Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
General
-
Subcontractors inducted
-
New employees inducted
-
PMP/Standard drawing file on site
-
Emergency numbers displayed
-
Safe work procedures followed
-
Job diary page & records filled out
-
"As Constructed" information up to date
-
"Inspection and Test Plan" up to date
Amenities
-
Compound secure and safe
-
Good house keeping compound & site
-
Toilet clean and in good condition
-
Amenities adequate for project
-
Container & tool store satisfactory
First Aid
-
First aid kit & facilities on site
-
First aid officer nominated
-
First aid injuries since last audit (name, date & injury details)
Personal Protection Equipment
-
Hearing protection available
-
Safety footwear being worn
-
Helmets worn
-
Safety jackets worn
-
Eye and sun protection available
Excavation / Pipe Laying
-
Relevant permits to work obtained
-
Trenching / pipe laying practice ok
-
Ground support for excavations > 1.5m deep
-
Mine manager onsite & nominated
-
Workcover notified > 1.5m
-
Lookout on top at all times
-
Barricade in place for open trench
-
Materials stored correctly
-
Defect materials isolated
-
Material record sheet filled out
Plant and Equipment
-
Waste oil and other waste collected
-
Daily plant inspections and fault reports completed all plants
-
Subcontractors plant in good condition and inspected daily
-
All operators competency tested
-
Vehicles parked to reduce impact on road users and pedestrians
-
Electric leads and tools in good condition and tagged
-
Power & hand tools in good condition
-
Lifting equipment in good condition
Site Safety
-
Hazard analysis in PMP being used
-
Warning signs and other traffic signs are displayed in public places as per TMP
-
Toolbox meeting held. Records kept on site
-
Inspect for dangerous goods
-
Applicable MSDS onsite
-
Work practices inspected for potential hazards with workers
-
Warning signs stacked and clean
-
Existing services located
-
Appropriate lighting for night work
-
Inspect for other hazards
Environmental
-
Env. analysis in PMP being used
-
Inspect for extra Env. hazard
-
Erosion control arranged
-
Sedimentation control arranged
-
Clearing works limited to site only
-
Control measures monitored
Sign Off
-
General comments:
-
Defect/Suggestion report form and copy of report given to safety coordinator: Yes/No............
-
Signed (Inspection officer)
-
MFJ Constructions (Vic.) Pty. Ltd. Issue 6, 16 October 2017. MFJ-Form 03-01