Information

  • Audit Title

  • Customer/Client

  • Site Name

  • Site Number

  • Conducted on

  • Prepared by

  • Location

TOWER / SYSTEM INFORMATION

  • System Name?

  • Cooling tower or Evaporative Condensor?

  • How many towers make up the system?

  • Are all towers clearly identified and labelled?

  • Take Photographs of towers and identification.

  • Cooling Tower make?

  • Cooling tower model?

  • Cooling tower serial number?

  • System Volume (kL) ( estimated or calculate, refer to maintenance manual)?

  • Materials of construction - Cooling tower basin?

  • Materials of construction - condenser water pipe work?

  • Take photographs of basin and pipe work indicating current condition.

  • Is the EC clearly identified and labelled?

  • Take Photographs of EC and associated pipe work indicating current condition.

  • EC serial number?

  • EC manufacturer/make

  • EC Model?

  • EC Serial number?

  • System Volume?

  • Materials of construction - Basin and tower?

  • Is the WHS cooling tower certificate of registration displayed (Qld) OR DHS Registration number (Vic) ?

  • All no answers require a follow up action to be recommended. Add comments and actions required below.

  • Comments and actions required.

MAINTENANCE AND OPERATIONS MANUALS

  • Are CURRENT MSDS for each product on site located in the maintenance manual?

  • Are laminated MSDS located at chemical storage area?

  • Are current SMWS located in the maintenance manual?

  • Are all cooling tower cleaning and service reports on site?

  • Is the service register/log sheet up to date?

  • Does the customer / site have a specific log book requirement?

  • Is the Technician completing the BES requirements. (Ie all log entries are up to date?)

  • Photograph last pages (2) of BES log.

  • Is the maintenance manual suitably located?

  • Is there a weather proof cabinet for the maintenance manual?

  • Log book location?

  • Photograph of log book on site.

  • Are the test results for the last three months within range?

  • Has the technician made the correct adjustments?

  • Comments?

  • Are the past 12 months micro laboratory test certificates in the manual?

  • Is the contact information in the manual current and correct?

  • Update information:

  • Comments on manuals and improvements proposed?

STAGNANT WATER RISK

  • How many condenser water pumps are installed?

  • What is the changeover frequency and control method used to ensure these pumps are not dead legs?

  • Is there a balance line?

  • Can the drain line be easily drained and/or flushed?

  • Does the balance line have by-pass flow through it to ensure it is not a dead leg?

  • Take photographs of the balance lines and drain points.

  • Are there any dead legs in the system?

  • Take photographs of the dead legs in the system.

  • Stagnant water comments and improvements recommended?

OHS REQUIREMENTS

  • Is the electrical switch board clearly labelled to enable the plant to be safely shut down?

  • Is there a chemical spill kit available near the chemical storage area?

  • Is there an emergency eye washing facility in close proximity(<5m) to the chemical dosing systems?

  • Are PPE and hazard signs installed?

  • Does the site require a risk management plan due to location or other concerns?(kitchen exhaust, smoking areas, air intake)

  • Are all chemicals appropriately bunded?

  • Are all chemical drums and bundling correctly labelled?

  • Take Photographs of OHS check list items.

  • Comments and recommendations for OHS conditions and improvements.

TOWER CLEANING

  • Is a detailed shut down and start up procedure available on site?

  • Is there safe access to the cooling tower for cleaning?

  • Is there safe access to the top of the tower?

  • Why is it unsafe?

  • Take photos representing the lack of access.

  • From visual inspection, are the drift eliminators in good condition?

  • Take photographs of drift eliminators.

  • Are there any water leaks evident from the tower?

  • Describe leaks?

  • Take photographs of reported leaks.

  • Describe the general cleanliness of the CT internal surfaces?

  • Describe general condition of the tower internals?

  • Take photographs of tower internals.

  • Is the water distribution through the cooling tower balanced?

  • Describe general condition and cleanliness of the cooling tower components?

  • Photograph tower components to demonstrate current condition, include air intake louvres, splash guards and tower basin etc

  • Comments?

DOSING EQUIPMENT

  • Describe the general cleanliness of the tower and surrounds?

  • Photograph tower and surrounds.

  • Comments?

  • Equipment make?(Aquarius, Advantage, Digi etc)

  • Dosing controller model?(Digi AB, Digichem 2, Aquagard, Megatron SS etc)

  • Take photograph of dosing controller.

  • CHECK OPERATION OF ALL EQUIPMENT AND REPORT BELOW.

  • Biocides A pump tested, all operational?

  • Biocide B pump tested and operational?

  • Inhibitor dosing pump tested and operational?

  • Bromine tablet solenoid valve tested and operational?

  • Conductivity controller and solenoid tested and operational?

  • Is there a stand alone circulation pump installed for the dosing controller?

  • Circulation pump checked and operational?

  • Is the tower fitted with a side steam filter?

  • Record type of filter?

  • Take photograph/s of the side steam filter installations?

  • Does the system have a dedicated sample point?

  • Is the sample point clearly identified or labelled?

  • Take photograph of the sample point?

  • Is there a corrosion rack installed?

  • Is the coupon rack installed a 2 or 4 station rack?

  • Is the flow through the rack measurable? Ie is there a flow meter

  • Take photographs of corrosion racks and flow meters?

  • Are their chemical dosing pots for the closed systems?

  • Are the dosing pots clearly labelled?

  • Are the pipes feeding the dosing pot clearly identified as heating or chilled water?

  • Take a photograph of each dosing pot and pipe work.

  • Are there water meters installed on the cooling towers?

  • Are there bleed and or make up meters?

  • Is there a meter on each tower?

  • Are we required to record the meter readings?

  • Comments and recommendations?

DOSING EQUIPMENT SETTING

  • Conductivity set point?

  • Conductivity reading today?

  • Take photograph of conductivity screen?

  • ORP set point

  • ORP reading today?

  • Take photograph of ORP readout screen.

  • Inhibitor dosing pump and controller settings?

  • Biocides A (Primary) pump and timer settings?

  • Biocides B (secondary) pump and timer settings?

  • Does the system have a dispersant pump?

  • Dispersant pump and control settings?

  • Dispersant product in use?

  • Per bleed settings?

  • Bleed lockout settings?

  • Does the controller have automatic disinfection via ORP?

  • Record frequency?

  • Record duration?

  • ORP or mV setting?

  • Comments and recommendations?

END OF REPORT, SIGNATURES

  • Signature:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.