External Surfaced Areas / Roof Area defects
-
Yard surface
-
Yard making
-
Gates
-
Exit / Em Exit doors clear and opertional
-
Roof area clear
Building Exterior / Interior defects
-
Glazing
-
Cladding / Walls
-
Flooring
-
Entrance lobby
-
Stairs risers
Toilets
-
Flooring walls and fixtures
Floor lift lobbies
-
Flooring walls fixtures
PPM Inspections
-
Em lighting monthly inspection and recorded within site file
-
Lighting all areas <br>All sales floors <br>backstage<br>carparks<br>plant rooms
-
Disabled toilet alarm
-
5 yearly electrical inspection up to date
-
Fuel and heating pumps
-
Water temps as per L8 report book
-
Heating valves 3-12 Monthly
-
Grilles and diffusers
-
Fans ventilation make sure all are operational
-
AC units all serviced and operational
-
Pumps
-
Elec D/Boards
-
Em lighting annual inspection
-
Heating pipe work within plant rooms
-
AHU filters all clean
-
Fire alarm associated equipment - fire doors
-
Cold water storage tanks and cisterns all operational
-
RCD inspection all rcds tested and operational and recorded on test sheets
-
PAT testing
-
Smoke vent Mall area all operational
-
Smoke vents car parks all operational
-
Over door heatings
-
Gantry system operational
-
Gas boilers serviced and operational<br>
-
Sprinkler system all tests are complete
-
Auto doors and shutters all operational and PPM's up to date
-
Fire alarm system clear of faults and PPM inspections up to date
-
Compactor & Baler emergency stops all working and PPM services up to date
-
Generator testing complete and all recorded
Plant Rooms
-
Plant rooms all clear and locked
-
All lighting operational
Comments or other issues
-
\ -