Title Page

  • Site ITP conducted - (Project Name & Address)

  • SOLIDFC/ITP

  • Conducted on

  • Conducted by

  • Head Contractor

  • Project

INSPECTION REPORT

  • Work Description

  • Are you in the possession of most current drawing set

Set-out and Excavation Works

  • Completed Surveyor setting out works

  • Has DBYD been done to identify services?

  • Confirmed Top Rl's and Bottom RL's of bored piers

  • Geotechnical Engineer has Inspected and approved to proceed

Pre-Pour Check List

  • Finish RL' s are confirmed

  • Concrete Mix - ( Include mix design code )

  • Concrete Volume

  • Concrete tests are booked

  • Concrete Pump is booked

Reinforcement

  • Structural Drawing Reference

  • Surface is clean and free of debris

  • Completed setting out works

  • Checked reinforcement Cover to concrete

  • Checked lap lengths

  • Checked Spacing

  • Installed all starter bars, Dowel bars

  • Engineer's inspection done and approved to proceed

  • Attach Structural engineers inspection report and photos of reinforcement rectification works

By signing below you acknowledge that all set-out, excavation, reinforcement and formwork meet your requirements and authorise Solid FC to proceed with concreting.

  • Date and time

  • Solid FC signed

  • Principal Contractor Signed

Post - Pour

  • Attach last concrete Docket

  • Attach Concrete Pump Docket

  • Attach Photos of work progress

  • Attach Building surveyour's report

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.