Title Page

  • Site conducted

  • Plot Number

  • Conducted on

  • Prepared by

  • Name of 2nd fix engineer

Distribution board

  • Has the Distribution board been 2nd fixed, with all Busbar covers, blanks and board cover intact

  • Is the distribution board installed at the correct height- MCB's to be within 1350-1450mm FFL

Lighting

  • Are all lights installed as per RCP

  • Take Photo

  • Are the correct fittings installed as per locations i.e bathroom IP rated downlights if applicable

  • Take photo

  • Are all lighting left in a safe manner, that once tested can be put into service

  • Take Photo

  • has all functional switches been installed, and are level

  • Take Photo

  • Has the external lighting been installed where applicable

  • Add media

Power

  • All sockets and power accessories connected, fixed back against wall and level

  • Take Photo

  • are all service accessories connected in utility cupboard

  • Photo

  • Are all kitchen appliance accessories connected, and correct type I.E unswitched socket, flex outlet etc .

  • Take Photo

  • all Kitchen above work top finished accessories connected to enable testing where unable to fit final accessories due to tiles/splashback etc

  • Take Photo

ELV

  • Has the door entry unit beed installed?

  • Take Photo

  • Has the data plate been installed in utility cupboard with a correct accessories I.E master RJ11 and RJ45

  • Take Photo

  • Has secondary RJ11 and where applicable RJ45 been installed in media plate and other locations

  • Take Photo

  • Has Quadplexor TV plate, and IEC return where applicable been installed in media plate, and TV point been installed in all bedrooms where applicable

  • Take Photo

Smoke detectors

  • has all heat and smoke detectors been installed with commissioning bags

  • Take Photo

  • Has the relay base and external sounder been fitted where applicable

  • Take Photo

Towel Rails/ Shavers/Thermostats

  • Has all thermostats been installed as per current drawing revision?

  • Take Photo

  • Has all flex outlets been installed for the towel rails where applicable and able to at 2nd fix stage or made safe

  • Take Photo

  • Has the shaver sockets been fitted where can at 2nd fix stage or been made safe

  • Take Photo

  • Any holes been made due to cables being brought out incorrect location by others take pictures

Testing

  • Has dead testing been completed with no faults found

  • Picture of damages

Sign off

  • add photos of the finished plot

  • Add date of completion of 2nd fix

  • Please sign as complete

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.