Title Page
-
Site conducted
-
Date/Time:
-
Client
-
Site:
-
HMS Contract # (5 digits):
-
Hoist Number (SRG Asset #):
-
Model #:
-
Serial #:
-
# Landings:
-
Platform SWL (kg):
-
Installed by:
-
Checked By:
HOIST BASE
-
1.1 Area under hoist is level, firm and stable ?
-
1.2 Are foundations sound to withstand the total mass of the hoist?
-
1.3 Area around the hoist base and loading ramp clear and free from obstructions?
-
1.4 Clearance between hoist and structure is 50mm-150mm maximum?
-
1.5 Driving pinion free from excess wear, has no missing teeth and is lubricated ?
-
1.6 Cable drum is secured and not in line-of-fire of hoist platform ?
PLATFORM
-
2.1 SWL displayed on hoist platform (Kgs)?
-
2.2 All stickers / signage on hoist platform clear, legible and in good condition ?
-
2.3 Manufacturer installed safety components and features present, functional and unmodified?
-
2.4 Platform guard railing as per manufacturer's specifications ?
-
2.5 Fold down ramps functional and secured adequately via the safety latch ?
MAST SECTIONS
-
3.1 Bolts joining mast sections are in place and secured ?
-
3.2 Rack on mast sections adequately lubricated ?
-
3.3 Teeth on rack in good condition / no teeth missing ?
BRACING / TIES
-
4.1 Bracing placed at intervals per the manual ?
-
4.2 Scaffolding tube and couplers used for hoist bracing / ties fit for purpose and adequately secured / tightened ?
-
4.3 Mast sections are vertically aligned after bracing and ties have been placed ?
-
4.4 Hoist supporting structure able to sustain the forces produced by the hoist and loads ?
-
4. No more than 4m of unsupported mast present at the top of the hoist ?
GENERAL
-
5.1 Client shown operating instructions and location ?
-
5.2 Client supplied with copy of hoist logbook ?
-
5.3 Emergency stops fitted, tested and operational ?
-
5.4 Hoist gates provided at all landings ?
-
5.5 Limit switches fitted and functional ?
-
5.6 Overspeed governor (emergency brake) fitted, tested and operational?
-
5.7 Safety interlocks fitted, tested and functional (where applicable) ?
-
5.8 Trailing cable guides fitted at intervals of not more than 6m ?
-
5.9 Trailing cable is spooling into drum correctly ?
-
5.10 Trailing cable free from cuts or damage and in good condition ?
-
5.11 Fault lights on control box tested and functional ?
-
5.12 Hoist pendent control tested and functional ?
-
5.13 Overload, brake, and drop tests conducted ?
-
5.14 Entire travel path of hoist platform has been test run to ensure there is no interference with supporting structure ?
-
5.15 Hoist electrical tag fitted and in date ?
-
5.16 Check to make sure that there is no access landings where the hoist car passes that there is the possibility of coming in contact with the hoist car or any moving parts?
COMMENTS
-
undefined
SIGNATORY
-
I hereby certify that I have examined and tested as appropriate the above mentioned equipment and I find that the equipment is in conformance with the relevant parts and sections of AS 1418 and AS 2550. I find that at the time of examination and tested the equipment is in satisfactory condition for safe use.
-
SRG Employee:
-
Client Representative: