InterCHECK
A. Site Establishment - Housekeeping
-
Is this Section relevant?
-
A1. Is the work area tidy?
-
A2. Is pedestrian access around work site clearly identified and in place?
-
A3. Is the site properly barricaded and isolated from the general public?
-
A4. Are hoses secured, isolated and protected? Are mats in use?
-
A5. Are overhead hazards identified and isolated?
-
A6. Are air hose clamps secured and safety pin in place?
-
A7. Has the site been fully set up as per the requirements nominated in the Traffic Management Plan?
-
A8. Is the Traffic Plan operating effectively?
-
A9. Has the Traffic Management Plan been signed off by the Interflow crew leader and has the Traffic Plan number been recorded on the work pack?
-
A10. Is the Traffic Plan site specific and all relevant fields
B. Documentation
-
Is this section relevant?
-
B1. Has the work pack been signed off by all people on site including subcontractors?
-
B2. Are all controls identified and listed within work pack 2 - Hazard Identification?
-
B3. Have nominated controls for work scope as identified within the work method statement been implemented and identified as working effectively.
-
B4. Is there a Quality, Environment and Safety Management Plan readily available?
-
B5. Does the crew have access to required SDS information?
-
B6. Can crews located an immediate SDS that identifies first aid response or otherwise for chemicals being used?
-
B7. Has the Client control room been notified of the current work activity? Can this be verified?
-
B8. Is a Flow Management plan being used onsite?
-
Is the plan working effectively?
-
B9. Has the Crew Leader completed the daily flow management checklist as required in the flow plan?
-
ADVISE THE CREW LEADER TO STOP WORK - review risks and implemented controls along with complete the required checklist
-
B10. Are Manual Handling controls implemented and working effectively i.e. Use of mechanical aids?
C. Confined Space Entry
-
Is this section relevant?
-
C1. Has the confined space permit been completed?
-
C2. Have all confined space controls as identified on the permit been implemented and identified as working effectively?
-
C3. Can 'Hook-up' (to a rated/ tagged anchor point i.e. Tripod) or 'Cover-up' (security grate covering OPEN access chamber) be positively identified?
-
ADVISE CREW TO STOP WORK AND IMPLEMENT immediate controls to mitigate OPEN ACCESS chamber RISKS
-
C4. Is an SDS readily available (i.e. Access to Chemwatch) for chemicals identified on the confined space permit?
-
C5. Has the Standby person set up a mean of communication with the person in the confined space and emergency services?
-
C6. Has the gas test response 'Bump Test' been recorded on the Entry permit?
-
C7. Is the gas test response bottle in date?
-
C8. Can the crew demonstrate how to complete a bump test?
-
C9. Is ventilation (either natural or forced) implemented in line with the hazard identification checklist (Work pack 2) ?
-
C10. Has all confined space equipment been inspected and validated as being within test and tag currency?
-
C11. Is 'DANGER CONFINED SPACE' signage erected?
-
ADVISE CREW TO STOP WORK AND IMPLEMENT immediate controls to mitigate OPEN ACCESS chamber RISKS
-
C12. Is the Self Rescue Breathing unit available at the confined space?
-
C13. Has the rescue plan rehearsal been recorded on the work pack?
-
C14. Do crew members have individual Confined Space training tickets readily available onsite?
D. Plant and Equipment
-
Is this section relevant?
-
D1. Housekeeping - is all equipment, materials secured / stored correctly on or in the vehicle(s)?
-
D2. Are flammable liquids stored in correct containers and labelled? i.e. de-cantered products
-
D3. Is the fire extinguisher(s) available and verified as current within Test and Tag?
-
Items such as Eyewash need to be verified as not having expired - IF EXPIRED the items are to be replaced immediately, or the kit deemed/ tagged 'unserviceable'.
-
D4. Is the interflow Plant Inspection Checklist(s) available and complete?
-
D5. Is the First Aid kit available and in date ?
-
D6. Has the allocated driver(s) been signed off in the front of the plant checklist?
-
D7. Is the operators drivers license(s) appropriate and current for the vehicle being driven?
-
D8. Are all electrical leads/ RCD's and power tools currently tested and tagged?
-
D9. Are the portable generator sets protected by an RCD?
-
D10. Have lifting chains been Tested and Tagged?
-
D11. Is a tag line being used to direct/ guide equipment when being lifted?
-
D12. IF a Vehicle Loading Crane (VLC) is being used, is the operator trained and has he/she been deemed competent?
-
Select controls implemented by the Operator as evidence of understanding of associated risks
- Signage
- Identified Exclusion Zone
- Use of a Spotter
- Use of communication - Two way/ Hand Signals
- Prestart check performed on VLC
- All lifting equipment has been verfied as currently tested and tagged
- Crane outriggers have been deployed and postioned onto Dunnage
- Tag line is being used
- Understanding of COP Approach Distances to 'overhead assets'
E. Employees
-
Is this section relevant?
-
E1. Is eye protection worn at all times?
-
E2. Are Hard Hats and brims being worn
-
E3. Is hand protection available for use? i.e. attached to self with a clip?
-
Are these gloves serviceable and identified as correct type for task?
-
E4. Is high visibility clothing being worn?
-
E5. Is hearing protection available (on person) and being worn by all at risk? i.e. when jacking this includes the stand by person located above the access chamber
-
E6. Are hand washing facilities available? - Note: this includes both water and appropriate sanitizer/cleaner
-
E7. Is safety footwear in good condition and fastened accordingly?
-
E8. Are P2 masks available and being worn when required?
F. Excavation
-
Is this section relevant
-
F1. Are trenches 1.5m or more in depth benched, battered or shored?
-
F2. Do excavations have barriers or handrails in place to prevent falls?
-
F3. Are ladders secured in excavations and extend out of the excavation by 1m?
-
F4. Is the Excavation edge clear of spoil? i.e. positioned at least 900mm from excavation.
-
F5. Is excavated material protected by silt fencing?
-
F6. Are 25mm thick road plates secured with pins and the leading edge of the plate ramped with cold mix?
-
Does the road plate have and anti-skid surface?
G. Environmental
-
Is this section relevant?
-
G1. Is the Environmental Management Plan available and understood by all?
-
G2. Can fuels be identified as having adequate bunding?
-
G3. Are erosion and sediment control in place eg. Silt Fencing, Sand Bags, Silt Socks etc.?
-
G4. Is contaminated waste collected, disposed of and tracked accordingly?
-
G5. Are Emergency spill kit(s) available?
H. Subcontractor
-
Is this section relevant?
-
H1. Does the subcontractor understand the specific scope of work?
-
H2. Is the Contractor appropriately trained/ or have been deemed competent to complete the task?
-
Tickets and/or qualifications have been verified/Sighted? i.e. Construction Card
-
H3. Has the subcontractor signed onto the work pack and been involved in the Pre-start?
-
H4. Has the subcontractor and/or employees completed the Interflow induction?
-
WORK MUST BE IMMEDIATELY STOPPED - THE SUBCONTRACTOR(S) IS TO BE INDUCTED
-
I. Training
-
Is this section relevant?
-