Information

  • Document No.

  • Conducted on

  • Job Name

  • Job Number

  • Prepared by

  • Location

Division#2 - Sitework

  • Will you be working on sitework in the next 30 days or are you currently working on sitework? This includes Demo, Site Utilities, Piles and Caissons, Excavation, Paving, C &G, Sidewalks, Landscaping and Irrigation. If so click yes.

Site Demolition

  • Will you be working on Demolition in the next 30 days or are you currently working on Demo? If so click yes.

  • Did you review permit requirements and time required?

  • Is the adjacent property protected?

  • Is an existing conditions 3rd party survey required?

  • Are the existing utilities protected, have you notified them about your work? Check cut off requirements.

  • Have you checked blasting procedures, requirements, protective measures needed before proceeding?

  • Are tree guards in place and according to jurisdiction approved plans?

  • Are traffic control plans established for trucking and pedestrians?

  • Are there dust control and truck wash requirements? If so are they in place?

  • Have all underground fuel tanks purged?

  • Have the proper people been notified of work proceeding and hours?

  • Are there any hazardous materials?(asbestos, lead?)

Site Utilities

  • Will you be working on site utilities in the next 30 days or are you currently working on site utilities? If so click Yes.

  • Have you verified that elevations are correct(inverts, catch basins, storm and sanitary lines)?

  • Are valves and fire hydrant located exactly as per drawings?

  • Are conduits or sleeves required?(for site lighting, irrigation, telephone, cable, power)

  • Have you verified your trenches are safe?

  • Have you or a 3rd party verified trench and backfill requirements/compaction?

  • Has the geotech been notified to monitor?

  • Is the proper signage in place?

Piles and Caissons

  • Will you be working on Piles or Caissons in the next 60 days or are you currently working on Piles or Caissons? If so Click Yes.

  • Have you checked for displacement due to horizontal/vertical heave?

  • Have you allowed for possible vertical heave in pile-cap excavation?

  • Are you maintaining required separation between driving and concreting operations?

  • Are you maintaing driving logs/records?

  • Are you monitoring adjacent structures for damage?

  • Have you checked quantities and location for accuracy?

  • Did you verify anchor bolt locations?

  • Did you perform air test in caissons for toxic gases?

  • Has the geotech been notified to monitor?

  • Possible dirt/spoils removal. Where is this being disposed of and by whom?

Excavation

  • Will you be working on excavation in the next 30 days or are you currently working on excavation? If so click Yes.

  • Did you take pictures of adjoining structures.

  • Is erosion control in place and installed correctly(per plans)?

  • Has erosion control measures been inspected by the local jurisdiction?

  • Is burning authorized? If so do you need to obtain a permit?

  • Did you review existing utility locations? Has miss utilities been contacted?

  • Is the excavation consistent with soil borings?

  • Are you shoring according to approved plans?

  • Review dewatering systems. Are observation wells required?

  • Are there areas where underpinning may be required?

  • Are movement detectors in place on adjoining structures?

  • Repairing of unsound rock(bolts, shotcrete)

  • Are backfill materials approved for density, compaction, what is the maximum lift height?

  • Is soil poisoning required?

  • Are sleeves required for utilities or irrigation?(power, water, irrigation, site lighting, etc.)

  • Temporary seeding does it match the specs or erosion control plan?

Blasting

  • Is blasting required? If so click Yes.

  • Have you reviewed measuring, payment, overblast procedures for rock excavation?(consider swell factor)

  • Have you reviewed blasting procedures for rock excavation.

  • Are movement detectors in place on adjoining structures?

  • Has everyone onsite been directed to turn off radios during blasting? Have you posted signs as required(blasting zone, etc.)

  • Are you having the geotech verify all measurements and quantities in their report?

Paving and Site Improvements

  • Will you be working on Paving, Curb and Gutter or Sidewalks in the next 30 days or are you currently working on them? If so click Yes.

  • Have you verified the asphalt mix design is pr plans and specs?

  • Is the sub-base stone correct depth?

  • Is milling/grinding called for? If so have you verified the depth prior to milling?

  • Is geotech required to monitor stone depths, etc?

  • Have you reviewed sequence of asphalt base and topping installation?(example: Is primer required?)

  • Have you verified if the plant is closing due to cold weather?

  • Are truck and delivery lanes designed for heavy traffic?

  • Have you verified you have no surface dishing or ponding?

  • Are the curb and gutter being installed per approved drawings?

  • Are handicap ramps and signage provided?

  • Prior to pouring HC ramps did you verify the proper slopes required?

  • Have you reviewed the lawn sprinkler installation sequence?

  • Prior to pavement did you verify slope tolerances for Handicap spaces.(2%)

  • If you have a fountain has the plumbing and electric been coordinated?

  • Where your working is it a state maintained roadway? If so have you received the proper permits are you meeting DOT requirements?

Landscaping and Plantings

  • Will you be working on Landscaping in the next 30 days or are you currently working on Landscaping? If so click Yes..

  • Do you have planters over occupied spaces if so is it waterproofed?

  • Did you check topsoil and plant backfill material for proper chemical requirements(ph, etc.)

  • Do trees require guy wires?

  • Have you protected existing trees to remain?

  • Is hydro seeding uniform and complete? (watch for erosion)

  • Is the sod gapless and slopes pegged?

  • Have you check the warranty and maintenance requirements(watering, fertilizer, cutting)?

  • Is power provided where your irrigation time clock is shown?

  • Is the backflow preventer installed for irrigation?

Division #3 - Concrete

  • Will you be working on concrete in the next 30 days? If so click Yes.

Formwork

  • Will you be working on formwork? If so click Yes.

  • Is the horizontal and diagonal bracing adequate?

  • Have you checked the form removal and reshoring requirements?

  • Have you verified the staggering jointing?

  • Have you verified the location of architectural embeds?

  • Are formliners required?

  • Have you verified insert/hardware requirements?

  • Did you verify the location of sleeves and expansion joints?

  • Have you verified they are using form oil on forms - not reinforcing?

  • Are the forms clean of dirt, debris, ice.?

  • Have you checked the line and grade of all forms before concrete placement?

  • Have you checked plumbness and camber before and after placement?

  • Have you watched rate of placement on vertical forms?

  • Have you verified the formwork against the structural/architectural drawings for formwork coordination/accuracy.?

  • Did you perform a foundation survey prior to your concrete pour?

  • Is geotech monitoring concrete pours?(air, slump, make cylinders)

  • Do you have a curing box on site?

Post Tension Cables

  • Are you using Post Tension Cables? If so click Yes.

  • Are approved shop drawings on site?

  • Are tendons secured/checked for proper locations?

  • Do you have a minimum of 16" of tendon beyond the form at the stressing end?

  • Is any of the sheathing damaged exposing the tendon? If so are they repaired?

  • Are anchors properly secured in position and greased?

  • Is there jack access at all stressing locations?

  • Have you verified the concrete strength meets the engineers requirements prior to tensioning tendons?

  • Have tensioning gauges been recently calibrated(within 6 months) and in good working order?

  • Do they have a spare calibrated jack at the site?

  • Is the stressing procedure on the shop drawings being followed?

  • Is the testing agency present to observe all tensioning?

Concrete Tilt Up

  • Will you be working on Concrete Tilt Up? If so click Yes.

  • Have your submitals been approved?

  • Have you verified your window and door opening sizes with the panels?

  • Are your embeds onsite for installation?

  • Has Everyone reviewed and approved the concrete mix designs?

Rebar Placement

  • Will you be working with Rebar Placement? If so click Yes.

  • Have you checked bar strength, size, spacing, slicing, bends?

  • Have you checked rebar for excessive rust?

  • Have you verified the location of rebar support - chairs, concrete blocks?

  • Have you checked form/rebar clearances?

  • Have you checked concrete clearances and coverage?

  • Have the screed methods discussed and been checked?

  • Have you inspected rebar for congested areas which will block concrete and aggregate distribution?

  • Is electrical bonding required?

  • Have you checked lap splice locations, lengths and ties?

  • Is wire mesh used? If so is it laying flat?

Concrete Placement

  • Will you be working with concrete placement? If so click Yes.

