Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Installation of insulation within SFS (if applicable)
-
Has EPS cut back flush with outside face of SFS
-
Is ther any voids within SFS/Timber frame have been packed with mineral wool insulation (Isover)
Installation of Y-Wall
-
Has the Boards been full fixed in line with manufactures direction
-
Are all joints have been sealed/taped
Installation of EPDM
-
Is EPDM fully bonded to existing window/existing EPDM
-
Is EPDM Fully bonded to Y-wall
Installation of VCL
-
Has it been installed in accordance with manufacturers details
-
Are all joints have been taped and sealed
Installation of Insulation
-
Is the Fixing pattern is in accordance with manufactures details
-
Are all voids been packed with mineral insulation (duo-slab)
Installation of Fire Breaks
-
Are Vertical fire breaks installed in accordance with construction issue drawings
-
Is there any compression on the fire break once the cladding has been reinstated
-
Are the vertical fire break installed in accordance with manufacturers details
-
Are the Horizontal fire breaks installed in accordance with construction issued drawings
-
Are the Horizontal fire beaks installed in accordance with manufacturers details
Installation of applicable wall covering
-
Are all items are installed line and level
-
Are all items are free of defects (other than that identified prior to removal)