Information
-
Document No.
-
Conducted on
-
Job Name
-
Job Number
-
Prepared by
-
Location
Division#2 - Sitework
-
Will you be working on sitework in the next 30 days or are you currently working on sitework? This includes Demo, Site Utilities, Piles and Caissons, Excavation, Paving, C &G, Sidewalks, Landscaping and Irrigation. If so click yes.
Site Demolition
-
Will you be working on Demolition in the next 30 days or are you currently working on Demo? If so click yes.
-
Did you review permit requirements and time required?
-
Is the adjacent property protected?
-
Is an existing conditions 3rd party survey required?
-
Are the existing utilities protected, have you notified them about your work? Check cut off requirements.
-
Have you checked blasting procedures, requirements, protective measures needed before proceeding?
-
Are tree guards in place and according to jurisdiction approved plans?
-
Are traffic control plans established for trucking and pedestrians?
-
Are there dust control and truck wash requirements? If so are they in place?
-
Have all underground fuel tanks purged?
-
Have the proper people been notified of work proceeding and hours?
-
Are there any hazardous materials?(asbestos, lead?)
Site Utilities
-
Will you be working on site utilities in the next 30 days or are you currently working on site utilities? If so click Yes.
-
Have you verified that elevations are correct(inverts, catch basins, storm and sanitary lines)?
-
Are valves and fire hydrant located exactly as per drawings?
-
Are conduits or sleeves required?(for site lighting, irrigation, telephone, cable, power)
-
Have you verified your trenches are safe?
-
Have you or a 3rd party verified trench and backfill requirements/compaction?
-
Has the geotech been notified to monitor?
-
Is the proper signage in place?
Piles and Caissons
-
Will you be working on Piles or Caissons in the next 60 days or are you currently working on Piles or Caissons? If so Click Yes.
-
Have you checked for displacement due to horizontal/vertical heave?
-
Have you allowed for possible vertical heave in pile-cap excavation?
-
Are you maintaining required separation between driving and concreting operations?
-
Are you maintaing driving logs/records?
-
Are you monitoring adjacent structures for damage?
-
Have you checked quantities and location for accuracy?
-
Did you verify anchor bolt locations?
-
Did you perform air test in caissons for toxic gases?
-
Has the geotech been notified to monitor?
-
Possible dirt/spoils removal. Where is this being disposed of and by whom?
Excavation
-
Will you be working on excavation in the next 30 days or are you currently working on excavation? If so click Yes.
-
Did you take pictures of adjoining structures.
-
Is erosion control in place and installed correctly(per plans)?
-
Has erosion control measures been inspected by the local jurisdiction?
-
Is burning authorized? If so do you need to obtain a permit?
-
Did you review existing utility locations? Has miss utilities been contacted?
-
Is the excavation consistent with soil borings?
-
Are you shoring according to approved plans?
-
Review dewatering systems. Are observation wells required?
-
Are there areas where underpinning may be required?
-
Are movement detectors in place on adjoining structures?
-
Repairing of unsound rock(bolts, shotcrete)
-
Are backfill materials approved for density, compaction, what is the maximum lift height?
-
Is soil poisoning required?
-
Are sleeves required for utilities or irrigation?(power, water, irrigation, site lighting, etc.)
-
Temporary seeding does it match the specs or erosion control plan?
Blasting
-
Is blasting required? If so click Yes.
-
Have you reviewed measuring, payment, overblast procedures for rock excavation?(consider swell factor)
-
Have you reviewed blasting procedures for rock excavation.
-
Are movement detectors in place on adjoining structures?
-
Has everyone onsite been directed to turn off radios during blasting? Have you posted signs as required(blasting zone, etc.)
-
Are you having the geotech verify all measurements and quantities in their report?
Paving and Site Improvements
-
Will you be working on Paving, Curb and Gutter or Sidewalks in the next 30 days or are you currently working on them? If so click Yes.
-
Have you verified the asphalt mix design is pr plans and specs?
-
Is the sub-base stone correct depth?
-
Is milling/grinding called for? If so have you verified the depth prior to milling?
-
Is geotech required to monitor stone depths, etc?
-
Have you reviewed sequence of asphalt base and topping installation?(example: Is primer required?)
-
Have you verified if the plant is closing due to cold weather?
-
Are truck and delivery lanes designed for heavy traffic?
-
Have you verified you have no surface dishing or ponding?
-
Are the curb and gutter being installed per approved drawings?
-
Are handicap ramps and signage provided?
-
Prior to pouring HC ramps did you verify the proper slopes required?
-
Have you reviewed the lawn sprinkler installation sequence?
-
Prior to pavement did you verify slope tolerances for Handicap spaces.(2%)
-
If you have a fountain has the plumbing and electric been coordinated?
-
Where your working is it a state maintained roadway? If so have you received the proper permits are you meeting DOT requirements?
Landscaping and Plantings
-
Will you be working on Landscaping in the next 30 days or are you currently working on Landscaping? If so click Yes..
-
Do you have planters over occupied spaces if so is it waterproofed?
-
Did you check topsoil and plant backfill material for proper chemical requirements(ph, etc.)
-
Do trees require guy wires?
-
Have you protected existing trees to remain?
-
Is hydro seeding uniform and complete? (watch for erosion)
-
Is the sod gapless and slopes pegged?
-
Have you check the warranty and maintenance requirements(watering, fertilizer, cutting)?
-
Is power provided where your irrigation time clock is shown?
-
Is the backflow preventer installed for irrigation?
Division #3 - Concrete
-
Will you be working on concrete in the next 30 days? If so click Yes.
Formwork
-
Will you be working on formwork? If so click Yes.
-
Is the horizontal and diagonal bracing adequate?
-
Have you checked the form removal and reshoring requirements?
-
Have you verified the staggering jointing?
-
Have you verified the location of architectural embeds?
-
Are formliners required?
-
Have you verified insert/hardware requirements?
-
Did you verify the location of sleeves and expansion joints?
-
Have you verified they are using form oil on forms - not reinforcing?
-
Are the forms clean of dirt, debris, ice.?
-
Have you checked the line and grade of all forms before concrete placement?
-
Have you checked plumbness and camber before and after placement?
-
Have you watched rate of placement on vertical forms?
-
Have you verified the formwork against the structural/architectural drawings for formwork coordination/accuracy.?
-
Did you perform a foundation survey prior to your concrete pour?
-
Is geotech monitoring concrete pours?(air, slump, make cylinders)
-
Do you have a curing box on site?
Post Tension Cables
-
Are you using Post Tension Cables? If so click Yes.
-
Are approved shop drawings on site?
-
Are tendons secured/checked for proper locations?
-
Do you have a minimum of 16" of tendon beyond the form at the stressing end?
-
Is any of the sheathing damaged exposing the tendon? If so are they repaired?
-
Are anchors properly secured in position and greased?
-
Is there jack access at all stressing locations?
-
Have you verified the concrete strength meets the engineers requirements prior to tensioning tendons?
-
Have tensioning gauges been recently calibrated(within 6 months) and in good working order?
-
Do they have a spare calibrated jack at the site?
-
Is the stressing procedure on the shop drawings being followed?
-
Is the testing agency present to observe all tensioning?
Concrete Tilt Up
-
Will you be working on Concrete Tilt Up? If so click Yes.
-
Have your submitals been approved?
-
Have you verified your window and door opening sizes with the panels?
-
Are your embeds onsite for installation?
-
Has Everyone reviewed and approved the concrete mix designs?
Rebar Placement
-
Will you be working with Rebar Placement? If so click Yes.
-
Have you checked bar strength, size, spacing, slicing, bends?
-
Have you checked rebar for excessive rust?
-
Have you verified the location of rebar support - chairs, concrete blocks?
-
Have you checked form/rebar clearances?
-
Have you checked concrete clearances and coverage?
-
Have the screed methods discussed and been checked?
-
Have you inspected rebar for congested areas which will block concrete and aggregate distribution?
-
Is electrical bonding required?
-
Have you checked lap splice locations, lengths and ties?
-
Is wire mesh used? If so is it laying flat?
Concrete Placement
-
Will you be working with concrete placement? If so click Yes.
