Entry Portal, Entry Vestibule, & Signage – IMAX Auditorium #15

  • Wall patching visible above recessed wood base Action: Sand and paint, provide level 5 finish on all walls in portal per J9/A513

  • Action: Touchup paint needed at topright corner of door frame

  • Action: Paint unfinished recessed wood base, rightinsidefront of portal

  • ½” gypsum reveal between white walls and DI metal frame missing

  • 8. Poor paint transitions visible in light alcoves and ceiling light slot. Action: touchup paint as needed. Ensure correct paint, sheen, and color is used

  • Mitered corners of DI metal frame have gaps indicating frame installation is not square Slot lighting is visible through gaps Action: GC to confirm floor was leveled per A13/A510 and work with DI to determine how gaps in mitered corners may be corrected

  • Old can light locations in soffit above entry portal signage are not yet patched

  • “AMC” channel letters not illuminated at time of observation, and sign standoffs (or tape?) is visible from a distance

  • Approximately 12” of ceiling slot lighting, each side, is missing or not illuminated at time of observation. Action: GC to coordinate installation/fix with DI as needed

  • Existing floor tile is chipped in places at transition to new carpet, likely cause during demolitionconstruction

  • Throughout entry portal, vestibule, and corridor, new recessed LED can lights have white trim and should be black per note 2 in fixture legend on sheet E6. Action: Provide black trim rings

  • Action: Coordinate the cleaning/fix of any scuffs on DI metal entry portal frame with manufacturer in order that damage does not occur during cleaning

  • Action: ensure black entry portal floor carpet extends into light coves of DI metal frame per J1/A512

  • Action: Confirm/ensure IMAX ‘busstop’ poster case is installed per A280, two locations

  • Action: Install tensabarrier at inside of entry doors per A13/A510

  • Action: Install missing ceiling tile(s) inside of entry door

  • Damaged and dusty ceiling tiles and grid found in entry corridor

  • Exit sign near floor missing adjacent to trash alcove and at corridor turn

  • Missing blue light strip above trash cabinet

  • Carpet to VCT transition not installed at trash alcove

  • Wall base not installed in trash alcoves

  • Action: Sand smooth and paint trash alcove header and ceiling black (PP3)

  • Recessed LED cans in entry corridor, circuit P15/30 appear to be at full brightness (Re: E4)

  • Action: Correct carpet base ripple to left of trash alcove

  • Action: Remove construction adhesive from floor below tactile exit sign and FEC near entry door

Auditorium

  • Squeaks found in floor framing and/or floor sheathing

  • Significant squeaks in plywood in entry corridor near opening to auditorium

  • Aisle stair landing at row B, screenleft

  • In front of wheelchair location C3

  • Construction dust remains throughout space on floors and wall finishes, on faces and in corners and crevasses, especially around port windows. Action: Complete final clean as needed

  • Action: Touchup visible marred gypsum wall surfaces behind seats, etc

  • Action: Remove glue/adhesive from walls, floors, nosings throughout auditorium:

  • Head above auditorium entry opening

  • Floor/carpet base under projection window

  • Walls behind seats C1, G6, G11

  • Walls in front of seats A16, E19, G2

  • Wall at cross aisle stairs facing entry opening (2 locations)

  • Walls near Irwin seat control box

  • Floor at Row G landing, screenleft

  • Sidewall at row F Landing, screenleft

Carpet Base:

  • 12” tall carpet base is installed where wallmounted lighting is installed at 16” AFF

  • No carpet base installed at front and side face of screen platform

  • c. Carpet base cut at Row A steps for aisle light raceway, both sides of auditorium, but none installed. Action: patch/replace carpet base

  • Action: Correct ripple in carpet base in front of seat F4

  • Wall Covering (PWC1):

  • Action: remove visible staples behind seat C1 and front face of stair knee wall next to seat F1

  • Action: Patch wall covering at visible, unfinished wall at angled buildout near Irwin seat control box

  • Action: Install trim strip at bottom of wall covering behind seats B11 to B16

Wood wall caps:

  • Action: ensure all wood caps have 2 coats of specified paint, notably at side faces and overhang of wood cap

  • Gap found between wood cap and blocking of sloped aisle stair knee walls

  • Action: Fill, sand, and refinish unfilled cap joints found behind seat G17 for example. Touchup paint at cap damage caused by construction activities

  • Action: Touchup paint at metal exit door and frame as needed

General

  • Found stain on arm of seat H10

  • Action: Patch or otherwise conceal exposed floor surface with carpet between stair tread and sloped wall, 3rd or 4th tread above cross aisle, seatside of stairs

  • Tempo floormounted and stairmounted lighting strips and raceways:

  • Action: Completely clean black paint, adhesive and, construction dust from stairmounted lighting strips and raceways

  • Action: GC to confirm AMC has adjusted lighting levels to code minimum as needed

  • Wheelchair location numbers not installed

  • Wall mounted Htype lights on front end of aisle stair knee walls at cross aisle installed but not powered/illuminated on front

  • HLS light above/near entry opening into auditorium appears to be brighter than all others

  • HLS lights over aisle Row B aisle stairs, both sides of auditorium, minimally shine on side walls. Action: Fox to confirm locationaiming is optimized

  • Fabricwrapped acoustical wall panels:

  • Marred acoustical wall panel at screenleft side wall above landing of row D

  • Action: Install acoustical panel over screen deliver access panel

  • Action: Install missing thermostat at jbox between rows F&G, screen right – slit in wall panel fabric

  • Jbox(s) for tuning mics visible

  • Fire alarm/strobe device not reinstalled above exit door per E2

  • Convenience power outlets missing at (3) locations

  • As constructed, screen platform edge does not extend 3” beyond face of screen as detailed in M13/A620 which creates fall hazard

  • Action: confirm all ceiling tiles are correctly seated in grid, typical of two locations – left side wall above cross aisle and behind rearleft speaker

  • Action: Install missing ceiling tiles and/or tiles cut too small

  • Observed only 2 of 4 angled safety cables at frontleft pocketed speaker

Behind screen/screen frame:

  • Action: Remove stored materials and tools

  • 3 of 4 subs installed

  • Action: Install acoustical batt insulation at exposed/bare walls. Install total 4” at front wall, 2” at side walls per note on A210, A1/A230

  • Action: Anchor screen shaker equipment rack, similar to audio rack, per 4/S0.11

  • Action: Remove unused stored materials, equipment, and paint masking

  • Action: Close and secure all open junction boxes

  • Audio racks not anchored at time of observation

  • ACT ceiling remains open in places

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.