Title Page
APLNG - Field Delivery Lease Pad ERSED Inspection Checklist
-
Property:
-
Conducted on
-
Inspected By
-
Lease pad Type
- Yes
- No
- N/A
-
Number of Lease Pad:
-
ESCP Drawing Number:
-
Comments: (for site visits, note relevant information here and disregard below inspection items)
1.0 Lease pad Set Up
-
1.1 Site specific ESCP submitted and approved prior to works commencing
-
1.2 Confirm survey set out is completed and clearing limits identified
-
1.3 Topsoil stripping depth as per ESCP (mm)
-
1.4 Depth of which topsoil has been stripped (mm)
-
1.5 Topsoil stockpiled within lease perimeter that does not impede drilling activities, minimises any mixing with other materials and not within 100m of a watercourse
2.0 Water Diversion / Control
-
2.1 Clean and dirty water diversion banks installed prior to the commencement of bulk earth work and as per standard drawing and ESCP
-
2.2 Number of whoaboys:
-
2.3 Batter diversion banks to be constructed from compacted sub-soil, topsoiled and stabilised as per the ESCP requirements
-
2.4 Whoa boys are installed as per standard drawing and ESCP (including entrance WB where required)
-
2.5 Any sediment control installed are in correct location and as per ESCP (water to flow through and not diverted around)
-
Number of rock checks:
-
2.6 Is there water ponding or batters being scoured in any other area’s of the lease pad
-
If so, what preventative measures should be put in place?
3.0 Batter Chutes
-
3.1 Are Batter Chutes installed and energy dissipators located where indicated on the ESCP
-
Dimensions of each batter chute:
-
3.2 Energy dissipator/s correctly installed at the base of the Batter Chutes?
-
Dimension of each Energy Dissipator:
-
3.3 Geofab used and has been keyed in prior to rock chute installation
4.0 Outlet Controls
-
4.1 Coir logs are keyed in, installed correctly and functional
-
Number of Coir Logs:
-
4.2 Excavated sediment traps constructed and installed as per the standard drawing (Q-1000-15-DD-054) and sized as specified in ESCP (refer to table 3)
-
Sump Number and Size:
5.0 Soil Amelioration:
-
5.1 Soil amelioration implemented as per construction soil management plan
-
Pre-topsoil strip rate (t/ha):
-
Subsoil application rate (t/ha):
6.0 Completion of civil works
-
6.1 Lease constructed as per approved site specific Erosion and Sediment Control Plan
-
6.2 If changes to the approved plan are required they must be captured via red line mark ups and approved immediately. Note: Any changes to the approved ESCP require approval and sign-off by the Engineering team and the Environmental team.
7.0 Stabilising Batters and Rehabilitation
-
7.1 Roughen cut and fill batters parallel to slope, apply gypsum to batters (including batter diversion banks)
-
Gypsum application rate (t/ha):
-
7.2 Topsoil has been respread over batters to depth defined in the ESCP
-
Topsoil reinstatement depth (mm):
-
7.3 Polyacrylamide Soil Binder has been applied as per the requriements of the ESCP (refer to table 2)
-
Quantity (m2):
-
7.4 Seed and Fertiliser has been applied as per the requirements of the ESCP (Table 2)
-
Seed rate and mix (t/ha):
-
Fertiliser rate (t/ha):
-
7.5 Final surface is free draining and constructed in accordance with lease ESCP
-
7.6 Remove outlet controls, fill sediment traps and remove dirty water diversion banks. Note: Clean water diversion banks, catch drains, batter chutes and energy dissipators are to remain in place
Comments / Design Changes:
-
Comments
CPB Representative
-
Signature
-
Role:
Other Inspectors:
-
Signature:
-
Role: