LASER 2ND FIX QA SHEET
2ND FIX INSTALLATION
-
Downlights cut out and installed correctly, batten holders, Pendants and lamps fitted
-
All Fire and CO detection accessories (smoke detectors & bases, heat & bases, carbon monoxide detectors and bases ) Installed and 300mm away from all other accessories, and interlinking
-
Co2 Detector installed between 1m and 3m of the boiler
-
All (sockets outlets, spurs, cooker switches, grids, doorbell chime etc) Installed
-
All TV and BT accessories Installed - list missing items
-
All ventilation equipment, ( extract fans, diffusers, MVHR & MEV units etc.) Installed correctly
-
All loft roof accessories, batten holders, sockets, Installed
-
All consumer units ( breakers, blanks, busbar covers, labelling) Installed correctly
FINALS (2ND AND SUBSEQUENT VISITS)
-
All heating controls, ( thermostatts, cylinder statts, motorised valves, programmers, pumps, junction boxes, wiring centers, immersion supplys) Installed correctly
-
Power up, Functional Testing
-
Earthing & bonding installed, clamps fitted where applicable
-
All externals fitted, outside lights, grills, ev box
-
Garage complete, armoured cleated, spurs, switches, sockets and batten holders fitted
-