Information

  • Project Name: BRUCE HIGHWAY / PUMICESTONE ROAD INTERCHANGE UPGRADE PROJECT
    Contract Number: NCHD-2578
    Job Number: 250/10A/1
    Contractor: ACCIONA INFRASTRUCTURE
    SKM Project Reference: QB10496

  • Inspector - Bill Butler

Inspector Daily Diary

  • Project Name: BRUCE HIGHWAY / PUMICESTONE ROAD INTERCHANGE UPGRADE PROJECT
    Contract Number: NCHD-2578
    Job Number: 250/10A/1
    Contractor: ACCIONA INFRASTRUCTURE
    SKM Project Reference: QB10496

  • Select date

  • DAY TYPE

  • contract

  • public holiday

  • working

  • non working

  • WEATHER

  • dry

  • hot and dry

  • humid

  • windy

  • overcast

  • rain

  • RAIN

  • Rain: Overnight

  • Rain: All Day

  • Rain: Morning

  • Rain: Afternoon

  • Rain: Intermittent

  • Rain Start Time

  • Select date

  • Rain End Time

  • Select date

  • Rain Gauge Reading (mm)

  • Comments

  • SITE ACTIVITIES

  • SITE ACTIVITY No.1

  • Primary Activity

  • Control Line

  • Location Chainage

  • Labour Type & Number (Prefix S = Subcontractor)

  • Plant Type & Number (Prefix S = Subcontractor)

  • Hours

  • Idle

  • Photos

  • COMMENTS

  • SITE ACTIVITY No.2

  • Primary Activity

  • Control Line

  • Location Chainage

  • Labour Type & Number (Prefix S = Subcontractor)

  • Plant Type & Number (Prefix S = Subcontractor)

  • Hours

  • Idle

  • Photos

  • COMMENTS

  • SITE ACTIVITY No.3

  • Primary Activity

  • Control Line

  • Location Chainage

  • Labour Type & Number (Prefix S = Subcontractor)

  • Plant Type & Number (Prefix S = Subcontractor)

  • Hours

  • Idle

  • Photos

  • COMMENTS

  • SITE ACTIVITY No.4

  • Primary Activity

  • Control Line

  • Location Chainage

  • Labour Type & Number (Prefix S = Subcontractor)

  • Plant Type & Number (Prefix S = Subcontractor)

  • Hours

  • Idle

  • Photos

  • COMMENTS

  • SITE ACTIVITY No.5

  • Primary Activity

  • Control Line

  • Location Chainage

  • Labour Type & Number (Prefix S = Subcontractor)

  • Plant Type & Number (Prefix S = Subcontractor)

  • Hours

  • Idle

  • Photos

  • COMMENTS

  • SITE ACTIVITY No.6

  • Primary Activity

  • Control Line

  • Location Chainage

  • Labour Type & Number (Prefix S = Subcontractor)

  • Plant Type & Number (Prefix S = Subcontractor)

  • Hours

  • Idle

  • Photos

  • COMMENTS

  • SITE ACTIVITY No.7

  • Primary Activity

  • Control Line

  • Location Chainage

  • Labour Type & Number (Prefix S = Subcontractor)

  • Plant Type & Number (Prefix S = Subcontractor)

  • Hours

  • Idle

  • Photos

  • COMMENTS

  • SITE ACTIVITY No.8

  • Primary Activity

  • Control Line

  • Location Chainage

  • Labour Type & Number (Prefix S = Subcontractor)

  • Plant Type & Number (Prefix S = Subcontractor)

  • Hours

  • Idle

  • Photos

  • COMMENTS

  • SITE ACTIVITY No.9

  • Primary Activity

  • Control Line

  • Location Chainage

  • Labour Type & Number (Prefix S = Subcontractor)

  • Plant Type & Number (Prefix S = Subcontractor)

  • Hours

  • Idle

  • Photos

  • COMMENTS

  • SITE ACTIVITY No.10

  • Primary Activity

  • Control Line

  • Location Chainage

  • Labour Type & Number (Prefix S = Subcontractor)

  • Plant Type & Number (Prefix S = Subcontractor)

  • Hours

  • Idle

  • Photos

  • COMMENTS

  • DAILY NOTES

  • Delays & Reasons

  • Comments

  • Add media

  • Site Instructions Issues (SI)

  • Comments

  • Add media

  • Traffic / Safety Incidents

  • Comments

  • Add media

  • Unsuitable Material

  • Comments

  • Add media

  • Plant-related stand downs

  • Comments

  • Add media

  • Changes in Material

  • Comments

  • Add media

  • Visitors to site

  • Comments

  • Add media

  • Design Changes

  • Comments

  • Add media

  • Environmental Cultural Heritage Issues / Breaches

  • Comments

  • Add media

  • Surveys Performed

  • Comments

  • Add media

  • Construction Difficulties

  • Comments

  • Add media

  • Discussions / Meetings / Staff / Land Owners

  • Comments

  • Add media

  • Soil / Audit Tests Performed

  • Comments

  • Add media

  • PUP

  • Comments

  • Add media

  • Sketch

  • General Comments

  • NON CONFORMANCES AND CORRECTIVE ACTIONS

  • Non Conformance

  • Comments

  • Sketch

  • Add media

  • Corrective Action

  • Comments

  • Sketch

  • Add media

  • SIGNATURES

  • Inspector

  • Superintendent's Representative

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.