Punch List Walk Through
-
IMAX Punch List.
Entry Portal, Entry Vestibule, & Signage – IMAX Auditorium #15
-
Wall patching visible above recessed wood base Action: Sand and paint, provide level 5 finish on all walls in portal per J9/A513
-
Action: Touchup paint needed at topright corner of door frame
-
Action: Paint unfinished recessed wood base, rightinsidefront of portal
-
½” gypsum reveal between white walls and DI metal frame missing
-
8. Poor paint transitions visible in light alcoves and ceiling light slot. Action: touchup paint as needed. Ensure correct paint, sheen, and color is used
-
Mitered corners of DI metal frame have gaps indicating frame installation is not square Slot lighting is visible through gaps Action: GC to confirm floor was leveled per A13/A510 and work with DI to determine how gaps in mitered corners may be corrected
-
Old can light locations in soffit above entry portal signage are not yet patched
-
“AMC” channel letters not illuminated at time of observation, and sign standoffs (or tape?) is visible from a distance
-
Approximately 12” of ceiling slot lighting, each side, is missing or not illuminated at time of observation. Action: GC to coordinate installation/fix with DI as needed
-
Existing floor tile is chipped in places at transition to new carpet, likely cause during demolitionconstruction
-
Throughout entry portal, vestibule, and corridor, new recessed LED can lights have white trim and should be black per note 2 in fixture legend on sheet E6. Action: Provide black trim rings
-
Action: Coordinate the cleaning/fix of any scuffs on DI metal entry portal frame with manufacturer in order that damage does not occur during cleaning
-
Action: ensure black entry portal floor carpet extends into light coves of DI metal frame per J1/A512
-
Action: Confirm/ensure IMAX ‘busstop’ poster case is installed per A280, two locations
-
Action: Install tensabarrier at inside of entry doors per A13/A510
-
Action: Install missing ceiling tile(s) inside of entry door
-
Damaged and dusty ceiling tiles and grid found in entry corridor
-
Exit sign near floor missing adjacent to trash alcove and at corridor turn
-
Missing blue light strip above trash cabinet
-
Carpet to VCT transition not installed at trash alcove
-
Wall base not installed in trash alcoves
-
Action: Sand smooth and paint trash alcove header and ceiling black (PP3)
-
Recessed LED cans in entry corridor, circuit P15/30 appear to be at full brightness (Re: E4)
-
Action: Correct carpet base ripple to left of trash alcove
-
Action: Remove construction adhesive from floor below tactile exit sign and FEC near entry door
Auditorium
-
Squeaks found in floor framing and/or floor sheathing
-
Significant squeaks in plywood in entry corridor near opening to auditorium
-
Aisle stair landing at row B, screenleft
-
In front of wheelchair location C3
-
Construction dust remains throughout space on floors and wall finishes, on faces and in corners and crevasses, especially around port windows. Action: Complete final clean as needed
-
Action: Touchup visible marred gypsum wall surfaces behind seats, etc
-
Action: Remove glue/adhesive from walls, floors, nosings throughout auditorium:
-
Head above auditorium entry opening
-
Floor/carpet base under projection window
-
Walls behind seats C1, G6, G11
-
Walls in front of seats A16, E19, G2
-
Wall at cross aisle stairs facing entry opening (2 locations)
-
Walls near Irwin seat control box
-
Floor at Row G landing, screenleft
-
Sidewall at row F Landing, screenleft
Carpet Base:
-
12” tall carpet base is installed where wallmounted lighting is installed at 16” AFF
-
No carpet base installed at front and side face of screen platform
-
c. Carpet base cut at Row A steps for aisle light raceway, both sides of auditorium, but none installed. Action: patch/replace carpet base
-
Action: Correct ripple in carpet base in front of seat F4
-
Wall Covering (PWC1):
-
Action: remove visible staples behind seat C1 and front face of stair knee wall next to seat F1
-
Action: Patch wall covering at visible, unfinished wall at angled buildout near Irwin seat control box
-
Action: Install trim strip at bottom of wall covering behind seats B11 to B16
Wood wall caps:
-
Action: ensure all wood caps have 2 coats of specified paint, notably at side faces and overhang of wood cap
-
Gap found between wood cap and blocking of sloped aisle stair knee walls
-
Action: Fill, sand, and refinish unfilled cap joints found behind seat G17 for example. Touchup paint at cap damage caused by construction activities
-
Action: Touchup paint at metal exit door and frame as needed
General
-
Found stain on arm of seat H10
-
Action: Patch or otherwise conceal exposed floor surface with carpet between stair tread and sloped wall, 3rd or 4th tread above cross aisle, seatside of stairs
-
Tempo floormounted and stairmounted lighting strips and raceways:
-
Action: Completely clean black paint, adhesive and, construction dust from stairmounted lighting strips and raceways
-
Action: GC to confirm AMC has adjusted lighting levels to code minimum as needed
-
Wheelchair location numbers not installed
-
Wall mounted Htype lights on front end of aisle stair knee walls at cross aisle installed but not powered/illuminated on front
-
HLS light above/near entry opening into auditorium appears to be brighter than all others
-
HLS lights over aisle Row B aisle stairs, both sides of auditorium, minimally shine on side walls. Action: Fox to confirm locationaiming is optimized
-
Fabricwrapped acoustical wall panels:
-
Marred acoustical wall panel at screenleft side wall above landing of row D
-
Action: Install acoustical panel over screen deliver access panel
-
Action: Install missing thermostat at jbox between rows F&G, screen right – slit in wall panel fabric
-
Jbox(s) for tuning mics visible
-
Fire alarm/strobe device not reinstalled above exit door per E2
-
Convenience power outlets missing at (3) locations
-
As constructed, screen platform edge does not extend 3” beyond face of screen as detailed in M13/A620 which creates fall hazard
-
Action: confirm all ceiling tiles are correctly seated in grid, typical of two locations – left side wall above cross aisle and behind rearleft speaker
-
Action: Install missing ceiling tiles and/or tiles cut too small
-
Observed only 2 of 4 angled safety cables at frontleft pocketed speaker
Behind screen/screen frame:
-
Action: Remove stored materials and tools
-
3 of 4 subs installed
-
Action: Install acoustical batt insulation at exposed/bare walls. Install total 4” at front wall, 2” at side walls per note on A210, A1/A230
-
Action: Anchor screen shaker equipment rack, similar to audio rack, per 4/S0.11
-
Action: Remove unused stored materials, equipment, and paint masking
-
Action: Close and secure all open junction boxes
-
Audio racks not anchored at time of observation
-
ACT ceiling remains open in places