  • Has the mix design been approved?

  • Verify you are using the correct mix design for the application.(example: is air required?)

  • Has the form stripping procedure been approved?

  • Have the admixes for winter, summer been approved?

  • How long do you wait before the forms should be stripped?

  • Is pumping required? If so do you have a pump mix approved?

  • Do you need blankets or heating provisions for concrete.

  • Do you have a curing box?

  • Do you know the concrete testing requirements? Is a geotech required?

  • Is the curing compound compatible with floor finishes?

  • Is air required for the concrete you are pouring?

Division #4 - Masonry

  • Are you placing Masonry Products? If so click Yes.

Brick and Block

  • Are you installing Brick or Block. If so click Yes.

  • Are they using the specified mortar mixes?

  • Is weather protection needed?

  • Is coursing correct?

  • Is the mortar joint strike correct?

  • Have you verified all openings(windows, doors, elevator shafts)?

  • Do bond beams have specified rebar in them?

  • Have you verified elevation of embeds(elevator inserts, bearing plates, etc.)?

  • Is brick cavity clean?

  • Is flashing correctly installed?

  • Are brick ties or horizontal reinforcing spaced properly?

  • Are weeps being installed at the correct spacing?

  • Is a mock up wall required?

  • Steel lintels are they the correct size, quantity are they to be galvinized?

Precast or Natural Stone

  • Are you using precast concrete or natural stone? If so click

  • Have you verified flashing location and insure proper drainage?

  • Has the color been verified?

  • Is there a maximum height that can be laid per day?

  • Have you verified the connection details?

Division #5 - Metals

  • Are you installing Metals?(Structural Steel, Steel Stairs, Ornamental Metals). If so click Yes.

Structural Steel

  • Are you installing Structural Steel? If so click Yes.

  • Did you verify anchor bolt spacing?

  • Who is responsible for setting the leveling nuts? Has this been done?

  • Are the connections per the approved shop drawings and structural drawings?

  • Did you ensure plumbness prior to final connections?

  • Did you verify proper grouting of base plates and grout strength?

  • Prior to pouring back diamonds is a bond breaker required on steel?

  • Is a 3rd party testing agency required to inspect steel? Have you complied with all inspections required?

  • Is the steel to be primed?

  • Is the torque on the bolts specified?

Bar Joist

  • Are you installing Bar Joist. If so click Yes.

  • Are the bar joist spaced correctly?

  • Do the bar joists have the proper bearing?

  • Are steel frames installed where required?(openings, etc.)

  • Is bridging installed correctly?

  • Are they to be primed?

Metal Deck

  • Are you installing Metal Deck? If so click Yes.

  • Who is providing Pour Stops?

  • Have you verified pour stop locations?

  • Is welder certification required? If so have they provided the proper certification documents?

  • What is the minimum overlap of deck required? Have you verified?

  • Have you verified welding or crimping requirements?

  • Is Shoring required?

  • Are studs in the proper location and length?

  • Is reinforcing required at columns and openings? Is it installed correctly?<br>This is the end of this section.<br>Proceed to questions below.

Ornamental Metals

  • Prior to welding ensure protection of adjacent materials during erection/installation?

Division #6 - Wood and Plastics

  • Are you working on carpentry?(framing or interior millwork) If so click yes?

Rough Carpentry

  • Are You doing Rough Carpentry?

  • Have you verified rough openings for windows and doors?

  • Have you verified truss spacing at floor and roof trusses?

  • Is treated material required at locations? If so is it being installed properly?

  • Has tyvex been installed properly? Pay attention to openings.

  • Have you coordinated blocking requirements?(toilet accessories, grab bars, cabinets, shelving, etc.)

  • Have you verified all headers installed per drawings?

  • Are all window heads at the same elevation?

  • Have you verified truss orientation?

  • Is truss bracing installed per shop drawnigs?

  • Do trusses miss HVAC ductwork and openings?

  • Are access doors required? Are the openings framed?

  • Have you checked squareness of corners particularly where cabinet corners are?

Millwork

  • Are you doing interior millwork or trim?

