Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Job site Administration

  • Emergency numbers / contacts posted

  • First aid kits available

  • Employees trained in first aid and CPR

  • Pre-task planning cards completed, focusing on hazards and exposures to specific tasks being performed

  • Project specific MSDS information available to employees

  • Job site personnel informed of accident procedures

Housekeeping

  • Aisles & stairs clear of obstacles

  • Aisles & stairs adequately lighted

  • Work areas orderly & generally clean

  • Adequate and clean drinking water clean

  • Disposable drinking cups available

  • Material stored properly

  • Waste containers of adequate sizes available

  • Trash bin available at cutting stations for cutoff material

  • Trash disposed of properly

Electrical / Utility

  • Temporary lighting properly guarded

  • Task lighting guarded with lens and cage

  • Electrical panels labeled HOT and covered

  • ISEC GFCI protection utilized - pigtails on every electrical item

  • Extension cords inspected & in good condition

Hand and Power Tools

  • Personal hand tools in good working order

  • Plugs and receptacles in good working order

  • Power tools inspected and tested before use

  • All mechanical safeguards in use

  • Magnetic shut-off switch utilized on all table saws

  • Stand-offs used where fence interferes with guard on all table saws

  • Depth of blade on all table saws set to correspond with material being cut

  • Handles not broke / splinter free

Equipment

  • Brakes, lights, signals and alarms operative

  • Daily check list / inspection of equipment ( fork lift, aerial lift, scissor lift )

  • Seat belts are being worn on equipment

  • Aerial lift & scissor lift - PPE being used

  • Personnel forbidden to move equipment in an elevated position (aerial lifts & scissor lift)

  • Personnel forbidden to ride material hoists

  • Cranes - swing radius protected

  • Rigging equipment inspected - tag showing

Barricades and fall protection

  • Floor openings planked or barricaded

  • Wall, roof openings covered or barricaded

  • Leading edges guarded

  • Guard rails in good condition

  • Fall protection used when exposed to fall potential of 6' or more

  • Floor holes greater than 2" in diameter covered

  • Drop offs or irregular walking surfaces flagged or noted for potential danger

  • Personal Fall Arrest Systems inspected before use

  • Proper and adequate anchor points in use

  • Employees trained in fall protection

Ladders

  • Ladders inspected & in good condition before using

  • Heavy duty ladders in use, type A1 or better

  • Ladders are being used properly

  • Side rails extend 36" above landings

  • Proper for task and secured

  • Step ladders fully open when in use

  • Placement of ladder safe

Scaffolding

  • All scaffolds inspected with checklist before each shift

  • All scaffolds plumbed and leveled

  • Are adequate sills, base plates, or locking wheels being used

  • If electrical power lines are near the scaffold, are precautions being taken

  • Do scaffold planks extend past their end supports not less than 6" and no more than 12"

  • Are guard rails and end rails in place

  • Are work levels fully decked

  • Are toe boards in use or are work areas below barricaded off

  • Are frames and panels braced by cross, horizontal, or diagonal braces

  • Do scaffolds have a (4:1) base to height ratio

  • Is fall protection being used in areas where required

  • Are scaffolds securely anchored at least every 30' of length and 25' in height

  • Is there an access ladder, steps or equivalent safe access to scaffold

  • Is the scaffold within its weight capacity

Environmental & chemical safety/controls

  • Hazard communication explained to personnel

  • MSDS available for all chemicals

  • Hazardous materials stored properly

  • Hazardous chemical containers properly labeled & identified

  • If required, is PPE available

  • Adequate ventilation provided

Fire prevention

  • Are safety cans being used and properly labeled

  • Propane tanks - barricade installed - labeled -(flammable,no smoking,fuel type)

  • Compressed gas cylinders secured-upright- protected from damage

  • Fire extinguishers immediately available and inspection current

PPE

  • Hard Hats worn 100% of the time

  • Gloves worn 100%, proper glove for cut resistance or dexterity as work demands

  • Face shields being used - cutting, chipping, and other operations

  • Eye protection - 100% safety glasses

  • Hearing protection available and being used

  • Safety harness and lanyards in good working condition

  • Safety vests or high visibility shirts in use

GC / Other trades violations putting ISEC and others at risk

ISEC warnings and violations

Location

  • Add location
  • Select date

  • Add media

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.