Information

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

PRE-TASK PLANNING and BBS

  • Pre-task plan completed and discussed with all crew members

  • Pre-task plan updated if scope of work changes

  • Site specific safety plan reviewed

  • JHAs reviewed and signed

  • BBS Card/s assigned

PERSONAL PROTECTIVE EQUIPMENT (BPM ALL)

  • Hardhats worn at all times (SM 9.4)<br>

  • Proper hand/arm protection

  • Hearing protection used when required (SM 9.12)

  • Face shields when there is potential for flying objects or working overhead (SM 9.5)

  • Safety Glasses with Side-shields (SM 9.5)

  • Full Body Harness w/ Lanyard or Retractable where needed (SM 9.10)

HOT WORK (BPM 5, 7, 10 & 28)

  • Hot Work permit filled out, signed and posted

  • Fire Protection (extinguishers / fire blankets) (SM 12.2)

  • Fire extinguishers inspected and tagged (SM 12.3)

  • Welding shields in use

  • Cylinders secured and capped when not in use

  • Leads and Hoses in good condition (SM 12.6)

WALKING / WORKING SURFACES (BPM 3 & 31)

  • All floor openings and holes greater than 2" covered (SM 9.11.2)

  • Aisle ways are clear of tripping hazards such as ext. cords, welding leads and stored material

  • All leading edges with falls greater than 6' protected (SM 9.11)

  • Weld rods / all-thread stubs are placed in buckets or trash containers (SM 12.5)

  • Work area properly illuminated (SM 18.5)

  • Roof top work has proper fall protection system (SM 9.11)

MATERIAL LIFTING / HANDLING (BPM 12, 14, 26 & 30)

  • Employees are using proper lifting techniques

  • Slings and chokers in good condition

  • Shackles are used on multi-leg picks

  • Cranes, chain falls, come-alongs and air tuggers are properly sized and used correctly

SCAFFOLDS AND MAN-LIFTS (BPM 2, 20 & 11)

  • Handrails and toe-boards in place (SM 16.3)

  • Scaffolds have proper access and are tagged, dated and inspected by a competent person (SM 16.2, 16.4, 16.6)

  • Fall protection used in boom-lifts (SM 9.10)

  • Fall protection requirements for scissor lifts are being met (SM 9.10)

EXCAVATIONS (BPM 24)

  • 5 feet or more in depth - shored, sloped or benched (SM 7.14)

  • Spoils are a minimum of 2' from edge of the excavation (SM 7.9)

  • Excavations are inspected daily for any changes in working conditions (SM 7.10)

  • Entry permits are filled out and posted for excavations greater than 5 feet (SM 7.10)

  • Proper access / egress is provided (SM 7.4)

LADDERS (BPM 1)

  • All ladders are free of defects (SM 10.3)

  • Stepladders used only in the open and locked position ( SM 10.4)

  • Straight ladders are being used at proper angle (SM 10.4)

  • Straight ladders are equipped with safety feet and are secured to avoid displacement (SM 10.4)

  • Access to ladders free of debris and/or obstructions (SM 10.4)

POWER TOOLS (BPM 3, 4, 6, 8, 9, 23, 27, 34, 35 & 36)

  • Power cords in good condition (SM 18.3)

  • Guards and handles in place (SM 11.5)

  • Ground-fault interruption protection in place (SM 18.4)

Comments and Action Items

  • Comments

  • Action Items

SIGNATURES

  • SITE REPRESENTATIVE

  • AUDITOR

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.