Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Vehicles- Pre-Trip
-
1. A Pre-Trip inspection was conducted on vehicle before beginning the trip?
-
2. Up to date drivers log book- last duty status entered.
-
<br>3. A Journey management meeting was conducted and documented before beginning the trip?
-
4. Equipment and supplies are secured by a cargo net or properly strapped?
-
5. Tractor and trailer paperwork is in the tractor cab?
-
Registration current on trailer and tractor?
-
Annual inspection is current on tractor and trailer?
-
6. Spill kit in at least one vehicle.
-
7. Other?
Pre-Job safety Meeting
-
8. JSA was completed properly and signed by all crew members?
-
9. Job hazards identified based on services to be performed?
-
10. Responsibilities/ Task outlined and delegated to responsible person ?
-
11. Restricted work areas identified?
-
12. Emergency response plan in place and understood by all employees.
-
13. Evacuation/All-Clear alarms
-
14. SSE Assigned a mentor?
-
15. SIMOPS Coordinated through company man?
-
16. All personnel sign in / out when entering / exiting location?
-
17. Personnel using designated smoking areas?
-
18. Safety briefing/muster area designated?
-
19. 2 people on location trained in CPR/First aid?
-
20. 2 people trained in well control?
-
21. Personnel trained in H2S?
-
22. Other?
Mandatory Safety Equipment
-
23. FRC worn by all employees and properly (zipped up and sleeves rolled down)?
-
24. Hard hats? All employees
-
25. Safety glasses? All employees
-
26. Steel toe safety boots worn by all employees?
-
27. Hand protection/ gloves?
-
28. Hearing protection?
-
29. Safety Harness available? Inspected / Current
-
30. Safety harness lanyard in good condition? Inspected / Current
-
31. Gas monitors calibrated, inspected and being used properly? If required on location
-
32. Hard hats and safety glasses available for visitor?
-
33. Other?
Rig Up- General/Wellhead
-
34. Spotters used when backing equipment.
-
35. 20lbs Fire extinguisher located at the left front bumper of each piece of equipment.
-
36. Fall arrest system in use while in aerial lift.
-
37. Fall Arrest System used while working from heights greater than 4 feet.
-
38. Personnel using fork lift and aerial lift must have current certification cards
-
39. Fork lift inspected prior to use.
-
40. Seat belt used while operating fork lift
-
41. Ropes used on hammer wrenches
-
42. Iron certification current?
-
43. Hammer unions in good condition not mushroomed
-
44. Whip checks on iron? Rated for that pressure
-
45. Lubricators marked with pertinent serial number
-
46. Lubricator certification current
-
47. BOPs tested
-
48. Well head bolted properly all bolts in flange?
-
49. All personnel not involved with pressure testing outside of taped off areas
-
50. Caution tape around high pressure and crane working areas
-
51. Other?
Rig up- CT Unit
-
52. CT unit placed up wind from well
-
53. Steps leading to operators cab, secured, level, has handrail and keeper pins in place.
-
54. All railing in place and secured with keeper pins
-
55. All hydraulic hoses in good condition with no leaks
-
56. All pins and keepers in reel saddle
-
57. Only necessary personnel in area while rigging up
-
58. Injector gooseneck pinned?
-
Injector head / BOPS secured properly?
In CT unit operators cab
-
59. IPS Field safety manual available?
-
60. Emergency phone numbers posted and available.
-
61. MSDS'S in cabin for chemicals on site?
-
62. Copy of the emergency response plan posted. If not mentioned in JSA of if more than 10 IPS employees on location
-
63. First aid kit available and properly stocked?
-
64. Fire extinguisher monthly and annual current.
-
65. Good house keeping
-
66. Other?
Rig up N2 pump
-
67. Iron certification Current
-
68. Hammer union in good shape and not mushroomed
-
69. Steps leading to operators cab, secured, level, has handrail and keeper pins in place.
-
70. N2 PPE being used
-
71. Other
Rig up fluid pump
-
72. Steps leading to operators cab, secured, level, has handrail and keeper pins in place.
-
73. Iron certification current
-
74. Hammer union in good shape and not mushroomed
-
75. All chemical on well site clearly labeled with MSDS on site.
-
76. All bagged/bucketed material stacked properly
-
77. Assessment for respirator conducted
-
78. All personnel wearing proper PPE per MSDS
-
79. Other
Rig up Crane
-
80. Lift sling condition? Identification tags/label attached and readable?
-
81. Chains inspected and tagged grade 8 or higher
-
82. Tag lines inspected and used while lifting loads
-
83. Only one person signaling crane operator
-
84. Outriggers fully extended and pads under them
-
85. Outrigger floats secured with pad pin
-
86. Cones out to identify crane swing path
-
87. Hydraulic system has no apparent leaks
-
88. Air system has no audible leaks
-
89. Boom exhibits no damage to structure, wear to pads, boom stops or cylinder
-
90. Wire rope free of dirt, excess lube, kinks and spooled correctly
-
91. Block not damaged
-
92. No damage to the hook and it swivels freely
-
93. All guards in place
-
94. Handrails in place, secured and not damaged
-
95. Cab glass not cracked and wipers are functional.
-
96. Anti-two block in place and functioning
-
97. Light and horns are functional
Crane operators cab
-
98. 5# Fire Extinguisher in cabin? Monthly/annual inspection current
-
99. daily Crane inspection conducted and filled out?
-
100. Annual crane inspection is current
-
101. Crane operators manual
-
102. Crane load chart legible and visible to operator.
-
103. Crane hand signal chart visible to workers
-
104. Hand held wind speed indicator
-
105. Other
Job Execution
-
106. Supervisor/ PIC identified and in control
-
107. Employees working as a team?
-
108. Any equipment failures
-
Job started on time?
-
109. Regular check of equipment conducted?
-
110. Tools in good working order?
-
111. Trash picked up? Good housekeeping?
-
112. Any visible leaks on equipment? Contained?
-
113. Spill kit available in each unit?
-
114. Spill containment in place
-
115. Safety procedures followed
Outside of Equipment
-
116. Is equipment clean?
-
117. Fuel tanks, tank mounts, tank caps all attached and in good condition?
-
118. Fuel, Hydraulic and other tanks properly labeled
-
119. All drive belts and rotating lines have guards in place
-
120. All hoses on equipment in in good condition
-
121. wheel Chock blocks in vehicle?
-
Tire chains in vehicle?
-
122. Trailer plug and hitch secured and not damaged
-
123. Break away cable on light duty trailers connected and working properly
-
124. Tool boxes uncluttered and lids able to close and latch
-
125. Leaks on equipment
-
126. Other
Post Job Responsibilities
-
127. Area policed and cleaned up?
-
128. All spills cleaned up before leaving location.
-
129. Location left clean
-
130. Other?
Audit Comments
-
Supervisor comments.
-
Supervisor signature
-
Company man comments
-
Site auditor comments.
-
Site Auditor signature