-
Has the mix design been approved?
-
Verify you are using the correct mix design for the application.(example: is air required?)
-
Has the form stripping procedure been approved?
-
Have the admixes for winter, summer been approved?
-
How long do you wait before the forms should be stripped?
-
Is pumping required? If so do you have a pump mix approved?
-
Do you need blankets or heating provisions for concrete.
-
Do you have a curing box?
-
Do you know the concrete testing requirements? Is a geotech required?
-
Is the curing compound compatible with floor finishes?
-
Is air required for the concrete you are pouring?
Division #4 - Masonry
-
Are you placing Masonry Products? If so click Yes.
Brick and Block
-
Are you installing Brick or Block. If so click Yes.
-
Are they using the specified mortar mixes?
-
Is weather protection needed?
-
Is coursing correct?
-
Is the mortar joint strike correct?
-
Have you verified all openings(windows, doors, elevator shafts)?
-
Do bond beams have specified rebar in them?
-
Have you verified elevation of embeds(elevator inserts, bearing plates, etc.)?
-
Is brick cavity clean?
-
Is flashing correctly installed?
-
Are brick ties or horizontal reinforcing spaced properly?
-
Are weeps being installed at the correct spacing?
-
Is a mock up wall required?
-
Steel lintels are they the correct size, quantity are they to be galvinized?
Precast or Natural Stone
-
Are you using precast concrete or natural stone? If so click
-
Have you verified flashing location and insure proper drainage?
-
Has the color been verified?
-
Is there a maximum height that can be laid per day?
-
Have you verified the connection details?
Division #5 - Metals
-
Are you installing Metals?(Structural Steel, Steel Stairs, Ornamental Metals). If so click Yes.
Structural Steel
-
Are you installing Structural Steel? If so click Yes.
-
Did you verify anchor bolt spacing?
-
Who is responsible for setting the leveling nuts? Has this been done?
-
Are the connections per the approved shop drawings and structural drawings?
-
Did you ensure plumbness prior to final connections?
-
Did you verify proper grouting of base plates and grout strength?
-
Prior to pouring back diamonds is a bond breaker required on steel?
-
Is a 3rd party testing agency required to inspect steel? Have you complied with all inspections required?
-
Is the steel to be primed?
-
Is the torque on the bolts specified?
Bar Joist
-
Are you installing Bar Joist. If so click Yes.
-
Are the bar joist spaced correctly?
-
Do the bar joists have the proper bearing?
-
Are steel frames installed where required?(openings, etc.)
-
Is bridging installed correctly?
-
Are they to be primed?
Metal Deck
-
Are you installing Metal Deck? If so click Yes.
-
Who is providing Pour Stops?
-
Have you verified pour stop locations?
-
Is welder certification required? If so have they provided the proper certification documents?
-
What is the minimum overlap of deck required? Have you verified?
-
Have you verified welding or crimping requirements?
-
Is Shoring required?
-
Are studs in the proper location and length?
-
Is reinforcing required at columns and openings? Is it installed correctly?<br>This is the end of this section.<br>Proceed to questions below.
Ornamental Metals
-
-
Prior to welding ensure protection of adjacent materials during erection/installation?
Division #6 - Wood and Plastics
-
Are you working on carpentry?(framing or interior millwork) If so click yes?
Rough Carpentry
-
Are You doing Rough Carpentry?
-
Have you verified rough openings for windows and doors?
-
Have you verified truss spacing at floor and roof trusses?
-
Is treated material required at locations? If so is it being installed properly?
-
Has tyvex been installed properly? Pay attention to openings.
-
Have you coordinated blocking requirements?(toilet accessories, grab bars, cabinets, shelving, etc.)
-
Have you verified all headers installed per drawings?
-
Are all window heads at the same elevation?
-
Have you verified truss orientation?
-
Is truss bracing installed per shop drawnigs?
-
Do trusses miss HVAC ductwork and openings?
-
Are access doors required? Are the openings framed?
-
Have you checked squareness of corners particularly where cabinet corners are?
Millwork
-
Are you doing interior millwork or trim?
-
Have you verified rated doors have the proper rating of frames and doors? Ensure the painter does not paint the labels.
-
Have you checked the swing of doors?
-
Have you verified doors have been prepared for the proper backset?
-
Have you verified door undercut requirements?
-
Have you verified the temperature and humidity are controlled prior to millwork delivery?
Division #7 - Thermal and Moisture Protection
-
Are you working with Thermal and Moisture Protection?(Insulation, vapor barrier, waterproofing, etc.)
Waterproofing
-
Are you working with waterproofing?
-
Has the primer been installed correctly?
-
Is the product overlapped correctly?
-
If installed on concrete, have all the honeycombed areas been repaired propertly?
-
Does the waterproofing transition to a second material? (example concrete to block) If so is it installed per the manufacturers recommendations?
-
Are cant strips, termination bars in place and installed correctly?
-
Is protection board required?
-
Is an under drain system required?(pipe in sock w/gravel)
-
Has a manufacturers rep reviewed the installation?
Roofing
-
Are you working with roofing?
Shingles
-
Are you working with Shingles?
-
Has the ice and water shield been installed in the proper locations?
-
Have you ensured the roof is vented properly at the ridge and eaves? Is the plywood cut back at the ridge for the ridge vent?
-
Are plumbing stacks flashed properly?
-
Is step flashing installed properly?
-
Have you verified the felt weight prior to installation?(30lbs or 15lbs)
-
Have you verified the shingle color?
-
Have you verified the shingle being installed is the proper shingle?(30 year/ 20 year)
-
Are the correct fasteners being used?(if copper flashing you need copper nails)
-
Have you verified the sheathing is fastened correctly?
Flat Roof
-
Are you working with a flat roof?
-
Have you verified the substrate dry and cured?
-
Have you verified the roof drains have been sealed and flashed properly?
-
Have you verified if walk pads are required? If so have they been installed properly?
-
Have you verified treated nailers are in place where required?
-
Have roof hatches and vents been secured?
-
Has a manufacturers rep been contacted to make periodic site visit to inspect the roofing operation?
-
Does your roofing membrane turn up walls? If so have you verified any penetrations are sealed properly?
-
Does equipment set on the roof? If so have you verified you are using the specified vibration isolation?
-
After each days work have you verified that the work is properly sealed and protected from weather?
-
Have they installed screens on the roof drains promptly to prevent clogging?
Caulking and Sealants
-
Are you working with Caulking and Sealants?
-
Have you verified the air temperature within the manufacturers installation limits?
-
Is the correct size of backer rod being used?
-
Is the area clean and free of moisture?
-
Have you verified the systems depth to width ratio according to the product data submittal?
-
Did you verify the proper color is being used?
Spray Fireproofing
-
Are you working with Spray Fireproofing?
-
Are you spraying on steel? If so was the steel left unprimed? Check product data to ensure proper bonding.
-
Have adjacent surfaces or equipment been properly protected?
-
Did you verify thickness required?
-
Did you coordinate any hangers that need to be installed by MPE trades before fireproofing?
Division #8 - Doors & Windows
Doors
-
Are you working with Door Installation?
-
Have you verified that the Hollow Metal frames are securely anchored to the slab, plumb and are the spreaders installed?
-
Have you verified if the door frames required to be grouted? If so are they grouted correctly?
-
Have you verified rated doors and frames are labeled and installed where shown?
-
Have you verified correct door hardware is installed per the hardware schedule?
-
Have you verified the proper glass is in fire rated doors?
-
Have you verified that the wood doors shimmed and fastened properly?
-
Have you provided power or a raceway to doors requiring electric strikes or push plates?
-
Did you verify the throats match the wall thickness?
-
Have you verified the doors have the correct swing?
Windows
-
Are you working with Window Installation?
-
If a window mock up is required have you provided one and has it been approved?
-
Have you verified the windows are installed and flashed per manufacturers recommendations?(verify nail size and placement)(Is sealant required behind nail fins, shims in place.)
-
If it is an aluminum window is it flashed properly? Is the sill flashing sloping to the outside? Are end dams installed and sealed properly?