  • Have you verified rated doors have the proper rating of frames and doors? Ensure the painter does not paint the labels.

  • Have you checked the swing of doors?

  • Have you verified doors have been prepared for the proper backset?

  • Have you verified door undercut requirements?

  • Have you verified the temperature and humidity are controlled prior to millwork delivery?

Division #7 - Thermal and Moisture Protection

  • Are you working with Thermal and Moisture Protection?(Insulation, vapor barrier, waterproofing, etc.)

Waterproofing

  • Are you working with waterproofing?

  • Has the primer been installed correctly?

  • Is the product overlapped correctly?

  • If installed on concrete, have all the honeycombed areas been repaired propertly?

  • Does the waterproofing transition to a second material? (example concrete to block) If so is it installed per the manufacturers recommendations?

  • Are cant strips, termination bars in place and installed correctly?

  • Is protection board required?

  • Is an under drain system required?(pipe in sock w/gravel)

  • Has a manufacturers rep reviewed the installation?

Roofing

  • Are you working with roofing?

Shingles

  • Are you working with Shingles?

  • Has the ice and water shield been installed in the proper locations?

  • Have you ensured the roof is vented properly at the ridge and eaves? Is the plywood cut back at the ridge for the ridge vent?

  • Are plumbing stacks flashed properly?

  • Is step flashing installed properly?

  • Have you verified the felt weight prior to installation?(30lbs or 15lbs)

  • Have you verified the shingle color?

  • Have you verified the shingle being installed is the proper shingle?(30 year/ 20 year)

  • Are the correct fasteners being used?(if copper flashing you need copper nails)

  • Have you verified the sheathing is fastened correctly?

Flat Roof

  • Are you working with a flat roof?

  • Have you verified the substrate dry and cured?

  • Have you verified the roof drains have been sealed and flashed properly?

  • Have you verified if walk pads are required? If so have they been installed properly?

  • Have you verified treated nailers are in place where required?

  • Have roof hatches and vents been secured?

  • Has a manufacturers rep been contacted to make periodic site visit to inspect the roofing operation?

  • Does your roofing membrane turn up walls? If so have you verified any penetrations are sealed properly?

  • Does equipment set on the roof? If so have you verified you are using the specified vibration isolation?

  • After each days work have you verified that the work is properly sealed and protected from weather?

  • Have they installed screens on the roof drains promptly to prevent clogging?

Caulking and Sealants

  • Are you working with Caulking and Sealants?

  • Have you verified the air temperature within the manufacturers installation limits?

  • Is the correct size of backer rod being used?

  • Is the area clean and free of moisture?

  • Have you verified the systems depth to width ratio according to the product data submittal?

  • Did you verify the proper color is being used?

Spray Fireproofing

  • Are you working with Spray Fireproofing?

  • Are you spraying on steel? If so was the steel left unprimed? Check product data to ensure proper bonding.

  • Have adjacent surfaces or equipment been properly protected?

  • Did you verify thickness required?

  • Did you coordinate any hangers that need to be installed by MPE trades before fireproofing?

Division #8 - Doors & Windows

Doors

  • Are you working with Door Installation?

  • Have you verified that the Hollow Metal frames are securely anchored to the slab, plumb and are the spreaders installed?

  • Have you verified if the door frames required to be grouted? If so are they grouted correctly?

  • Have you verified rated doors and frames are labeled and installed where shown?

  • Have you verified correct door hardware is installed per the hardware schedule?

  • Have you verified the proper glass is in fire rated doors?

  • Have you verified that the wood doors shimmed and fastened properly?

  • Have you provided power or a raceway to doors requiring electric strikes or push plates?

  • Did you verify the throats match the wall thickness?

  • Have you verified the doors have the correct swing?

Windows

  • Are you working with Window Installation?

  • If a window mock up is required have you provided one and has it been approved?

  • Have you verified the windows are installed and flashed per manufacturers recommendations?(verify nail size and placement)(Is sealant required behind nail fins, shims in place.)

  • If it is an aluminum window is it flashed properly? Is the sill flashing sloping to the outside? Are end dams installed and sealed properly?

