Title Page

  • The inspection is carried out on a fully assembled solar installation by Soolar by qualified personnel.

    If any action is needed, the action requirement is noted. After the action is taken, the inspection document is updated with a note of when the action was taken, and a new analysis is conducted to determine if the checkpoint can be approved.

  • Date

  • Installers full names:

  • Adress

Installation

  • Uploaded images of any damages prior to assembly.

  • Panels installed according to the layout (Picture of all panels visible required*).

  • Hooks installed with a maximum cc distance of 90cm. Double hooks at panel ends. Tightening torque 1.5Nm.

  • Last hook within 25cm from panel end.

  • Rail within the distance of 15cm-45cm from panel end.

  • Rails level adjusted. Tightening torque 6Nm.

  • Clamps screwed with a tightening torque of 4.5Nm.

  • No visual assembly damage on installed material or roof.

DC

  • Connection carried out in accordance with string diagram.

  • DC cables secured correctly under panels and not laid over sharp edges.

  • DC cables protected and sealed from the roof to the inverter.

  • MC4 connectors connected and properly tightened.

  • DC cables pulled down to inverter location.

  • DC cables correctly labeled and voltage measured.

Client

  • Customer's property left in good condition, with dismantled scaffolding and a clean yard.

  • Uploaded pictures of any damages caused during assembly.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.