Division #9 - Finishes
-
Are you working with finishing work(drywall, paint, wallpaper or flooring)?
Drywall
-
Are you woking with Drywall?
-
If control joints are required have you verified their location?
-
Have you verified the drywall being fastened at the required spacing?
-
Have you verified the location of moisture resistant board if required? If so is it installed there?
-
Have you verified blocking is installed in the proper locations prior to sheetrock installation?
-
If you floor/ceiling assembly is rated have you verified if penetrations(can lights) require sheetrock boxes over them?
-
Have you verified the level of sheetrock finish that is required in the specs?
Painting
-
Are you working with Painting?
-
Did you check to see if the bottoms of doors are painted or sealed especially if they are undercut?
-
Did you verify if the tops of doors are required to be painted? If so are they painted?
-
Have you checked to verify UL Labels are not painted?
-
Have you checked the number of coats of paint that are required?(prime coat plus ____ coats)
-
Have you verified the finish of paints throughout the project?(flat, gloss, semi-gloss, eggshell,etc.)
-
Are sprinkler heads and fire dampers protected from paint spraying?
Wallpaper
-
Are you working with wallpaper?
-
Have the walls been sized prior to wallpaper install?
-
Have walls been primed prior to wallpaper install?
Ceramic Tile
-
Are you working with ceramic tile?
-
Have you verified the floors slope to the drain?
-
Have you confirmed if bullnose is required?
-
Is the tile being used as specified and approved?
-
Is the grout color being used as specified and approved?
-
Is the floor level and are walls plumb?
-
Have the walls and floors been cleaned prior to fixtures being installed to prevent pitting?
Resilient Flooring
-
Are you working with Resilient Flooring?
-
If seams are required has the architect reviewed the seaming locations?
-
Is it laid in the correct direction?
Carpet
-
Are you working with Carpet?
-
If seams are required has the architect reviewed the seaming locations?
-
Are the correct transition strips being used?
-
Have you verified carpet pad requirements? HC units have different requirements.
-
Have you verified the requirements for glue down carpet?(Is the temperature adequate? Has the slab been tested for moisture?)
-
Have you thought about carpet protection?
Suspended Ceilings
-
Are you working with Suspended Ceilings?
-
Have you coordinated the light fixtures and HVAC Registers layout?
-
Are they installing the tiles in the correct direction?
-
Have you reviewed the borders prior to installation of main runners?
-
Is the HVAC running? Will this cause the tiles to sag?
-
Have all penetrations above the ceiling been sealed prior to tile installation?
-
Has all the work above the ceiling been completed prior to tiles being placed?(example: fire caulking, valves tagged, etc.)
-
Have you verified the color of the tile and the grid being installed is correct?
Division #10 - Specalties
-
Are you working with Toilet Accessories or Blinds?
Toilet Accessories
-
Are you working with Toilet Accessories?
-
Have you ensured all Toilet Accessories are hitting solid blocking?
-
Have Handicap bars been installed in the correct location? Can they support the required weight?
Blinds
-
Are you working with Blinds?
-
Have you verified the color of the blinds?
-
Have you checked to see if the blinds are to have strings or wands? Are they installed correctly?
Division #13 - Special Construciton
Pre-Engineered Metal Building
-
Are you working with a pre-engineered metal building?
-
Have the colors been selected?
-
Do you have a delivery date for the building?
-
Have you compared PEMB anchor bolt layout to the structural layout? Has the PEMB anchor bolt plan been forwarded to the structural engineer?
-
Have the anchor bolt plans from the PEMB been forwarded to LMB-Surveyor?
-
Do you have any additional items hanging from the PEMB? If so has teh PEMB manufacturer been notified of these loads?
-
Does the PEMB contact any other materials? IE: masonry, concrete. Do you have sufficient details on these transitions?
Division #14 - Conveying Systems
-
Are you workiing with any conveying system?(elevator, escalator)
Elevator or escalator
-
Have you coordinated pit opening, shaft size and machine room with shop drawings?
-
Are hoist beams required and installed?
-
Have inserts been installed in the proper location?
-
If using during construction, have you protected the cab from damage?
