Information

  • Audit Title

  • Project

  • Conducted on

  • Prepared by

  • Location
  • Personnel

1. OSHA, MCC General Requirements & Postings

  • A. Is a well stocked first aid cabinet on site?

  • B. Are Hazard Communication requirements in place?

  • C. Have all radios for entertainment including MP3, I-pods, and cell phones with music turned off during construction activities?

  • D. Are safety signs, MCC company signs, and emergency numbers posted?

  • E. Are the OSHA postings displayed?

  • F. Are the signs and barricades adequate?

  • G. Are safety documents current? (Safety Audits, Training Records, Site Specific Plan, etc.)

2. Personal Protective Equipment

  • A. Are employees wearing hardhats and eye protection?

  • B. Are employees wearing hearing, hand (gloves), and high vis protection when required?

  • C. Are employees wearing proper clothing and work boots?

  • D. Are employees compliant with respiratory procedures?

3. Fall Protection

  • A. Are employees using 100% fall protection when required (6ft)?

  • B. Are employees using fall protection properly?

  • C. Have employees been trained in fall protection?

  • D. Is the fall protection equipment in good condition?

  • E. Anchor points for Personal Fall Arrest Systems are minimal 5,000 pounds?

  • F. Warning lines are 6 feet from leading edges?

4. Sanitation

  • A. Are toilet facilities adequate and reasonably clean?

  • B. Are drinking containers placed into the trash?

5. Fire Protection

  • A. Have fire extinguishers been inspected and are personnel trained?

  • B. Is hot work permit completed?

  • C. Is there a fire extinguisher within 100 feet of all work areas?

  • D. Are fire extinguishers in good working order?

  • E. Is a fire extinguisher located at least 50 feet from all flammable or combustible liquids of 5 gallons or more?

  • F. Is a fire watch utilized correctly?

  • G. Are adequate "NO SMOKING" signs provided.

6. Ladders

  • A. Are the spreaders on step ladders locked?

  • B. Are ladders in good condition?

  • C. Do side rails extend 36" above landings?

  • D. Are extension or job made ladders secured properly?

  • E. Are doorways barricaded when ladders are set in front of them?

  • F. Are employees using ladders properly?

  • G. Are job made ladders built properly?

  • H. Is fall protection used when working on ladders closer than one and one-half (1-1/2) times the ladder height to an opening or edge of the building?

7. Housekeeping and Material Handling

  • A. Are isle-ways cleared of material debris?

  • B. Are items stacked low enough to prevent materials from falling?

  • C. Are nails removed from scrap lumber?

  • D. Are materials secured to prevent the wind from blowing?

  • E. Is trash and debris removed from work areas?

8. Tools

  • A. Are hazardous parts guarded?

  • B. Are employees trained to operate the tool correctly?

  • C. Are powder actuated shots stored and/or disposed of correctly?

9. Electrical

  • A. Are electrical cords in good condition and used correctly?

  • B. Are GFCI'S in good working order?

  • C. Are temporary lights properly suspended?

  • D. Are all electrical boxes, cords, receptacles, breakers, etc. being used for their intended use per NFPA, NEC, OSHA, and their UL rating?

  • E. Are all knock-outs blanked?

10. Welding & Cutting

  • A. Are all leads and stringers in good condition?

  • B. Is the first 10ft of welding leads free from repair?

  • C. Is proper eye and face protection being used?

  • D. Are all cylinders secure in an upright position and stored properly (20ft)?

  • E. Are fire prevention measures in place (hot work permit, fire watch, fire extinguishers, etc.)?

11. Scaffolds

  • A. Is fall protection provided for employees erecting or dismantling scaffolding?

  • B. Are scaffolds set on firm, secure footings with baseplates, and mud sills?

  • C. Are scaffolding components inspected (tagged) and are they in good condition?

  • D. Has the scaffold been tied off every 30ft in length and every 25ft in height? (Ties must be installed when the height of the scaffold is more than 4 times the minimum base width)

  • E. Are scaffold boards properly overlapped (12 inches max, 6 inches min) and maintained in good condition?

  • F. Are rolling scaffolds used correctly?

  • G. Is fall protection and falling object protection provided?

  • H. Have employees been trained in the hazards associated with scaffolds and scaffold work?

12. Excavations

  • A. Are employees protected from falling into excavations (piers, trenches, holes, etc.)?

  • B. Is a competent person present?

  • C. Are excavation that are 5ft or deeper properly sloped, benched, shielded or shored?

  • D. Are spoil piles placed a minimum of 2ft from the edge of an excavation?

  • E. Have utilities been located?

  • F. Have excavation of 20ft or more in depth been designed by a PE?

  • G. Is heavy equipment kept a safe distance from the edge of the excavation?

  • H. Has proper access and egress been provided?

13. Floor & Wall Openings, Stairwells & Roofs

  • A. Do all holes or perimeters that are 6ft or more above a lower level have guard rails or hole covers?<br>

  • B. Where there is a break in elevation of 19" or more, is a stairway or ladder provided at all personnel points of access?

  • C. Are 2" or more holes covers secured, marked (hole), or (cover) and are they capable of supporting intended loads?<br>

  • D. Are employees protected from falling objects?<br>

  • E. Are materials that are stacked higher than the toe boards kept at least 10' away from the toe board?

  • F. Are steel stair pan treads filled?

14. Structural

  • A. Is the bolt-up crew within 2 floors of the decking crew?

  • B. Has the steel been properly guyed and properly braced?

  • C. Are controlled access zones utilized correctly?

  • D. Is shoring installed properly and inspected?

  • E. Are all impalement hazards eliminated?

15. Cranes and Rigging

  • A. Are all inspections and paperwork updated?

  • B. Are the ANSI approved hand signals being used?

  • C. Is rigging in good condition and used correctly?

  • D. Is the entire swing radius barricaded?

  • E. Are riggers qualified?

  • F. Is the proper cribbing or matting being used?

  • G. Are cranes located a safe distance from power lines?

16. Aerial Lifts

  • A. Are employees using proper fall protection?

  • B. Are operators trained on aerial lift?

  • C. Is the gate or chain close closed when occupied?

  • D. Is total weight capacity of man basket maintained?

17. Mobile Equipment

  • A. Are operators trained on mobile equipment?

  • B. Are seat belts worn during operation of mobile equipment?

  • C. Are back up alarms working properly?

  • D. Are cell phones in use?

18. Miscellaneous

  • A. Are confined space procedures being followed?

  • B. Are Lock-out Tag-out procedures executed correctly?

  • C. Are all Environmental and Health hazards (mold, asbestos, lead, spill containment, etc.) eliminated or mitigated?

Corrective Actions

  • Enter corrective actions with completion dates.

Sign Off

  • Auditor's Signature

  • Project Manager's signature

  • Superintendent's Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.