Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Principal Contractor
-
Masterton is the principal Contractor as per the CDM REGs 2007.
Previous inspection signed off
-
Has the previous inspection points raised been signed off<br>
-
Actions outstanding are now
General site conditions
-
Is the site secure
-
Are work areas secure and have barriers to secure the work area from unauthorised access
-
Are the works areas clear of slip trip falls, debris, protruding nails.<br>
-
Is house keeping good, clean and tidy.
Plant and equipment
-
Plant and equipment on site has beacons and mirrors or reversing cameras
-
Excavators have quick hitch pins in place.
-
All driven plant was used correctly. Keys removed if not in use. Seat belts were worn. Parked or driven in a safe manner, in accordance with the traffic management plan.
-
Plant used for lifting has been connected correctly. SWL is clearly marked and is lifting within capacity.
-
Equipment being used is in sound condition and fit for purpose.
-
Unsafe actions.
Excavations
-
Excavations were shallow and did not pose a danger
-
Excavations were more than 1 meter and had barriers and were shored with edge protection.
-
Excavation more than 2 meters deep, had Shoreing in place edge protection and checked by a competent person at the start of each shift.
-
Excavation more than 3 meters deep. Had temporary works co-ordinator signed off. Edge protection in place. Signed off if open more than seven days.
-
Services are supported across open excavations
-
Excavations are not confined spaces requiring gas tests,training and rescue equipment
-
Unsafe actions.
Emergency arrangements
-
There were First aiders on site relative to the risk. First notice displayed and up to date.
-
There was fire fighting equipment on site. Fire assembly point was displayed. Smoke detectors in canteen, fire blanket in the canteen.
-
Fire risk assessment was in place.
Management procedures.
-
Site inductions and tool box talks have been completed for operatives on site.
-
Site registers, (blue book) is up to date and completed according to the CDM REGS 2007
-
Permits required for current works on site.
-
Copies of services are on site and service termination documentation in place
-
Certificates for plant were on site, including chains etc.
-
Training certificates were on site for operatives using plant and equipment.
-
Safety signs and poster including F10 where applicable
-
Management procedures are in place to reduce the risk of HAVS.<br>details recorded on HAV record sheet .
Environmental
-
Environmental procedures in place.
-
Spill kits and drip trays on site .
Personal Protective Equipment
-
All operatives on site were wearing Head Protection, in good order, the correct way round.
-
Operatives were observed wearing hearing protection correctly. They understood the requirement to wear them and dangers if not worn whilst working in noisy environment.
-
Operatives were observed wearing RPE. Correct type for the works. Face fit tested and clean shaven.
-
Safety googles or glasses were being worn for the correct operation.
-
Gloves fit for the task were worn. <br>Where mandatory requirement of the principal contractor.
Surface mounted and Underground Services
-
All services on site have been identified, drawings on site, area CAT scanned and ground marked.
Traffic Management
-
Traffic management plan is in place, displayed and being followed
Signatures.
-
Signed by site supervisor
-
Signed by Ian Straker - Safety, Health and Environment
-
Received by Contracts Manager
-
Time and date of inspection
-
Remedial action to be completed by
-
Add drawing