Title Page
-
Site ITP conducted - (Project Name & Address)
-
SOLIDFC/ITP
-
Conducted on
-
Conducted by
-
Head Contractor
-
Project
INSPECTION REPORT
-
Work Description
-
Are you in the possession of most current drawing set
Set-out and Excavation Works
-
Completed Surveyor setting out works
-
Has DBYD been done to identify services?
-
Confirmed Top Rl's and Bottom RL's of bored piers
-
Geotechnical Engineer has Inspected and approved to proceed
Pre-Pour Check List
-
Finish RL' s are confirmed
-
Concrete Mix - ( Include mix design code )
-
Concrete Volume
-
Concrete tests are booked
-
Concrete Pump is booked
Reinforcement
-
Structural Drawing Reference
-
Surface is clean and free of debris
-
Completed setting out works
-
Checked reinforcement Cover to concrete
-
Checked lap lengths
-
Checked Spacing
-
Installed all starter bars, Dowel bars
-
Engineer's inspection done and approved to proceed
-
Attach Structural engineers inspection report and photos of reinforcement rectification works
By signing below you acknowledge that all set-out, excavation, reinforcement and formwork meet your requirements and authorise Solid FC to proceed with concreting.
-
Date and time
-
Solid FC signed
-
Principal Contractor Signed
Post - Pour
-
Attach last concrete Docket
-
Attach Concrete Pump Docket
-
Attach Photos of work progress
-
Attach Building surveyour's report