-
Did you verify power requirements with elevator sub and electrician?(3-phase)
-
Have you discussed with the local fire marshal and asked what is required for sprinkler heads at the top and bottom of the shaft?
-
Have you checked to see if a shunt trip breaker required?
-
Have you verified if an oil minder pump required?
-
Have you verified cab finishes, floor colors and all materials are correct?
Division #15 - Plumbing, Mechanical & Sprinkler Systems
Plumbing Rough In
-
Are you currently working on Plumbing Rough-In work?
-
Have you verified all fire safing at rated penetrations?
-
Have you verified who is providing access doors for their work?
-
Have you verified what piping is required to be insulated if any?
-
Have you checked to ensure the plumbing drawings and civil drawings show the water and sewer connections at the same location?
-
Have you verified the location and size of equipment pads?
-
Have you verified the location of shower valves?
-
Have you verified if showers require additional blocking for future grab bars?
-
Will all valves be accessable?
Plumbing Trim out
-
Are you currently working on Plumbing Trim-Out work?
-
Have you verified the fixtures are providing hot and cold water?
-
Have you insulated hot water lines and p-traps under handicap sinks?
-
Has piping been labeled and valves tagged?
HVAC Rough In
-
Are you currently working on HVAC Rough-In work?
-
Have you verified all fire safing at rated penetrations?
-
Have you verified who is providing access doors for their work?
-
Have you verified that all ducts are sealed properly?
-
Have you coordinated electrical starters, transformers, controllers and disconnects with the electrical trade?
-
Have you verified how much and what type of insulation is required?(interior of ducts or exterior)
-
Have you verified flex duct does not exceed length limitations?
-
Are open ducts protected from dust and debris?
-
If you have electric heaters have you verified who is installing electrician or HVAC subcontractor?
-
Have you verified what power is required for the power actuated dampers?(120 volt or low voltage)
-
Have you verified who is providing louvers for HVAC work?
HVAC Trim Out
-
Are you currently working on HVAC Trim-Out work?
-
Do all fire dampers have access to them?
-
Have you verified the subcontract if a filter change is required at completion?
-
Have you checked the specs to see what is required for testing and ballancing?
Sprinkler Rough In
-
Are you currently working on Sprinkler Rough-In?
-
Have you verified all fire safing at rated penetrations?
-
Have you verified who is providing access doors for their work?
-
Have you verified thrust blocks are installed where required?
-
Do you have approved drawings from the fire marshal?
-
Have you verified if the heads installed are the correct heads?(semi-recessed, pendant)
-
Have you verified the sprinkler piping material?(cpvc or steel)
-
Do dry pendant heads have the proper insulation around them to prevent freezing in the winter? Are the heads sealed tight around the exterior sheathing?
-
Is the sprinkler riser room heated?
Sprinkler Trim Out
-
Are you currently working on Sprinkler Trim-Out?
-
Do sprinkler heads have proper clearances from light fixtures?
-
Are sidewall heads have the proper clearance from the ceiling?
-
Are valves monitored(flows and tamper switches) or are they chained off in the open position?
Division #16 - Electrical
Electrical Rough In
-
Are you currently working on Electrical Rough-In work?
-
If you have electrical duct banks, has this been coordinated?
-
Have you verified the electrical subcontract to ensure they are providing what temporary electric is in their subcontract?
-
Have you verified who provides plywood backing where required for telephone boards, etc?
-
Have you verified the locations of floor boxes?
-
Have you verified who is providing access doors for their work?
-
Have you verified all fire safing at rated penetrations?
-
Have you verified the location and size of equipment pads?
Electrical Trim Out
-
Are you currently working on Electrical Trim-out work?
-
Have you verified the owner has provided phone lines for the fire alarm panel?
-
Have you verified if egress maps are required by the fire marshal?
-
Have you coordinated electrical starters, transformers, controllers and disconnects with the HVAC trade?
-
Have electrical panels been labeled?
-
Are exit lights and emergency lights in their proper location?
-
If you have a generator have you verified who is to provide fuel at the completion of work?
Corrective Actions
-
Enter any corrective actions that will be undertaken
Sign Off
-
Auditor's signature
-