Title Page

  • Site conducted

  • GeoOP job number

  • Client / Site

  • Conducted on

  • Prepared by

  • Location

Solar Module Details

  • PV module manufacturer and model number

  • Number of solar modules

  • String configurations

Inverter Details

    Inverter
  • Inverter manufacturer

  • Inverter model number

  • Inverter Serial Number

  • Number of MPPTs

Installation Checkoff

  • Array frame is certified to AS1170.2 for installation location

  • Array frame is installed to to manufacturers instructions

  • No galvanically dissimilar metals are in contact with the array frames or supports

  • Roof penetrations are suitably sealed and weatherproofed

  • PV wiring losses are less than 3% at the maximum current output of the array

  • Where PV array comprises multiple strings, string protection has been provided

  • Wiring is protected from mechanical damage and is appropriately supported

  • Weatherproof PV isolator mounted adjacent to array

  • All low voltage wiring has been installed by a licensed electrical tradesperson

  • All wiring has been tested and approved by a qualified electrical tradesperson

  • PV array isolator mounted adjacent to the inverter

  • Isolator is mounted on output of inverter

  • Lockable AC circuit breaker is mounted within the switchboard to act as the inverter main switch for the PV/inverter

  • Inverter is installed to manufacturers specification

  • Inverter ceases supplying power within 2 seconds of a loss of mains power

  • Inverter does not resume supplying power until mains have been present for more than 60 seconds

  • All labels are installed to CEC and Australian Standards

Continuity check

  • Continuity of all strings, sub-arrays and array cables

  • Continuity of all earth connections (including module frame)

Insulation resistance measurements

  • Array Positive to earth M ohm

  • Array negative to earth M ohm

System Commissioning check

  • String Test Results

  • String
  • String tilt and orientation

  • String polarity

  • Irradiance at time of testing

  • String measured Voc

  • String operating voltage

  • String measured Isc

  • String operating current

Anti Islanding Test

  • Time for inverter to disconnect is less than 2 seconds

  • Time for inverter to reconnect greater than 60 seconds

Installers Information

  • Name and CEC Accreditation number of Installer

  • CEC Designer and Installers signature

  • Name and Licence of Electrician

  • Electricians signature

undefined

  • Supply Requirements

  • Supply Phases

  • CT requirements

  • Off Peak Requirements

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.