Division #9 - Finishes

  • Are you working with finishing work(drywall, paint, wallpaper or flooring)?

Drywall

  • Are you woking with Drywall?

  • If control joints are required have you verified their location?

  • Have you verified the drywall being fastened at the required spacing?

  • Have you verified the location of moisture resistant board if required? If so is it installed there?

  • Have you verified blocking is installed in the proper locations prior to sheetrock installation?

  • If you floor/ceiling assembly is rated have you verified if penetrations(can lights) require sheetrock boxes over them?

  • Have you verified the level of sheetrock finish that is required in the specs?

Painting

  • Are you working with Painting?

  • Did you check to see if the bottoms of doors are painted or sealed especially if they are undercut?

  • Did you verify if the tops of doors are required to be painted? If so are they painted?

  • Have you checked to verify UL Labels are not painted?

  • Have you checked the number of coats of paint that are required?(prime coat plus ____ coats)

  • Have you verified the finish of paints throughout the project?(flat, gloss, semi-gloss, eggshell,etc.)

  • Are sprinkler heads and fire dampers protected from paint spraying?

Wallpaper

  • Are you working with wallpaper?

  • Have the walls been sized prior to wallpaper install?

  • Have walls been primed prior to wallpaper install?

Ceramic Tile

  • Are you working with ceramic tile?

  • Have you verified the floors slope to the drain?

  • Have you confirmed if bullnose is required?

  • Is the tile being used as specified and approved?

  • Is the grout color being used as specified and approved?

  • Is the floor level and are walls plumb?

  • Have the walls and floors been cleaned prior to fixtures being installed to prevent pitting?

Resilient Flooring

  • Are you working with Resilient Flooring?

  • If seams are required has the architect reviewed the seaming locations?

  • Is it laid in the correct direction?

Carpet

  • Are you working with Carpet?

  • If seams are required has the architect reviewed the seaming locations?

  • Are the correct transition strips being used?

  • Have you verified carpet pad requirements? HC units have different requirements.

  • Have you verified the requirements for glue down carpet?(Is the temperature adequate? Has the slab been tested for moisture?)

  • Have you thought about carpet protection?

Suspended Ceilings

  • Are you working with Suspended Ceilings?

  • Have you coordinated the light fixtures and HVAC Registers layout?

  • Are they installing the tiles in the correct direction?

  • Have you reviewed the borders prior to installation of main runners?

  • Is the HVAC running? Will this cause the tiles to sag?

  • Have all penetrations above the ceiling been sealed prior to tile installation?

  • Has all the work above the ceiling been completed prior to tiles being placed?(example: fire caulking, valves tagged, etc.)

  • Have you verified the color of the tile and the grid being installed is correct?

Division #10 - Specalties

  • Are you working with Toilet Accessories or Blinds?

Toilet Accessories

  • Are you working with Toilet Accessories?

  • Have you ensured all Toilet Accessories are hitting solid blocking?

  • Have Handicap bars been installed in the correct location? Can they support the required weight?

Blinds

  • Are you working with Blinds?

  • Have you verified the color of the blinds?

  • Have you checked to see if the blinds are to have strings or wands? Are they installed correctly?

Division #13 - Special Construciton

Pre-Engineered Metal Building

  • Are you working with a pre-engineered metal building?

  • Have the colors been selected?

  • Do you have a delivery date for the building?

  • Have you compared PEMB anchor bolt layout to the structural layout? Has the PEMB anchor bolt plan been forwarded to the structural engineer?

  • Have the anchor bolt plans from the PEMB been forwarded to LMB-Surveyor?

  • Do you have any additional items hanging from the PEMB? If so has teh PEMB manufacturer been notified of these loads?

  • Does the PEMB contact any other materials? IE: masonry, concrete. Do you have sufficient details on these transitions?

Division #14 - Conveying Systems

  • Are you workiing with any conveying system?(elevator, escalator)

Elevator or escalator

  • Have you coordinated pit opening, shaft size and machine room with shop drawings?

  • Are hoist beams required and installed?

  • Have inserts been installed in the proper location?

  • If using during construction, have you protected the cab from damage?

