Title Page
-
Document No:
-
Customer
-
Site Address
-
Date
-
Arrival Time
-
System Make & Model
-
Next Inspection due
-
% of system tested
-
False Alarms form last visit
Remote Signalling
-
Site Connected to ARC
-
System has been put on test at ARC
-
Test all ATS pins to ARC and ensure that ARC receives signals in correct order
-
Check operation of all ATS paths. Record results below
-
ATS Path
-
Do site require connection to ARC?
System Test & Inspection
-
General State of System
-
Tamper detection tested
-
Alarm Indication
-
Check Setting, & Unsetting functions at all keypads
-
Check Entry and Exit procedures (inc timers)
-
Check correct attributes assigned for all zones
-
Check all power supplies for correct voltage & current readings. Details following
-
Readings
-
Battery size Ah, Location & Installation date
-
Check correct functioning of all detectors and HD's
-
Check environmental conditions for adverse effects
-
Check correct operation of all WD's inc removal of SAB supply
-
Visual inspection carried out of all devices and wiring
-
Check CIE clock for correct date and time
-
Check system is 'off test' at ARC and out of Engineer's mode
Documentation for Site / System
-
System Log Book Present
-
Log Book up to Date
-
All Recorded Faults Rectified
-
Zone information upto date
-
Does the customer want a log book sent?
Test Completion
-
Test result
Signature
-
Engineers Signature
-
Customer Signature