Title Page
-
Project Name
-
Conducted on
-
Contractor Completing Audit
-
Person Completing Audit
Pre Install (H & S)
-
Are all installers wearing Branded High VIs and appropriate PPE
-
Advise why
-
Have all tools, plant, machinery, and access equipment been checked<br>and tested where applicable?
-
Advise reason
-
Is the work area and access to and from the work area safe, free from<br>obstructions, suitably protected from slips trips and falls and lit<br>correctly etc?
-
Advise why
-
Have all of the team attended and understood a suitable site<br>induction, signed the RAMS pack and have all safety information<br>readily available on site? e.g.: COSHH, asbestos register, etc?
-
advise why
-
Any other H & S Concerns?
-
advise concern
Existing Cabinets
-
Take a few pictures of existing Run in situ if applicable (Purely for Reference)
-
Existing cabinet asset number if applicable (repeat for each cabinet removed)
Existing cabinet asset number (repeat for each cabinet removed)
-
Write cabinet asset number
Cabinet Install Issues
-
Was there any delays on site
-
Advise Issue / Outcome?
-
Take Pictures if applicable
Second Fix
-
Is Second Fix Needed
-
What needs to be completed to finish install
-
Have Parts for Second fix been left on Site
-
Advise where parts are left
Cabinet Install - Detail
-
Case/Endwall Joints Pulled Tight, Gasket Fitted, Service Entries Sealed and all Fixings Installed?
-
Advise reason
-
Shelving / Brackets & Base Trays, Data Strip and Shelf Risers Complete ?
-
Advise reason
-
Pipe Upstands Fitted and Aligned?
-
Advise reason
-
Bumper Completed?
-
Advise reason
-
Canopies Complete and Aligned?
-
Advise reason
-
Endwalls Installed and as per Drawing?
-
Advise Reason
-
Swarf and Debris, cleaned away?
-
Advise Reason
-
Nightblind tensioning checked and adjusted?
-
Advise Reason
-
System Dividers and associated brackets complete and fitted?
-
Advise Reason
-
Siliconing complete and excess removed?
-
Advise Reason
-
Are the Control Trays in good order and without damange?
-
Advise Reason
-
Signage Brackets Fitted as per Drawing?
-
Advise Reason
-
Was Cabinet Drainage completed by Cabinet Installer?
-
Take general pictures of Drainage install including floor upstands
-
Has the Drainage been Leak tested?
-
Please advise why?
-
Are cabinets to planogram
-
Advise reason
-
Were all kickplate fitted
-
Take general pics of kickplates installed
Snagging
- Add tab per Cabinets snags
-
Take Picture of cabinet Serial No / Asset Tag
-
Advise Refrigeration Contractor Cabinet System No (If Known)
-
Advise reason for Snag
-
List missing Parts
-
Take Pictures if applicable
-
Note reason for damage
-
take pictures of damage
-
List Parts needed to complete
-
Note reason for damage
-
Take pictures of damage
-
List parts needed to complete
-
Who Damaged the cabinet
-
Take Picture of Damage
-
List parts needed to complete
undefined
Cabinet Install - General
-
No of cabinets installed
-
No of cabinet removed If applicable
-
Take General Pictures of Cabinet Install (The whole run giving a good impression of Install) Numerous Pictures
Add per Cabinet - Take Pictures of Serial No / Asset Tag and Face on
-
Cabinet Serial No, Asset Tag and Refrigeration System No
-
Note cabinet Asset Tag
-
Take picture Face on of Cabinet
-
Take Pictures of all End walls (A few pictures of each to show correct install and no damage etc)
-
Take general picture of areas surrounding the cabinets installed to prove site was left tidy
-
Advise name and Contractor who marked the floor to position cabinets?
Completion - Sign Off
-
Cabinet Installer SIgnature
-
Main Contractor Signature