  • Did you verify power requirements with elevator sub and electrician?(3-phase)

  • Have you discussed with the local fire marshal and asked what is required for sprinkler heads at the top and bottom of the shaft?

  • Have you checked to see if a shunt trip breaker required?

  • Have you verified if an oil minder pump required?

  • Have you verified cab finishes, floor colors and all materials are correct?

Division #15 - Plumbing, Mechanical & Sprinkler Systems

Plumbing Rough In

  • Are you currently working on Plumbing Rough-In work?

  • Have you verified all fire safing at rated penetrations?

  • Have you verified who is providing access doors for their work?

  • Have you verified what piping is required to be insulated if any?

  • Have you checked to ensure the plumbing drawings and civil drawings show the water and sewer connections at the same location?

  • Have you verified the location and size of equipment pads?

  • Have you verified the location of shower valves?

  • Have you verified if showers require additional blocking for future grab bars?

  • Will all valves be accessable?

Plumbing Trim out

  • Are you currently working on Plumbing Trim-Out work?

  • Have you verified the fixtures are providing hot and cold water?

  • Have you insulated hot water lines and p-traps under handicap sinks?

  • Has piping been labeled and valves tagged?

HVAC Rough In

  • Are you currently working on HVAC Rough-In work?

  • Have you verified all fire safing at rated penetrations?

  • Have you verified who is providing access doors for their work?

  • Have you verified that all ducts are sealed properly?

  • Have you coordinated electrical starters, transformers, controllers and disconnects with the electrical trade?

  • Have you verified how much and what type of insulation is required?(interior of ducts or exterior)

  • Have you verified flex duct does not exceed length limitations?

  • Are open ducts protected from dust and debris?

  • If you have electric heaters have you verified who is installing electrician or HVAC subcontractor?

  • Have you verified what power is required for the power actuated dampers?(120 volt or low voltage)

  • Have you verified who is providing louvers for HVAC work?

HVAC Trim Out

  • Are you currently working on HVAC Trim-Out work?

  • Do all fire dampers have access to them?

  • Have you verified the subcontract if a filter change is required at completion?

  • Have you checked the specs to see what is required for testing and ballancing?

Sprinkler Rough In

  • Are you currently working on Sprinkler Rough-In?

  • Have you verified all fire safing at rated penetrations?

  • Have you verified who is providing access doors for their work?

  • Have you verified thrust blocks are installed where required?

  • Do you have approved drawings from the fire marshal?

  • Have you verified if the heads installed are the correct heads?(semi-recessed, pendant)

  • Have you verified the sprinkler piping material?(cpvc or steel)

  • Do dry pendant heads have the proper insulation around them to prevent freezing in the winter? Are the heads sealed tight around the exterior sheathing?

  • Is the sprinkler riser room heated?

Sprinkler Trim Out

  • Are you currently working on Sprinkler Trim-Out?

  • Do sprinkler heads have proper clearances from light fixtures?

  • Are sidewall heads have the proper clearance from the ceiling?

  • Are valves monitored(flows and tamper switches) or are they chained off in the open position?

Division #16 - Electrical

Electrical Rough In

  • Are you currently working on Electrical Rough-In work?

  • If you have electrical duct banks, has this been coordinated?

  • Have you verified the electrical subcontract to ensure they are providing what temporary electric is in their subcontract?

  • Have you verified who provides plywood backing where required for telephone boards, etc?

  • Have you verified the locations of floor boxes?

  • Have you verified who is providing access doors for their work?

  • Have you verified all fire safing at rated penetrations?

  • Have you verified the location and size of equipment pads?

Electrical Trim Out

  • Are you currently working on Electrical Trim-out work?

  • Have you verified the owner has provided phone lines for the fire alarm panel?

  • Have you verified if egress maps are required by the fire marshal?

  • Have you coordinated electrical starters, transformers, controllers and disconnects with the HVAC trade?

  • Have electrical panels been labeled?

  • Are exit lights and emergency lights in their proper location?

  • If you have a generator have you verified who is to provide fuel at the completion of work?

Corrective Actions

  • Enter any corrective actions that will be undertaken

Sign Off

  • Auditor's signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.