are safety “anti-collision” devices fitted when 2 or more tower cranes are close together?
23 - Hot Weather
-
23a - Has a “Hot weather” assessment been conducted?
-
23b - Have the recommended controls been implemented?
-
23c - Are workers informed of MTR hot weather requirements?
24 - Manual Handling
-
24a - Have Manual Handling hazards been identified?
-
24b - Are the weights of all items over 15kg displayed?
-
24c - Are Manual Handling “aids” provided and used effectively?
-
24d - Are items requiring “team lift” or “Do NOT lift by hand” clearly identified?
25 - Method statements
-
a - Is a suitable method statement available for each task with significant risk?
-
b - Is a copy of an approved method statement, readily available for supervisors and engineers responsible for the works?
-
c - Is there evidence that the method statement has been briefed to supervisors, engineers and workers assigned to the works?
-
d - Are the works being conducted in accordance with the method statement stipulated controls?
Closing - End of Inspection
Closure
-
All actions on this report have been completed on:
Sign off
-
I confirm I have had the contents of this audit report explained to me.
-
Project Manager
-
Person conducting this Audit.
-
Audit concluded at:
Corrective Actions
Audit Risk Level
-
Risk rating for this Audit.