Information
-
Audit Title
-
Customer/Client
-
Site Name
-
Site Number
-
Conducted on
-
Prepared by
-
Location
TOWER / SYSTEM INFORMATION
-
System Name?
-
Are all towers clearly identified and labelled?
-
System volume (kL) - estimated or calculate, refer to maintenance manual.
-
Comments and actions required.
MAINTENANCE AND OPERATIONS MANUALS
-
Are CURRENT MSDS for each product on site located in the maintenance manual?
-
Are current SMWS located in the maintenance manual?
-
Are all cooling tower cleaning and service reports on site?
-
Is the service register/log sheet up to date?
-
Does the customer / site have a specific log book requirement?
-
Is the maintenance manual suitably located?
-
Is there a weather proof cabinet for the maintenance manual?
-
Are the past 12 months micro laboratory test certificates in the manual?
-
Is the contact information in the manual current and correct?
-
Update information:
-
Are the test results for the last three months within range?
-
Has the technician made the correct adjustments?
-
Comments?
-
Comments on manuals and improvements proposed?
STAGNANT WATER RISK
-
Are there any dead legs in the system?
-
Take photographs of the dead legs in the system.
OHS REQUIREMENTS
-
Is the electrical switch board clearly labelled to enable the plant to be safely shut down?
-
Is there a chemical spill kit available near the chemical storage area?
-
Is there an emergency eye washing facility in close proximity(<5m) to the chemical dosing systems?
-
Are PPE and hazard signs installed?
-
Are all chemicals appropriately bunded?
-
Are all chemical drums and bundling correctly labelled?
TOWER CLEANING
-
Is a detailed shut down and start up procedure available on site?
-
Is there safe access to the cooling tower for cleaning?
-
Is there safe access to the top of the tower?
-
Why is it unsafe?
-
From visual inspection, are the drift eliminators in good condition?
-
Are there any water leaks evident from the tower?
-
Describe leaks?
-
Describe the general cleanliness of the CT internal surfaces?
-
Describe general condition of the tower internals?
-
Is the water distribution through the cooling tower balanced?
-
Describe general condition and cleanliness of the cooling tower and components?
DOSING EQUIPMENT
-
Equipment make?(Aquarius, Advantage, Digi etc)
- Digichem
- Advantage
- Aquarius
- Hoffman
- LMI
- Prominent
-
Dosing controller model?(Digi AB, Digichem 2, Aquagard, Megatron SS etc)
- Digi AB
- Digi 2
- AT522
- Aquagard
- Megatron SS
- CTH1
-
CHECK OPERATION OF ALL EQUIPMENT AND REPORT BELOW.
-
Biocides A pump tested, all operational?
-
Biocide B pump tested and operational?
-
Inhibitor dosing pump tested and operational?
-
Bromine tablet solenoid valve tested and operational?
-
Conductivity controller and solenoid tested and operational?
-
Is there a stand alone circulation pump installed for the dosing controller?
-
Circulation pump checked and operational?
-
Is the tower fitted with a side steam filter?
-
Record type of filter?
-
Does the system have a dedicated sample point?
-
Is the sample point clearly identified or labelled?
DOSING EQUIPMENT SETTING
-
Conductivity set point?
-
Conductivity reading today?
-
ORP set point
-
ORP reading today?
-
Inhibitor dosing pump and controller settings?
-
Biocides A (Primary) pump and timer settings?
-
Biocides B (secondary) pump and timer settings?
-
Does the system have a dispersant pump?
-
Dispersant pump and control settings?
-
Dispersant product in use?
-
Pre bleed settings?
-
Bleed lockout settings?
-
Comments and recommendations?
END OF REPORT, SIGNATURES
-
Signature: